midas Gen
Advanced Webinar
Column Shortening for High-rise Building
03 11 14 19 24
03 11 14 19 24
Column Shortening
Introduction
Wind
Earthquake
Completed structure
Construction Sequence
4
Column Shortening
Introduction
8,000 4,500
9,000 4,500
8,000
9,400 9,400
9,400
3,800
1,800
3,800
Column Shortening
Introduction
Steel
Concrete
19.6 19.6
Column Shortening
Introduction
Nonstructural Effect
Structural Effect
Column Shortening
Introduction
Pre-slab installation shortenings Shortenings of supports that take place up to the time of slab installation Post-slab installation shortenings Shortenings of supports that take place after the time of slab installation
:Compensation
: Design Level
Column Shortening
Introduction
Reinforced Concrete Structure Pre-slab installation shortenings has no importance Compensation by leveling the forms Post-slab installation shortenings due to subsequent loads and creep/shrinkage
Steel Structure Columns are fabricated to exact length. Attachments to support the slabs Pre-slab installation shortenings need to be known. Compensation for the summation of Pre-installation and Post-installation shortenings
Column Shortening
Introduction
Application in field
Material Experiment
Compressive strength Modulus of elasticity Creep & Shrinkage
10
Project Applications
03 11 14 19 24
11
Column Shortening
Project Applications
Height No. of floors Location Function / Usage Designer Architect General Contractor
705 m 160 Dubai, United Arab Emirates Office Building & Residential Building Adrian D. Smith Skidmore, Owings & Merrill Samsung Development 12
overview
Column Shortening
Project Applications
Area No. of floors Location Function / Usage Structure Type Foundation Type Lateral load resisting system
39,600m2 36 Seoul, Korea Office Building Composite Structure Mat Foundation RC Core + Steel + RC Composite Frame 13
overview
03 11 14 19 24
14
Column Shortening
Define materials, sections Assign elements, boundaries, & loads to the groups
Perform an analysis
Specify the duration of CS Activate/Deactivate element groups / Activate/Deactivate boundary groups/ load groups
15
Column Shortening
Construction Stage
Creep/Shrinkage - Eurocode, ACI, CEB-FIP, PCA, India Comp. Strength - Eurocode, ACI, CEB-FIP, Ohzagi , India
16
Column Shortening
0 day
10 day
20 day
30 day
40 day
Activation or Deactivation of load with time span from the stage start
17
Column Shortening
Analysis results can be checked for each construction stage. Absolute minimum or maximum results of envelope can be also checked among entire construction stages. Results for creep and shrinkage effect are provided.
CS1
CS10
Min/Max
CS3
CS12
CS6
18
03 11 14 19 24
19
Column Shortening
The wizard readily allows us to define the timing of elements created and loadings applied in the
20
Column Shortening
Define an analytical model for each construction stage by assigning activated or inactivated sections
21
Column Shortening
Construction stage for auto climbing formwork system (ACS) can be generated in midas Gen.
22
Column Shortening
Tendon Loss
Pre-stress load can be considered in construction stage analysis. Tendon primary / secondary forces are provided with pre-stress loss graph.
23
Demonstration
03 11 14 19 24
24
Design Procedure
Demonstration
Example model
5m
2@4.5=9m
9@4=36m 50m
25
Design Procedure
Demonstration
Section size
400x700 400x700 600x800 500x800 400x700 600x800
Column
Story 10~12 8~9 6~7 4~5 2~3 1 C1 600x600 800x800 800x1000 1000x1000 1000x1200 1000x1300 C1A 500x600 500x600 500x600 600x600 700x700 700x700
Wall
Design Procedure
Demonstration
Construction Schedule
3 levels of shoring Construction cycle time=7 days Time of removal of lowest level of shores from concreting of top floor=5 days
Age
0 Age 0 5 7
27
Design Procedure
Demonstration
Construction Schedule
Age Age 0 5 12 7 14 5 12
0
7 14 21
5 12 19
19
26
3F Formwork Installation
3F Concrete Casting
4F Concrete Casting
15th day
17th day
22th day
24th day
29th day
28
Design Procedure
Demonstration
Construction Schedule
Date 1 3 8 10 Work 1F Formwork Installation 1F Concrete Casting 2F Formwork Installation 2F Concrete Casting 2F 2F Formwork Removal Formwork Installation 1F 1F Conc. Casting Stage Definition Program Date Stage Duration
15
17 22 24 29 31
3F Formwork Installation
3F Concrete Casting 1F Formwork Removal, 4F Formwork Installation 4F Concrete Casting 2F Formwork Removal, 5F Formwork Installation 5F Concrete Casting 2F 1F
3F
3F 4F 1
stage 1
4F 5F stage 2 5F 10 3 8
36
38 43 45
3F
6F
stage 3 6F
15
7 17 22 stage 4 7F 24 7
4F
7F
29
Design Procedure
Demonstration
Construction Schedule
Date 50 52 57 59 64 66 71 73 78 80 85 92 95 98 99 101 133 Work 5F Formwork Removal, 8F Formwork Installation 8F Concrete Casting 6F Formwork Removal, 9F Formwork Installation 9F Concrete Casting 7F Formwork Removal, 10F Formwork Installation 10F Concrete Casting 8F Formwork Removal, 11F Formwork Installation 11F Concrete Casting 9F Formwork Removal, 12F Formwork Installation 12F Concrete Casting 10F Formwork Removal 11F Formwork Removal, 1~3F SDL 4~6F SDL 7~9F SDL 12F Formwork Removal 10~12F SDL Live Load 12F stage 12 dummy 10F 11F stage 11 9F 12F 12F 8F 11F 11F 7F 10F 10F 6F 9F 9F
Formwork Removal Formwork Installation Conc. Casting Stage Definition Program Date Stage Duration
5F
8F 8F
stage 5
29 31 36 38 43 45 50 52 57 59 64 71 74 77 78 80 112
stage 6
stage 7
stage 8
stage 9 stage 10
7 7
7 28 30
Thank You!
One Stop Solution for Building and General Structures
http://en.midasuser.com/ esupport@midasuser.com