Anda di halaman 1dari 62

Placing and Finishing Concrete

Basic Requirements for Placing Concrete (1)

Preserve concrete quality


Water-cement ratio Slump Air-content Homogeneity

Avoid separation of aggregate and mortar

Placing and Finishing Concrete

Basic Requirements for Placing Concrete (2)

Avoid excessive horizontal movement Consolidate adequately Maintain sufficient placement capacity Choose the right equipment for the concrete

Placing and Finishing Concrete

Preparation Before Placing Includes:

Trimming the subgrade

Placing and Finishing Concrete

Preparation Before Placing Includes:

Moistening the subgrade

Placing and Finishing Concrete

Preparation Before Placing Includes:

Compacting the subgrade

Placing and Finishing Concrete

Depositing Concrete

DO NOT (a) disturb saturated subgrades so bearing capacity is maintained (b) deposit on frozen subgrade
Deposit continuously and as near as possible to its final position

Placing and Finishing Concrete

Rate of placement should be such that previously placed concrete has not set when the next layer is placed upon it

Depositing Concrete
Slab Construction

Start placing along perimeter at one end with each batch discharged against previously placed concrete Do not (a) dump in separate piles & then level and work together (b) deposit in large piles & then move horizontally into position

These practices result in segregation


Placing and Finishing Concrete (mortar flows ahead of coarser material)

Depositing Concrete
Effective use of wheelbarrows

Placing and Finishing Concrete

Discharging into previously placed concrete

Incorrect Placement with Conveyor Belt


Baffle

Mortar

Rock

Mortar

Shallow hopper Rock

Mortar

Placing and Finishing Concrete

Placement with Conveyor Belt

Provide at least 0.6 m (24 in.) headroom for downpipe, elephant trunk or equivalent

Belt Scraper

No Separation

Placing and Finishing Concrete

Depositing Concrete
Pavement Slab

Concrete deposited in front of slip form paver by dump trucks Concrete spread evenly across the subgrade by the paver before consolidation and finishing

Placing and Finishing Concrete

Depositing Concrete
Curb/Curb and Gutter

Concrete deposited into hopper of slip form curb and gutter machine which then extrudes the concrete into the desired shape

Placing and Finishing Concrete

Depositing Concrete
Walls

Deposit in horizontal layers of uniform thickness

Reinforced 150 mm to 500 mm Mass 375 mm to 500 mm

Consolidate each layer before next is placed Timely placement & consolidation prevents flow lines and cold joints

Placing and Finishing Concrete

Horizontal Construction Joint

Placing and Finishing Concrete

Horizontal Construction Joints

Placing and Finishing Concrete

Underwater Placement Methods

Tremie Pump Bottom dump buckets Grouted preplaced aggregate (specialized) Toggle bags Bagwork Diving bell

Placing and Finishing Concrete

Placing Concrete Under Water


Basic Recommendations

Water velocity 3 m (10 ft) / min. Water temperature 5C (if below test for strength gain) w/c 0.45 Cementing materials content 390 kg/m3 (600 lb/yd3) Slump range 150 to 225 mm (6 to 10 in.)

Placing and Finishing Concrete

Placing Concrete Underwater

Used: Tremie Advantages: Can be used to funnel concrete down through the water into the structure. Watch for: Discharge end always has to be buried in fresh concrete to ensure seal between water and concrete mass.

Placing and Finishing Concrete

Consolidating Concrete

Internal Vibration External Vibration

Placing and Finishing Concrete

Internal Vibration
Vibrator
d

1 R

Placing and Finishing Concrete

Radius of Action

Internal Vibrators
Recommended Approximate Rate of Diameter frequency, radius of placement, of head, vibrations per action, mm m3/h mm (in.) minute (in.) (yd3/h) 20-40 (3/4-1) 9000-15,000 80-150 (3-6) 0.8-4 (1-5) Application Plastic and flowing concrete in thin members. Also used for lab test specimens. Plastic concrete in thin walls, columns, beams, precast piles, thin slabs, and along construction joints. Stiff plastic concrete (less than 80-mm [3in.] slump) in general construction .

30-60 (1-2)

8500-12,500

130-250 (5-10)

2.3-8 (3-10)

Placing and Finishing Concrete

50-90 (2-3)

8000-12,000

180-360 (7-14)

4.6-15 (6-20)

Adapted from ACI 309

Systematic Vibration of Each New Lift


CORRECT
Vertical penetration a few inches into previous lift (which should not yet be rigid) of systematic regular intervals will give adequate consolidation

INCORRECT
Haphazard random penetration of the vibrator at all angles and spacings without sufficient depth will not assure intimate combination of the two layers

Placing and Finishing Concrete

Placing Concrete in a Sloping Lift


CORRECT
Start placing at bottom of slope so that compaction is increased by weight of newly added concrete. Vibration consolidates the concrete.

INCORRECT
When placing is begun at top of slope the upper concrete tends to pull apart especially when vibrated below as this starts flow and removes from concrete above.

Placing and Finishing Concrete

External Vibration

Form vibrators Vibrating tables Surface vibrators


Vibratory screeds Plate vibrators Vibratory roller screeds Vibratory hand floats or trowels

Placing and Finishing Concrete

Consolidating Concrete
Inadequate consolidation can result in:
Honeycomb Excessive amount of entrapped air voids (bugholes) Sand streaks Cold joints Placement lines Subsidence cracking

Placing and Finishing Concrete

Nuclear Gauges to Determine Subbase Compaction

Placing and Finishing Concrete

Screeding (Strikeoff)
The process of cutting off excess concrete to bring the top surface of a slab to proper grade

Placing and Finishing Concrete

Vibratory Screeds

Placing and Finishing Concrete

Bullfloating

Placing and Finishing Concrete

Darbying

Placing and Finishing Concrete

Edging
Edging densifies and compacts concrete next to forms where floating is less effective

Required along all edge forms, isolation and construction joints in floors and exterior slabs Cut concrete away from forms to a depth of 25 mm with a pointed mason or margin trowel Edging may be required after each subsequent finishing operation for interior slabs

Placing and Finishing Concrete

Highway Straightedges

Placing and Finishing Concrete

Floating (Power or Hand)

To embed aggregate particles just beneath the surface To remove slight imperfections, humps, and voids To compact the mortar at the surface in preparation for additional finishing operations.

Placing and Finishing Concrete

Troweling

Creates smooth, hard,dense surface Exterior concrete should not be troweled because:
it can lead to a loss of entrained air caused by overworking the surface troweled surfaces can be slippery when wet.

Placing and Finishing Concrete

Brooming

Placing and Finishing Concrete

Tining

Placing and Finishing Concrete

Curing and Protection

Placing and Finishing Concrete

Cure for 7 days

Placing on Hardened Concrete


Preparing Hardened Concrete

Placing and Finishing Concrete

Bonding New to Previously Hardened Concrete


Cement-sand grout Latex Epoxy

Placing and Finishing Concrete

Isolation Joints

Placing and Finishing Concrete

Contraction Joints

Placing and Finishing Concrete

Spacing of Contraction Joints in Meters


Slab thickness, mm 100 Maximum-size aggregate less than 19 mm 2.4 Maximum-size aggregate 19 mm and larger 3.0

125 150 175 200 225 250


Placing and Finishing Concrete

3.0 3.75 4.25 5.0 5.5 6.0

3.75 4.5 5.25 6.0 6.75 7.5 Metric

Spacing of Contraction Joints in Feet


Slab thickness, in. 4 5 6 7 8

9 10
Placing and Finishing Concrete

Maximum-size aggregate less than in. 8 10 12 14 16 18 20

Maximum-size aggregate in. and larger 10 13 15 18 20 23 25 Inch-Pound

Making Contraction Joints


Grooving tool on bull-float

Placing and Finishing Concrete

Dry-cut sawing concrete

Construction Joints

Placing and Finishing Concrete

Joint Layout for Slabs


Basic Factors to Remember

Placing and Finishing Concrete

Panels created by contraction joints should be approximately square Panel aspect ratio max. 1 to 1 Contraction (control) joints should only terminate at a free edge or at an isolation joint When joint spacing exceeds 4.5 m (15 ft), load transfer by aggregate interlock decreases significantly

Typical Joint Layout

Placing and Finishing Concrete

Finishing Operations
Single Course Floors

Consolidation Strike-off Edging Darbying or Bull Floating


Lapse of Time

Edging Grooving (if desired) Floating (power or hand) Troweling (power or hand)
Lapse of Time

Placing and Finishing Concrete

Second Troweling (power or hand) Final Troweling (hand) Curing

Finishing Operations - Exterior Slabs


Sidewalks, Driveways etc.

Consolidation Strike-off Depress aggregate with metal/wood strip at joint location if hand tooled Darbying or Bull floating
Lapse of time

Edging Jointing (optional if hand tooled) Floating


Lapse of time

Placing and Finishing Concrete

Texturing (brooming/swirl float finish) Curing

Patching

Placing and Finishing Concrete

Curing Patches

Placing and Finishing Concrete

Cleaning Concrete Surfaces

Cleaning methods:

Water Chemical

Mechanical

Placing and Finishing Concrete

Finishing Formed Surfaces


Rough-form finishes
Smooth off-the-form finish Smooth, rubbed finish Sand-floated finish Grout cleandown (sack-rubbed finish)

Placing and Finishing Concrete

Special Surface Finishes


Pattern and Textures Exposed Aggregate Concrete Colored Finishes Stains, Paints and Clear Coatings

Placing and Finishing Concrete

Placing and Finishing Concrete

Working Safely with Concrete


Protect:

Your Eyes Your Back

Your Skin

Placing and Finishing Concrete

Precautions
WARNING: Contact with wet (unhardened) concrete, mortar, cement, or cement mixtures can cause SKIN IRRITATION, SEVERE CHEMICAL BURNS (THIRD-DEGREE), or SERIOUS EYE DAMAGE. Frequent exposure may be associated with irritant and/or allergic contact dermatitis. Wear water-proof gloves, a long-sleeved shirt, full-length trousers, and proper eye protection when working with these materials. If you have to stand in wet concrete, use waterproof boots that are high enough to keep concrete from flowing into them. Wash wet concrete, mortar, cement, or cement mixtures from your skin immediately. Flush eyes with clean water immediately after contact. In-direct contact through clothing can be as serious as direct contact, so promptly rinse out wet concrete, mortar, cement, or cement mixtures from clothing. Seek immediate medical attention if you have persistent or severe discomfort.

Placing and Finishing Concrete

http://www.cement.org/pdf_files/ms271.pdf

Videos 1/4

Placing and Consolidating Placing and Finishing Concrete

Vibration

Videos 2/4

Finishing I Placing and Finishing Concrete

Finishing II

Videos 3/4

Contraction Joints Placing and Finishing Concrete

Jointing

Videos 4/4

Improper Finishing Placing and Finishing Concrete

Anda mungkin juga menyukai