5CE-A
SUMMARY
Petitioner COORDINATED GROUP, INC. (CGI) is a corporation engaged in the construction business, with petitioner: spouses ROBERTO and EVELYN DAVID as its President and Treasurer, respectively. Respondents spouses NARCISO and AIDA QUIAMBAO engaged the services of petitioner CGI to design and construct a five-storey concrete office/residential building on their land in Tondo, Manila
Design/Build Contract:
a) CGI shall prepare the working drawings for the construction project b) Respondents shall pay petitioner CGI the sum of P7,309,821.51 for the construction of the building, including the costs of labor, materials and equipment, and P200,000.00 for the cost of the design c) Construction of the building shall be completed within 9 months after securing the building permit
Petitioners ,CGI, failed to follow the specifications and plans Respondents demanded the correction of the errors but petitioners failed to act on their complaint
rescinded the contract on October 31, 1998 paying 74.84% of the cost of construction
Respondents filed a case for breach of contract against petitioners before the Regional Trial Court (RTC) of Manila
Pre-trial Conference
parties agreed to submit the case for arbitration to the CONSTRUCTION INDUSTRY ARBITRATION COMMISSION (CIAC)
After conducting hearings and two (2) ocular inspections of the construction site, the arbitrator rendered judgment against Petitioners
Professional fees for geodetic surveys, etc P 72,500 Professional fees for engineers P 118,642.50
P 15,247.68
P 100,000 P 250,000 P 250,000 P 4,884,418.89
Summary of Awards
CGI ordered to pay P 4,073,229.94 with interest at 6% per annum from the date of the promulgation of this award
P 5,275,041
P 4,884,418.89 P 10,159,459.89
80% accomplishment
Costs of materials and equipment TOTAL
P 5,847,857.20
P 238,372.75 P 6,086,299.95
b) 3 additional concrete columns were constructed from the ground floor to the roof deck
affected the overall dimension of the building
1 instead of 2 windows at the fire exit absence of water-proofing along the basement wall and at roof deck use of smaller diagonal steel trusses at the penthouse
Site inspection
L-shaped kitchen counters instead of the required U-shaped counters failure to provide marble tops for the kitchen counters
installation of single-tub sinks where the plans called for double-type stainless kitchen sinks installation of much smaller windows than those required misaligned window easements to wall floors were damaged by roof leaks
Concrete samples
Basement, ground floor, mezzanine and 2nd floor Subjected to concrete core test 5 out of 9 samples failed the test
Question of Fact
It is contended that petitioner-spouses David cannot be held jointly and severally liable with petitioner CGI in the payment of the arbitral award as they are merely its corporate officers.
The rights of any party have been materially prejudiced The arbitrators exceeded their powers or imperfectly executed them
ANALYSIS
The decision, favoring the Quiambaos, made by the Court of Appeals was right.
Breaching of contract
2 concrete in the middle of the basement 3 addtl column from the ground to roof deck 5 of 9 core samples failed 8 of 18 steel samples failed on physical test
Punchlist
ANALYSIS
No relocation survey Cistern issues
Actual capacity was less than the designed capacity No internal partition separating cistern from sump pit
RECOMMENDATIONS
Communication Regular inspection of the Owner to the construction Always document changes of the project