Reaction Turbine
Impulse Turbine
1.HEAD (H)
2.DISCHARGE(Q)
HEAD
Gross Head (Hg) It is the difference in elevation between the water levels of the forebay and tail race (for Reaction Turbine) or Centre Line of Runner( For Impulse Turbine). Net Head(Hn) It is the gross head less all hydraulic losses except those chargeable to the turbine. Net head is the head available for doing work on the turbine.
HEAD
Maximum Net Head (Hmax) - It is the gross head resulting from the difference in elevation between the maximum forebay level and the tail race level (Reaction Turbine) or Centre Line of Runner for Impulse Turbine without spillway discharge and with one unit operating at no load speed. Under this condition , Hydraulic losses are negligible and may be neglected. Minimum Net Head (Hmin) It is the net head resulting from the difference in elevation between the minimum forbay level and the tail race level with all turbine operating at full gate
HEAD
Rated Head (Hr) - It is the head of which the specifications require that the turbine operating at full gate shall produce sufficient power to deliver the name plate power output. It is the 2/3rd of the difference between FRL and MDDL above the MDDL. Basically it is assumed that the volume of water above this level is same as below this level as the shape of pondage goes on decreasing. So the probability of this head to available is more .
Design Head (Hd) It is the net head under which the turbine reaches its peak efficiency at synchronous speed; Usually it is specified as =Hd=Min. Net Head+(2/3)*(Max. Net Head-Min. Net Head). This is the head which determines the basic dimensions of the turbine and therefore of the power plant. For optimum operation benefits the Design Head &Rated Head are kept same.
Discharge (Q)-It is the rate of volume of water coming to turbine. It depends on catchments
As per USBR
Specific Speed
Specific Speed: Specific Speed is a typical characteristic where all runners of a given specific speed are similar in form and vary only in size. This Speed form the basis of Classification of Turbines. It can be defined as the speed of a homologous turbine of such a size that it would develop unit power at unit head. Ns =(N x (P)^0.5) / Hd^(5/4) Where Ns= Specific Speed in rpm N = Unit Speed in rpm Hd= Design Head in Meters P = Rated Power .
4.Site characteristics:-Type of rock available and depth up to which the rock is available. 5.Type of Plant:-Peak Load Plant or Base Load Plant 6.Water Quality (silt):-If the turbine lies in the overlapping zone of Francis and Pelton the silt criteria needs to be seriously considered. 7.Cost:-The minimum cost is preferred taking into view above factors also. 8.Manufacturing Difficulty:-That turbine cant be taken which is very typical to make. 9. Cavitations:-The installation of reaction turbine over Impulse turbine is affected by the cavitation. 10.Maintainence:-The turbine selected should be also easy to maintain. Pelton is easy in maintenance as compared to Francis Turbine. 11.Time out of operation:- The case of repair is normally related to sand erosion.
Pelton Turbine
Francis Turbine
Kaplan Turbine
Turbine selection on the basis of discharge & head (by VA Tech Hydro)
Axial Turbine
Bulb Turbine
Efficiency of various turbine of our projects Malana-II 50X2 MW Type of turbine As per contract As per actual Field test Pelton 91.4 Not yet Sainj 2X2.5 MW Francis 91 92 Patikari 8X2 MW Pelton 93 89.04 Teesta-III 200X6 MW Pelton 92.2 Not yet
Conflicts between Pelton & Francis When the head is between 150 & 250m
1. Discharge :-If this is high Francis is preferred 2. Efficiency:-The efficiency of Francis is more at full load around 96% while Pelton around 90%. 3. Time out of operation:-Dismantling and assembly of the sand eroded parts takes shorter time for Pelton than for Francis turbines. Therefore Pelton turbines will normally be preferred where much sand erosion is expected. However, this again depends rather strongly on the plants operation schedule.
As per USBR
If one or more turbines are stopped for a long period of for example two months a year, Francis turbines may be chosen even if the water has a high sand content because there will be enough time for an annual repair. 4.Site Characteristics:-Installation cost in case of Francis Turbine also increased when the rock available is at very high depth. So we have to excavate up to that depth and even concrete up to required level. So additional excavation cost and concreting cost comes into picture
As per USBR
6.Cost comparison
5.Operation under part load
The cost of machine decreases as the speed increases
As per USBR
As per USBR
3. The upper economic and practical limit for the Kaplan turbine head is in the range of 60m, though extreme cases of 70 - 75 m have been planned for this turbine type as well. The head limit is caused by mechanical strength problems in hub and blades.
3.Size of Power House:-The Bulb turbine is still more favourable if only one unit shall be built because the scroll casing of a Kaplan turbine makes the power station much wider. The Bulb turbine will however, reach an upper limit design head because of the concentrated hydraulic load on the concrete foundation through the ribs. Thus the pressure will be limited to 15 - 20 m head for this turbine type.
Classification of Turbines
Type of machine Head variation Percent of rated head Load variation percent of rated output Specific Speed m-mhp Peak efficiency
Pelton
Francis Deriaz Kaplan Propeller Bulb
120 to 80
125 to 65 125 to 65 125 to 65 110 to 90 125 to 65
50 to 100
50 to 100 50 to 100 40 to 100 90 to 100 40 to 100
15 to 65
60 to 400 200 to 400 300 to 800 300 to 800 600 to 1200
90
93 92 92 92 92
As pert IS 12800, The overall dimensions of Power house mainly depend upon the following: 1. Overall dimension of the turbine, draft tube and scroll case; 2. Overall dimensions of the generator; 3. Number of Units in the power house; and 4. Size of erection bay
Note: Provision for inlet valve, erection of rotor and un-tanking of transformers should be made in such a way that space required is minimum without impairing the operational and maintenance requirements.
1.
2. 3.
It depends upon the Unit Spacing Length of erection bay Length required for the EOT Crane to handle the last unit
1.Unit Spacing(Us)
Inner diameter of the generator barrel is determined as per the norms and outer diameter of the barrel is taken as 0.5 to 1.5m more depending upon the size of machine.
As per Std. Malana II 8400mm As per Std. =10500 11500mm Teesta III 12000mm
79008900mm
A clearance of 1.5 to 2m shall be added on either side of the extremities of the generator barrel. These clearance should be such that concrete thickness on either side of scroll case should be 1 to 1.5m in case of fully embedded steel scroll case. Usually spacing with scroll/spiral case clearance is more and will be basis.
As per Std. Malana II
12183mm
As per Std.
-
Teesta III
16484mm
Us
1418315183
18484-19484 24000mm
Malana II HEP
A)Length of service bay Ls : 1.5times Us B)Length required for EOT crane to handle the last unit k : 3 to 5 m C)Length of Control Block Lcb C)Length of Power House:
As per Std.
19484 =1.5x19484 =29226
Teesta III
24000mm 48000mm 18950mm 214300mm
Malana II HEP
On the upstream side provision should be made for the following: a)A clearance of about 1.5 to 2 m for concrete the upstream of scroll case b)In case the main inlet valve is also accommodated in the power house, a valve pit of approachable size should have to be provided as per IS 7326(Part 1) and IS 7332(part 1)
As per Std Malana II As per Std. Teesta III
4534, 5183
1200 =2.6x1200 =3120 =9654 =7183 =16837
4376, 6373
1300 5126 =9400 =8100 =17500
5828, 6477
1900 =2.6x1900 =4940 =12768 =9977 =22745
8330, 8375
1900 5890 11500 =10000 =21500
c)The spaces as indicated against item(a) are supposed to be sufficient for accommodating the auxiliary equipment also but may have to be reviewed considering the layout of essential equipment and operational requirements.
Malana II HEP
Malana II HEP
Height coefficient
K3 = 0.65 or 0.75 or 0.85 Hj =K3 x sqrt of Df (for Suspension) and K3 X sqrt of (Di for umbrella)
H2 =Hj+Lf+6.75
H =H1 + H2
around 7 to 8.5
Hook allowance
around 4 to 6.5 m
Allowance below roof over EOT :0.5m Total Height of the Power House
Ht= H + ht of service bay+ ht Of unloading largest package + crane ht & hook allowance + allowance below roof over EOT + margin
As per Std. Height coefficient k Height of Load bearing bracket Hj Core Length Lc Length of stator frame Lf Distance between centre line of turbine and machine hall floor 0.75 =kxsqrt(Df) =1320 =1290 =Lc+1600 =2890 =Hj+Lf+6000 =10110
As per Std.
As per Std. Pelton wheel dimensions Wheel pitch diameter D2 Jet dia Outer wheel diamter Number of Buckets (Approximate)
Malana II
As per Std.
Teesta III
2330 229.4
3020 318
20
21
21
Suction head Hs To avoid discharge water Hs>4*H1 splash =2145>2400 CL of Turbine wheel is set above TWL 2400
3442
3407
3442 4200
4000
Malana II HEP