SCREEN
1
2 3 4 5
Dont Panic
Switch Off All Electrical Equipment Dont Run, Walk Fast! Go to the Assembly Point Wait for the Final Instruction
1. Safety Moment
6. Weekly Inspection
Committee Inspection Weekly Inspection
2. Previous Meeting
3. HSE Programs
Investigation Lesson Learnt
7. Environmental Issues
4. HSE Statistics
Performance per Area and Total
8. Action Plans
Seoyong Hilalco
NO.
ITEMS
ACTION PLANS
KEPCO representative mentioned that KEPCO continues to report HSE findings thru CCAP. The numbers are to be checked and reflected in this meeting. All findings issued to respective subcontractors are rated by a scoring system established by HSE. Findings under Hilalco reached 7.1 points landing them on top. The organization will come back with their plans next week The output from investigation and lesson learnt from recent serious incident involving toppled crane will be shared on next meeting.
ACTION BY
DUE DATE
STATUS
CCAP Findings
HSJV
Next Meeting
Hilalco
Next Meeting
Investigation Result
HSJV
Next Meeting
The CEO of Advan will be on site tomorrow (30 Advan Action April) to have a direct evaluation of organizations Plans HSE management .
Advan
Information
Description
Date/Time : 01 May 2013, 7:00 AM Venue : CO Conference Room Subject : Presentation of Corrective Actions Attendees : Advan CEO, HSJV, KEPCO Subcontractor Site Managers
Team Selection
Presentation of report
Sequence of Events 13 April 2013 : HSJV Architectural Dept. contacted subcontractor on relocation of Tower Crane 10 16 April 2013 : Relocation postpone 17 April 2013 :
Causal Factor : Team lifts the 14th counterweight block Root Cause : not qualified, work package/permit needs improvement (NI), enforcement NI, no preparation, scheduling NI
policy.
Obtain work permit prior work Improve scheduling, planning and preparation of work Lesson learnt : Deployment of qualified personnel to ensure implementation of PTW system
Sequence of Events 13 April 2013 : 6:00 AM IP and team attended tool box meeting 06:15 AM IP and team assigned to fix/align embed sleeve pipes. 06:30 AM IP and team prepares sleeve pipe
Lesson learnt :
Guidance for newly hired personnel.
Description
BNPP will implement traffic scheme for paved road/non -paved road. Heavy vehicle is prohibited from the use of paved road to protect damages by trucks. To prevent and minimize dust emerging from ground.
BARAKAH NUCLEAR POWER PLANT PROJECT
Description
Bulk bags are classified as lifting accessory which requires third party inspection as stated in Abu Dhabi code, COP 34.0 Safe Use of Lifting Equipment and Lifting Accessories. This bag is not
allowed on site.
Item
Near Misses
Over speeding
First Aid Cases (FA) Medical Treatment Cases (MTC) Restricted Work Cases (RWC) LTIs Property/Vehicle Accidents Environmental Release
0 0 0 1 0 0 0 0
0 0 2 1 2 0 2 0
0 0 0 0 0 0 0 0
0 0 0 1 1 0 1 0
0 0 1 0 0 0 0 0
2 0 5 4 0 0 4 0
0 0 3 0 0 0 0 0
13 0 27 5 3 3 7 0
0 0 0 0 0 0 0 0
0 1 4 1 0 0 1 0
0 0 0 0 0 0 0 0
0 0 2 1 0 0 1 0
0 0 4 1 0 0 0 0
15 1 40 13 6 3 16 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Cumulative 127*
Legend : Ancillary Rebar Shop, Batch Plant, Paint Shop, Heavy Equipment Shop Power Block Cut Off Wall, Wharf Area, Concrete Block Area * : 41 cases (Oct- Dec. 2011), 64 cases (2012), 22 (2013)
BARAKAH NUCLEAR POWER PLANT PROJECT
Issued
Findings
K E P C O H S J V
S U B C O N
Status
Total
Open
KEPCO HSJV Subcon KEPCO
Closed
HSJV Subcon
0 10 0 10
0 10 0 10
0 7 0 7
0 0 0 0
0 0 0 0
0 40 26 66
Electrical Safety
Hand & Power Tools Fall Protection Waste Management Health & Welfare Hot Works Working at Height Color Coding Excavation Poor Illumination Environmental PTW Training Documents Manual Handling Supervision LOTO Steel Erection
1
0
10
12
16
19 18
27 26 25 24 24
32
39 38 37 36 35
47
59
10
20
30
40
50
60
70
Scaffold should have scaf tags whether in use or under erection. ( Power Block, DOW) All guardrails must be secured to hold any fall or external forces (Village 1, Hanlim) Replace damaged sole plate and conduct re-inspection (GIB, Hilalco) Toe boards should be installed as required in any scaffolds (Power Block, Seoyong)
1
Access under modification must be properly tagged (ADB, Seobon) Install ladder on erection of rebars (Power Block, D&I) Clearing of materials obstructing the road ways (GIB, Hilalco) Ladder checklist must be followed in timely manner, ensuring access are secured by clamps (AB1, Advan)
Ensure rebars are lifted at center of gravity. (CWDC, Gusan) Lifting accessories like shackle requires third party inspection and certificate prior to use. (village 1, Towers Tech)
Material basket should have third party inspection and certificate prior to use. (Power Block AB2, Seoyong)
Ensure padding is available when lifting gears are exposed to sharp edges (Ancillary, Gusan)
Scaffolding
Lifting
100 90 80 70 60 50 40 30 20 10 0
84
76
56
50
31 20 11 5 10 3 5 2 4 10 4
12
3 4 1 1
90 80 70
60
50 40
14, Housekeeping
7, Housekeeping
30
20
10
3, Electrical Safety 6, Health and Welfare 2, Access and Egress
5, Lifting 4, Housekeeping
Steel Erection Supervision Documents Training Manual Handling Poor Illumination PTW Excavation Environmental Color Coding Hot Works Waste Management Working at Height Hand & Power Tools Health & Welfare Electrical Safety Plant & Equipment Fall Protection Fire Prevention PPE Material Management Lifting Signs, Barriers & Barricades Access & Egress Scaffolding Housekeeping
Seoyong
80 70 60 50 40 30 20 10 0
(This Week From April 27 May 3 , 2013)
6.0
4.2
5.0
Action Plan for Company requiring assistance and support from the system 1. Joint Inspection will be carried out by Area Management Team. 2. Spot Training will be given to workers about major findings 3. Action plan will be submitted to HSJV HSE Team develop by D&I
BARAKAH NUCLEAR POWER PLANT PROJECT
Waste Management, 1
Nos 11 6
PPE, 1 PTW, 2
Control Measure
Done
Ensure that access are properly inspected and passed the standard
Done
Color Coding, 2
Control Measure Provide proper fall protection on elevated surfaces and vertical openings. Lifting radius should be provided with barricades to restrict unauthorized entry.
Due Date
Done
Always
Control Measure Provide cable hangers & ensure that protruding nails are removed from unused woods. Scaffolding planks & toe boards should be properly installed according to standard.
Done
Fall Protection, 4
Waste Management, 6
Lifting, 5
Item No.
LOCATION
Area/Activity
FINDINGS
RECOMMENDED ACTIONS 1. Provision of appropriate First Aid Box with checklist attached. 2. First Aid - Criteria/Requirements Checklist should be posted on the first aid room. 3. Provision of "what to do" list/guidelines in applying first aid treatment. 4. Immediate repair on defective floor. 1. First Aid - Criteria/Requirements Checklist should be posted on the first aid room. 2. Provision of "what to do" list/guidelines in applying first aid treatment. 1. First Aid - Criteria/Requirements Checklist should be posted on the first aid room. 2. Provision of "what to do" list/guidelines in applying first aid treatment. 3. Immediate action needed to provide cover on the said electrical panel. 1. Provision of appropriate First Aid Room. 2. . First Aid - Criteria/Requirements Checklist should be posted on the first aid room. 3. Provision of "what to do" list/guidelines in applying first aid treatment.
RESPONSIBLE
STATUS
1. Inappropriate First Aid Box. Seoyong / First Aid 2. No Criteria or Guideline Checklist for First Aid Requirements. Room 3. Rely only to Kepco Clinic for Initial Treatment 4. Defective floor, prone to tripping hazard. Might cause foot injury.
Seoyong
Open
1. No Criteria or Guideline Checklist for First Aid Requirements. 2. Rely only to Kepco Clinic for Initial Treatment
Samjin
Closed
Laydown 3 Advan / First Aid Room 1. No Criteria or Guideline Checklist for First Aid Requirements. 2. Rely only to Kepco Clinic for Initial Treatment 3. Found First Aid Room Electrical Panel not covered. Exposure of conductive terminals.
Advan
Closed
1. No appropriate First Aid Room utilized the HSE Office as First Aid Room. 2. No Criteria or Guideline Checklist for First Aid Requirements. 3. Rely only to Kepco Clinic for Initial Treatment
Hilalco
Open
AB1
Lifting of Nylon Bags containing mixed waste materials without steel waste box.
Tool Box Meeting for all Riigers and Supervisors involved that no All involved lifting of nylon bags directly. Subcons / HSJV
Open
AB1
1. Checklist available for the First Aid Kit but inappropriate First Aid Box was used. 2.Rely only to Kepco Clinic for Initial Treatment
1. Provision of proper First Aid Box. 2. Provision of "what to do" list/guidelines for First Aid Trained Personnel to follow in case of first aid treatment. 1. First Aid - Criteria/Requirements Checklist should be developed and posted inside the First Aid Room next to the First Aid Boxes. 2. Provision of "what to do" list/guidelines for First Aid Trained Personnel to follow in case of first aid treatment. 1. Provision of appropriate First Aid Room. 2. First Aid - Criteria/Requirements Checklist should be posted on the first aid room. 3. Provision of "what to do" list/guidelines in applying first aid treatment. Provision of adequate welfare facilities for Heat Stress Prevention. (Shelters and Toilets) The Committee agreed that there should be a provision of the Heat Stress Prevention Campaign Banners posted at site. Design will be provided by ENEC.
Younchang
Open
TGB
Geumhwa
1. No Criteria or Guideline Checklist for First Aid Requirements. 2. Rely only to Kepco Clinic for Initial Treatment
Geumhwa
Closed
O&M Bldg
1. No appropriate First Aid Room, utilized Site Office as First Aid Room. 2. No Criteria or Guideline Checklist for First Aid Requirements. 3. Rely only to Kepco Clinic for Initial Treatment
Seobon
Open
Heat Stress Prevention not yet fully prepared. 9 All Locations All area and activities Heat Stress Prevention Campaign Banner not available at site.
Description
Standard is set for first aid
room facility at site ensuring management of incident are handled as per medical
practices.
The minimum requirements for first aid room shall be followed by Subcontractors.
1
0.5 0
Advan Gusan Hilalco
2
1
HSJV Seobon
2
1
Seoyong (PB) Towerstech
Area
Description
Immediate Action
The worker a welder Kim performed gas cutting Cleansing Welder on pipe when suddenly &wound Pain and skin Ancillary area his small finger came in dressing done abrasion Anti-bacterial contact with hot welding shop cream applied surface. Worker (Flamazine) 30-04-2013 sustained superficial Will need wound burn.
16:30
dressing - Daily
YOO A
Assessed by Dr.
Area
Description
Immediate Action
Jonghap
Electrical Helper The worker complained of Assessed by Dr. Low back Kim sudden pain, low back pain lifting Power Block Topical analgesic area after lifting a 20-30kg 30kg cable applied and cable. given 28-04-2013 10:00
Area
Description
Immediate Action
Advan
Carpenter
3
Injured person was Kim instructed by his Wound cleansing superior to replace tie and dressing done rod at concrete spacer, Steri-strip application so as injured person released the tie rod, Tetanus toxoid injection given at the spacer moved and left deltoid trapped his finger.
muscle.
Assessed by Dr.
Area
Description
Immediate Action
The injured person while moving plywood Labour was pressed by the Assessed by Dr. material during Kim Construction Office Area placement at back of Wound dressing done. pickup. Injured persons 02-05-2013 finger suffered light abrasion.
13:30
HSJV
Area
Description
Immediate Action
The worker tried to replace a new cutting Assessed by Dr. disc on portable Pipe fitter Kim grinder however while Injury cut tool was switched off, Wound cleansing Power Block / wound left and dressing done IP immediately started AB No. 2 index finger Tetanus injection to detach rotating given at left 02-05-2013 wheel thus his index deltoid muscle finger came in contact 10:20 with the slowing disc.
Youn Chang
Inspection Date: 1 st May Inspection Course:
Village 2 Municipal waste area Village 2 STP Power Block Area Temporary waste Area
Inspection Item:
Village 2 Seepage of treated water from adjacent plantation area. Foul smell. Area backfill carried out. Provision of dike to prevent seepage.
Status
CLOSED
AQMS Station Not barricaded and inadequate signboards Provided physical barricades and appropriate signages
Status
CLOSED
Village 1 Inappropriate waste segregation in GMET waste skip Spot Training and Waste Management Awareness conducted. Sorting and segregation of waste materials been carried out.
Status
CLOSED
No.0
Date
Action by Company
Description
Status
Closing Date
Expiration Date
Main Area
Sub-Area
Issued By
Issuer Company
2013.04.18
HSJV
ENV-IR- Village Seepage of treated water from CLOSED 2013.05.03 2013.04.26 13-0002 2 adjacent plantation area. Foul smell. ENV-IRCLOSED 2013.05.03 2013.04.26 13-0002
STP
Anthony Manuel
ENEC
2013.04.18
HSJV
Lay down
AQMS Station
Anthony Manuel
ENEC
2013.04.18 Towerstech
Waste Skips
Anthony Manuel
ENEC
WASTE TYPE
Paper Metal Construction Concrete Wood(Good) Wood(Bad) Plastic Municipal
Last week
Recycle(%)
Hazardous
Total Solid Waste
45 45 0 0 0 45 0 0 0 90 11.84%
0 0 0 0 0 45 0 0 0 45 7%
Legend: Collected - Waste from Site to Temporary Storage Area Disposal - Waste from Temporary Storage Area to Landfill Area Recycle - Treated waste ( GMET) to Recycling Plants BARAKAH NUCLEAR POWER PLANT PROJECT