Quality
Performance Objectives
WBS EXAMPLE (D
Canoe Trip to Boundary Waters
WIGHT
FISCHER)
Arrange Travel
Get Equipment
Plan Meals
Prepare Budget
Plan Activities
Obtain emerg. #s
Bring Cards
Rent Van
Rent canoes
Get deposits
Arrange contact at BW
Arrange Motel
Rent Tents
Prepare 7 breakfasts
Retain Receipts
Bring scotch
Prepare 7 lunches
Prepare 6 dinners
Close-out trip
SELECTING PROJECTS
Limited resources means not all projects can be undertaken Factors for selecting projects:
GANTT CHARTS
Used to schedule and monitor project activities Lists project activities, estimates of activity time length, and sequence of activities
Rewards associated with being part of successful project Thrill of working on different/unusual tasks and solving new problems Opportunities to meet new contacts & increase future job opportunities
Cons
Managers dont want to lose good workers to projects Disruption of daily routine Risk of being replaced on current job Fear of association with unsuccessful project
WHAT IS PERT?
Project Evaluation and Review Technique Developed in 1958 by Navy Used in the POLARIS missile program Helps forecast project completion date
1) How does the cost of work performed compare to the value of the work performed? 2) What is the value (in dollars) of work performed so far? 3) How does the amount of money spent so far on a project compare to what should have been spent?
PERT
PERT - a management tool for defining and integrating events; a process which must be accomplished in time to assure completing project objectives on schedule.
PERT
Objectives:
To provide, through applying an integrated management information system (which contains a balanced combination of the basic elements of time, cost, and performance) coordinate planning and control information at the proper levels so that timely managerial judgments will meet all established project objectives.
PERT NETWORK
Events may be represented in a PERT network by any selected geometric figure (ovals, circles, squares). The events must follow logically.
The arrows indicate the flow in the PERT network and the numbers identify the events. The arrows and not the #s indicate the order of events. Events that immediately follow one another are called successor events. Similarly, a predecessor event is one which immediately precedes another event.
PERT NETWORK
Key features of a PERT network are: 1) Events must take place in a logical order. 2) Activities represent the time and the work it takes to get from one event to another. 3) No event can be considered reached until ALL activities leading to the event are completed. 4) No activity may be begun until the event preceding it has been reached.
STEPS:
Step 1: *Define tasks Step 2: *Place tasks in a logical order, find the critical path
Critical path- longest time path through the task network which dictate finish date
Step 3: Generate estimates Step 4: Determine earliest and latest dates Step 5: Determine probability of meeting expected date
Use logic.*
SD=(TP-T0)/6
Calculate variance
V=SD2
a large variance indicates great uncertainty, a small variance indicates a more accurate estimate
V:VARIANCE
15
Probability of completion:
=NORMDIST(B10,E8,SQRT(G8),TRUE)
STEP 4: DATES
For each task, determine the latest allowable time for moving to the next task Slack- difference between latest time and expected time
Task
Mark Utilities Dig holes Plant trees Plant flowers Install edging TOTAL Enter desired time completion date:
To
1 2 1 1 1
TL
3 4 3 3 2
TP
5 7 6 5 4
TE
3.00 4.17 3.17 3.00 2.17 15.50
ES
0 3 7 10 13
EF
3 7 10.17 13 15.17
LS
0 3 7 10 13
LF
3 7 10.17 13 15.17
SLACK
0 0 0 0 0
SD
0.667 0.833 0.833 0.667 0.500
V
0.444 0.694 0.694 0.444 0.250 2.528 37.66%
15
Probability of completion:
To
0.5 0.5 0.5
TL
1 1 1
TP
3 3 3
TE
1.25 1.25 1.25 3.75
ES
0 0 1.25
EF
1.25 1.25 2.5
LS
3 3 4.25
LF
4.25 4.25 5.5
SLACK
3 3 3
SD
0.125 0.125 0.125
V
0.015625 0.015625 0.015625 0.047
LS=Latest Start
LF=Latest Finish
15
Probability of completion:
=NORMDIST(B10,E8,SQRT(L8), TRUE)
LS=Latest Start
LF=Latest Finish
STEP 5: PROBABILITIES
PERT IN A NUTSHELL:
1) A management tool for defining and coordinating what must be done to accomplish a projects objectives on time. These tasks were affected by our constructing a diagram of the PERT network. 2) A technique that aids the manager but does not decide for him. He uses it to calculate variance, slack, probability, and time estimates. 3) A technique that presents statistical knowledge about the uncertainties faced in completing the many activities associated with a project -- with it we calculated the expected task duration, variance, and probability. 4) A method for attracting a managers attention to latent problems that require decisions and/or solutions. We used it to analyze the PERT network for critical paths and slacks. 5) A method of attracting a managers attention to procedures for adjusting time, resources, or performance to meet target dates. He does so by analyzing the PERT network for areas of possible resource reallocation.
Critical Path:
The longest path (time) through the task network. The series of tasks (or single task) that dictates the calculated finish date of the project (in other words, when the last task in the critical path is done the project is done). -If shortened, it will decrease overall project completion time. -Activities outside the CP would not effect overall PC time.
Slack Time:
The amount of time a task can be delayed before the project finish date is delayed.
-TS (Total Slack) can be either positive (+) or negative (-). -If Positive: indicates amount of time that the task can be delayed w/out delaying project finish date.
-If Negative: indicates amount of time that must be saved so that the project finish date is not delayed.
- TS = Latest Start Earliest Start - A task w/ a TS = 0 is a Critical Task ( Float Time)
Crashing:
The shifting of resources to reduce slack time so the critical path is as short as possible. Always practice caution when crashing projects. -Results: Creates interference and increases project costs. An imaginary activity w/ 0 duration. It is used to show either an indirect relationship between 2 tasks or to clarify the identities of the tasks. -In CPM, each activity must be uniquely defined by its beginning and ending points. -When two activities begin and end at the same time a dummy activity is put in place to tell them both apart.
Dummy Activity:
Dependencies:
Links between project tasks. 3 Types: 1- Casual: Where one task must be completed before another can begin. (Critical Path Schedules) 2- Resource: Where a task is limited by availability of resources. 3- Discretionary: Optional task sequence preferences may reflect organizational preferences. (not required) -Milestone: A significant task which represents a significant accomplishment within the project. (Special Attention/Control)
Constraints:
Restrictions set on the start/finish date of a task. You can specify that a task must start on/finish no later than a particular date. 2 Types: 1- Flexible: As soon as possible (ASAP) / as late as possible (ALAP) do not have specific times allocated. Setting these times enables you to begin tasks ASAP/ALAP w/ the task ending before the project finish. -Must take into consideration all other factors.) 2- Inflexible: Must start on (MSO) / must finish on (MFO) require an allocated date, which controls the time completion of a task. -External factors: -Availability of Eq./Resources -Deadlines -Contract Milestones -Start/Finish Dates
Management Tool
PERT, analyzes only the longest likely chain of activities used to complete a project.
- Earliest time a project can be completed when using the longest possible task durations.
Deterministic,
probability.
- Events are determined by preceding events, not by -Deterministic (Time estimates that are fairly certain.) -Probabilistic (Estimates of times that allow for variation.)
Derives
Unrealistic estimates = Unrealistic Plans. - All plans are estimates and are only as good as the task estimates. Adding tasks = Added Time & Cost. - If there are any additions/reductions in the overall project, the estimates must adapt to the change. Expectation Control (Benefits) - Time estimates (likely) - How long will it take?
- How long will it take if it needs to be done sooner?
- Cost estimates
Duration:
The time it takes for an activity to be completed, given the planned amount of material, labor and equipment. Effort: The amount (not time-oriented) of work required to finish the task. Duration may decrease by adding resources but the overall effort required will remain constant. Scope: A specific definition of what the project does and does not entail. This is critical to the everchanging project environment as well as managing the expectations of not only customers, but workers. Resources: All available means utilized for the completion of the project. Such as equipment, employees, finances, etc.
-small set of activities make up the longest path, controlling the entire project. -these critical activities could be identified and managed with the optimum level of efficiency (personnel, resources, etc.) -Non-critical activities -Pareto Phenomenon
Assumptions:
-Each task possesses a distinct start and finish point. -Each estimate can be mathematically calculated. -Tasks must be able to be arranged in a defined sequences that produces a pre-defined result. -Resources may be re-allocated as required per needs. -Cost & time have a direct relationship. -Time has 0 value.
Project Assumption:
-CPM assumes projects may be crashed: Finishing a task/project in a shorter amount of time using extra resources. -Impacts: -Shared Resources -Other Projects -Quality -Reliability
Activity-on-Arrow Diagram
Necessary Information: -ES, the earliest time activity can start, assuming all preceding activities start as early as possible. -EF, the earliest time the activity can finish. -LS, the latest time the activity can start and not delay the project. -LF, the latest time the activity can finish and not delay the project. Used to Calculate: -Expected total project duration. -Slack time. (LS ES or LF EF) -The critical path.
Forward Pass:
-For each path, start at the left side of the diagram and work toward the right side. -For each beginning activity: ES = 0. -For each activity: ES + Activity Time = EF -For the following activity: ES = EF of preceding activity.
Backward Pass:
-For each path, start at the right side of the diagram and work toward the left side. -Use the largest EF as the LF for all ending activities. -For each activity: LS = LF Activity Time. -For the preceding activity: LF = LS of following activity.
SOURCES:
http://krypton.mnsu.edu/~tony/courses/609/PERT/te ch.html krypton.mnsu.edu/~tony/courses/609/PERT/pert2.p pt