Capital investment appraisal

Introduction
As investments involve large resources, wrong investment decisions are very expensive to correct Managers are responsible for comparing and evaluating alternative projects so as to allocate limited resources and maximize the firms wealth Basic techniques of making capital investment appraisal for evaluating proposed capital investment projects

Investment appraisal methods

Considering the time value of money concept

Ignoring the time value of money concept

Net present value Internal rate of return

Payback period Accounting rate of return

Net present value method

Time value of money


When facing different investment proposals, the management should choose the project that can generate the greatest addition of value to the company. For example, Project A Project B Initial investment $100 $100 Cash inflow at end of year Year 1 $110 Year 2 $121
5

At first sight, some may think that project B is better because it has a higher cash inflow. However, the time value of money concept states that a dollar today is always worth more than a dollar in the future The two projects are of equal value to the company because their present values are the same
6

After taking timing of cash flow into consideration, Project A Project B Present value of cash flow (interest rate is 10% per annum) 110 121 (1+10%) (1+10%)2 = $100 $100 The two projects are of equal value to the company because their present values are the same
7

Factors leading to the changes in value of money


Opportunity cost of money Erosion of purchasing power due to inflation Uncertainty and risk

Opportunity cost of money


Opportunity cost of money refers to the cost incurred or income forgone by not using the money for other purpose For surplus cash, the opportunity cost is the interest income forgone by investing the cash in other investments or depositing it in the bank

Erosion of purchasing power due to inflation


Inflation refers to the continual increase in the general price level of goods or services During a period of inflation, prices of goods increase while the purchasing power of money decrease. The purchasing power of a dollar today is greater than that of the future

10

Uncertainty and risk


Investors tend to avoid risk. The uncertainty involved in future cash inflows is much higher than that in present cash inflows If the level of risk rises, investors will expect a higher return as compensation. For example, suppose an investor expects $100 for return now. After adding a 10% risk premium, he will expect $110 one year later

11

Discounting

12

Discounting
According to the time value of money concept, a dollar in one year is not worth the same as a dollar in anther year. In evaluating a multi-year investment, cash inflows and outflows are generated in different years It is necessary to convert the cash flows for different years into a common value at a common point of time, either at present or in the future
13

Discounting is the process of reducing future cash flows to present values with the use of an interest rate
Present value = FVn (1+r)n Where FV = Future value of an investment n= Number of years r= Appropriate interest rate
14

Example

15

John has won a lucky draw. He is deciding whether to receive the Prize money of $3000 today or the following set of cash flows over the next three years: Year Cash flow 1 $1100 2 $1210 3 $1331

Future values Year 1 $1100 Year 2 $1210 Year 3 $1331

Discount processes Present value $1100/1.1 $1210/1.12 $1331/1.13 $1000 $1000 $1000

16

Net present value method

17

Net present value method


Net present value (NPV) method is a process that uses the discounted cash flow of a project to determine whether the rate of return on that project is equal to, higher than, or lower than the desired rate of return With the NPV method, we can compare the return on investment in capital projects with the return on an alternative equal risk investment in securities traded in financial market
18

Calculation procedures
Determining the discount rate 2. Calculating the NPV:
1.
FV1 FV2 NPV = (1+r)1 + (1+r)2 FV3 + + 3 (1+r) FVn (1+r)n - I0

where FV = future value of an investment n = no. of years r = Rate of return available on an equivalent risk security in the financial market I 0= initial investment
19

3.

Interpreting the NPV derived as follows:


Comments Reject the project Indifferent to accept or reject the project Accept the project Reasons
The rate of return from the project is small than the rate of return from an equivalent risk investment The rate of return from the project is equal to the rate of return from an equivalent risk investment The rate of return from the project is greater than the rate of return from an equivalent risk investment If various project are considered, the project with highest positive NPV should be chosen 20

NPVs <0 =0 >0

Highest Accept the project

Example

21

A company is considering making several investments in the Production facilities for the new products with an estimated useful Life of four years. The cash inflows and outflows are listed as follows: Project A B C D $ $ $ $ Initial investment 900000 1000000 303730 1500000 Cash inflow Year 1 120000 400000 100000 10000 Year 2 250000 400000 100000 10000 Year 3 400000 400000 100000 1000000 Year 4 1300000 400000 100000 1000000 The appropriate discount rate of these investment is 12%

22

Required: (a) Calculate the NPV of each investment and determine whether to accept it or not (assuming the company has unlimited resources) (b) If the company has limited resources, determine which investment should be accepted by referring to the highest NPV

23

(a)

Project A 120000 250000 400000 1300000 + + + NPV = 1.12 2 3 1.12 1.12 1.124 - 900000 = $517327 (accepting) Project B

40000 400000 + NPV = 1.12 1.122


= $214920(accepting)

400000 400000 + 1.123 1.124 - 1000000

24

(a)

Project C 100000 100000 100000 100000 + + + NPV = 1.12 2 3 1.12 1.12 1.124 - 303730 = $0 (indifferent to accept or reject) Project D

10000 10000 + NPV = 1.12 1.122


= -$135801(rejecting)

1000000 1000000 + 3 1.12 1.124 - 1500000

(b) With limited resources, the company should only accept project A because it generates the highest NPV

25

Advantages of NPV
Consistency with the time value of money concept Consideration of all cash flows Adoption of cash flows instead of accounting profit

26

Internal rate of return

27

Internal rate of return


The internal rate of return is the annual percentage return achieved by a project, of which the sum of discounted cash inflow over the life of the project is equal to the sum of discounted cash outflows If the IRR is used to determine the NPV of a project, the NPV will be zero. The company will accept this project only if the IRR is equal to or higher than the minimum rate of return or the cost of capital
28

Calculation procedures
1.

By trial and error, find out the discount rate that will give a zero NPV
FV1 FV2 NPV = (1+r)1 + (1+r)2 FV3 + + 3 (1+r) FVn (1+r)n - I0 = 0

where FV = future value of an investment n = no. of years r = internal rate of return I 0= initial investment
2.

If the NPV is positive, try a higher discount rate in order to give a negative NPV and vice versa
29

3.

After getting one positive NPV and one negative NPV, use interpolation to find out the rate giving zero NPV
P IRR = L + (H L) PN Where L = Discount rate of the low trial H = Discount rate of the high trial P = NPV of cash flows of the low trial N = NPV of cash flows of the high trial
30

4.

In evaluating an investment project, the IRR is compared with the managements predetermined rate
Comments Reasons NPV<0

IRRs

< lowest acceptable level of return Reject

= lowest acceptable level of return Accept


> Lowest accepted level of return Highest Accept Accept

NPV=0
NPV>0 If several project are considered, the highest IRR should be chosen 31

Example

32

A project costs $400 and produces a regular cash inflow of $200 at the end of each of the next three years. Calculate the IRR. If the minimum rate of return is 15 %, suggest with reason whether you Should accept the project or not. $200 $200 NPV = (1+r)1 + (1+r)2 $200 + (1+r)3

- $400 = 0

Assuming the discount rate is 22% $200 $200 $200 + + NPV = 1.22 1.222 1.223 Assuming the discount rate is 24% $200 $200 $200 NPV = 1.24 + 1.242 + 1.243

- $400 = 8.4

- $400 = -3.8

33

P IRR = L + (H L) PN Where L = Discount rate of the low trial H = Discount rate of the high trial P = NPV of cash flows of the low trial N = NPV of cash flows of the high trial IRR = 22% + 8.4 (24 22)% 8.4 (-3.8)

= 23.38% Since the IRR (23.38%) is higher than the minimum rate of return (15%), The project should be accepted
34

Payback period

35

Payback period
Payback period is the period of time it takes for a company to recover its initial investment in a project The method measures the time required for a projects cash flow to equalize the initial investment

36

Acceptance criterion
< predetermined cutoff period Accept the project
> Predetermined cutoff period Reject the project

37

Example

38

A company is considering making the following mutually exclusive Investments in the production facilities for the new products with an Estimated useful life of four years. The cash inflow and outflows are Listed as follows: Project A Project B $ $ Initial investment 900000 1000000 Cash inflow at the end of year Year 1 700000 600000 Year 2 100000 400000 Year 3 100000 400000 Year 4 1300000 400000 Project A : 3 years Project B: 2 years Project B takes only two years to recover its initial investment. With The shortest payback period, the company will accept project B
39

Advantages of payback period


Easy to adopt Facilities further evaluation

After obtaining an acceptable payback period, the project will be evaluated by other financial capital budgeting techniques

40

Disadvantages of Payback period


Ignore the cash flows after payback period Adopt an arbitrary standard for the payback period Ignores the timing of cash flow

41

Discounted payback period


The payback period method is criticized for ignoring the timing of cash flows, therefore discounted cash flows are used to calculate the discounted payback period

42

Example

43

A company is considering making the following mutually exclusive investments in the production facilities for the new products with an estimated useful life of four years. The cash inflow and outflows are listed as follows: Project A Initial investment 900000 Project B 1000000

Cash inflow at the end of year


Year 1 Year 2 Year 3 Year 4 Discount cash inflow (20%) 700000 100000 100000 1300000 600000 400000 400000 400000
44

Initial investment Discounted cash flow Year 1 700000 = 583333 400000 = 500000 1.21 1.21 Year 2 100000 = 69444 400000 = 277778 1.22 1.22 Year 3 100000 = 57870 400000 = 231481 1.23 1.23 Year 4 100000 = 626929 400000 = 192901 1.24 1.24 Discount payback period Project A 3+ 900000-710647 = 3.3 years 626929 Project B 2+ 100000-777778 = 2.96 years 231481
45

Project A $ 900000

Project B $ 1000000

Accounting rate of return

46

Accounting rate of return


The accounting rate of return compares the average accounting profit with the average investment cost of project The accounting profit can be expressed either before tax or after tax

47

Calculation procedures
Average net profit per year (over the life of the project) ARR = Average investment cost

Total profit Average net profit per year = No. of life of the project
Initial investment Average investment cost = 2

48

Acceptance criterion
In evaluating an investment project, the ARR of the project is compared with a predetermined minimum acceptable accounting Rate of return:

ARRs < minimum acceptable rate = minimum acceptable rate > minimum acceptable rate Highest

Comments Reject project Accept project Accept project Choose highest ARR
49

Example

50

A company is considering whether to buy specialized machines For a new production line. The purchase price of machinery is $400000 and its estimated useful life is four years. There is no scrap Value after four years The project income statements: Year1 Year 2 Year 3 Year 4 $ $ $ $ Revenue 310000 280000 280000 310000 Depreciation 10000 100000 100000 100000 Other expenses150000 100000 110000 120000 Profit before tax 60000 80000 70000 90000 Taxation (15%) 9000 12000 10500 13500 51000 68000 59500 76500 Should the company buy the new machinery if the minimum acceptable Rate of return is 20%?
51

51000+68000+59500+76500 = $63750 Average net income = 4 400000+0 = $200000 Average investment = 2


The cost of machinery is $400000 at the beginning The cost of machinery is $0 at the end as depreciation is provided On straight line method and there is no scrap value

$63750 ARR = $200000 = 31.875% Since the ARR is 31.875%, which is higher than the minimum Acceptable rate of 20%, the company should invest in the new machinery.

52

Advantages of ARR
It is easy to understand and compute It avoids using gross figures. Therefore, it enables comparisons to be made between projects with different useful lives

53

Disadvantages of ARR
It ignores the time value of money ARR method seems to be less reliable than the NPV method. It adopts the accounting profit instead of cash flows calculation. The change of depreciation method may also alter the accounting profit

54