MEANING
NEED
TRADITIONAL METHODS COMPARED ACTUAL COSTS WITH PLANNED COSTS, IGNORING THE % OF COMPLETION OF PROJECTS PHASE WISE
CONTROL ON COST OVER-RUN CONTROL ON SCHEDULE OVER-RUN VISIBILITY OF PROGRAMME PERFORMANCE PROVIDES THE LIKELY EXPENDITURE OF PROJECT WITH PRESENT PACE OF PROGRESS PROVIDES THE LIKELY COMPLETION DATE OF PROJECT WITH PRESENT PACE OF PROGRESS
REDUCTION IN RISK FOR TIMELY COMPLETION OF THE PROJECT BY ALLOCATING MORE RESOURCES IDENTIFICATION OF PROJECT TEAMS INEFFICIENCY OR DEFECTIVENESS IN PROJECT PLAN ALLOCATION OF MORE RESOURCES IF COST OVER RUN IS DUE TO UNFORESEEN TECHNICAL CHANGES IN THE PROJECT
METHODOLOGY
PREPARATION OF PRIMARY MEASURES: 1. Budget Cost of Work Scheduled (BCWS): Also known as planned value (PV) of the project. Each project has inputs in terms of human resource, material, overheads, R & D etc. Planned cost of each project - month wise, till the targeted month is prepared
METHODOLOGY Contd..
2. Preparation of Budgeted Cost of Work Performed (BCWP) also known as earned value (EV) At every phase the project collects earned value as the work is in progress, on a pro-rata basis. Eg., if the work completed is 80%, the earned value will be 80% of budgeted value.
METHODOLOGY Contd..
3. Preparation of Actual Cost of Work Performed (ACWP) Also known as Actual Cost (AC) Actual costs of all resources deployed are collected month wise or phase wise, as per requirement
DERIVED MEASURES
The earned value is compared with actual costs and planned costs - up to a phase of completion or month. This comparison will give Cost over-run and Schedule over-run This comparison will also predict the likely future cost at which the project is likely to be completed
2. SCHEDULE VARIANCE (SV): An indication to show how much a project/programme is ahead or behind schedule: SV = BCWP BCWS OR EV PV
6. ESTIMATE COST AT COMPLETION (ECAC): It indicates the likely expenditure when the project is completed when it goes in the same pace of progress ECAC = BAC (VALUE) / CPI
THANK YOU