Facilities Layout
Layout: the configuration of departments, work centers, and equipment, with particular emphasis on movement of work (customers or materials) through the system
Product layouts Process layouts Fixed-Position layout
Accidents
The introduction of new products or services
Safety hazards
6-6
that uses standardized processing operations to achieve smooth, rapid, high-volume flow that can handle varied processing requirements in which the product or project remains stationary, and workers, materials, and equipment are moved as needed
Process layout
Layout
Product Layout
Station 2
Material and/or labor
Station 3
Material and/or labor
Station 4
Finished item
Product Layout
Product Layout (sequential)
Work Station 1 Work Station 2 Work Station 3
In
4 5
Workers
6
Out
10
Process Layout
Dept. A Dept. B
Dept. C Dept. D
Dept. E Dept. F
many
longer variable
few
shorter fixed
greater higher
higher higher
shorter lower
lower lower lower
Equipment utilization
lower
higher
Line Balancing is the process of assigning tasks to workstations in such a way that the workstations have approximately equal time requirements.
Cycle Time
Cycle time is the maximum time allowed at each workstation to complete its set of tasks on a unit.
N=
t = sum of
Precedence Diagram
Precedence diagram: Tool used in line balancing to display elemental tasks and sequence requirements
0.1 min. 1.0 min.
a c
0.7 min.
b d
0.5 min.
e
0.2 min.
Using information contained in each of the following, do each of the following: 1. Draw a precedence dia. 2. Assuming an 8 hour workday. Compute the cycle time needed to obtain an output of 400 units per day 3. Determine the minimum number of workstations required
Task
Immediate follower
A
B C D E F G H
B
E D F F G H end
.2
.2 .8 .6 .3 1 .4 .3
Precedence Diagram
e
0.2 0.2 0.3
a
0.8
c
0.6
f
1.0
g
0.4
h
0.3
. 3 min
. 4 min
. 2 min
. 1 min
. 5 min
. 3 min
b
. 6 min
d
1.2 min
f
.6 min
Station 1
Station 2
Station 3
Station 4
a
c
e f d
Parallel Workstations
Parallel Workstations are used to achieve a smooth flow of production. These are beneficial for bottleneck operations which would otherwise disrupt the flow of product as it moves down the line.
The bottleneck may be the result of parallel or very long tasks. Parallel workstations increases the work flow and provide flexibility
Bottleneck Workstation
1 min.
30/hr.
1 min.
30/hr.
2 min.
30/hr.
1 min.
30/hr.
Bottleneck
Parallel Workstations
2 min.
30/hr. 1 min.
60/hr.
2 min.
30/hr.
Parallel Workstations
Cases
Johnsons Rule
A technique for minimizing completion time for a group of jobs to be processed on two machines
All units must be completed at the first work center before moving to second
Example
Time on machine A Job 1 Job 2 Job 3 Job 4 Job 5 10 5 4 12 9 Time on machine B 2 7 10 8 6
Problems
1. The time required to complete each of the 8 jobs in a 2 machine flow shop are shown in the table that follows on the next slide. Each job must follow the same sequence. Beginning with machine A and moving to machine B.
A. Determine a sequence that will minimize a Makespan time B. Construct a chart of resulting sequence and find machine Bs idle time
2. Precision machining provides custom machining for its customers. The company presently uses a first come first served sequencing rule for customer jobs. Because the company wants to finish customer jobs faster, it is considering 2 other rules : shortest processing time and critical ratio. The company thinks that these criteria are important in selecting a sequencing rule: average flow time, average number of jobs in the system, and average job lateness. Study precisions situation and recommend a sequencing rule.
Pl see the Table on next page
Job Sequence
Production time(hrs)
A B
2 5
4 18
C
D E
3
4 6
8
4 20
24
Case
6-46
a. Draw a precedence diagram b. Assuming that 55 minutes per hour are productive, compute the cycle time required to obtain 50 units per hour c. Determine the minimum number of workstations d. Assign tasks to workstations e. Find idle time and percent efficiency
4. Determine the placement of departments for a newly designed facility that will minimize total transportation costs using data in the following tables. Assume that reverse distances are the same. The locations are shown in the grid. Use a cost of $1 trip yard
Location A
Location B
Location C
Location D
4 contd.
Distance between location yards To A B C D Number of trips per day Between departments
To
From
A B 40 80 40 70 50
From
1 2 3 10 20 40 80 90 55
C
D
60
-
5 Five departments are to be assigned to locations B-F in the grid (For technical reasons deptt. 6 must be assigned to location A). Transportation costs is $2 per foot. The objective is to minimize total transportation cost. Information on interdepartmental work flows and distances between locations is shown in the following tables. Assign departments with the greatest interdepartmental work flow first.
See related tables in the next slides
From
A B C D E F
To
A
-
B
50 -
C
100 50 -
D
50 90 140 -
E
80 40 60 50 -
F
130 70 50 120 50 -
From
1 2 3 4 5 6
To
1
-
2
125 -
3
62 10 -
4
64 17 2 -
5
25 26 0 13 -
6
50 54 20 2 5 -
A Dept 6
If seasonal variations are present, is their incorporation into MRP fairly simple or fairly difficult. Explain briefly
What is the difference between planned order receipts and scheduled receipts
Problem
E M (3) I (2)
R (2)
N (4)
Problem
Given the following production schedule in units and the production standards for labor and machine time for this product, determine the labor and machine capacity requirements for each week. Then compute the percent utilization of labor and machines in each week if labor capacity is 200 hours per week and machine capacity is 250 hours per week.
Production Schedule: Week 1 2 Quantity 200 300 Standard Times . Labor .5 hour/unit Machine 1.0 hour/unit
3 100
4 . 150
Develop a Material Requirements plan for component H. Lead times for the end item and each component except B are 1 week. The LT for B is 3 weeks. Sixty units of A are required at the start of week 8. There are currently 15 units of B on hand and 130 units of E on hand, and 50 units of H are in production and will be completed by the start of week 2.
B (2)
C (4)
D (2)
E (2)
D (3)
G (2)
D
Problem
Balance system: Distributing the workload evenly among work stations Work assigned to each work station must be less than or equal to the cycle time Cycle time is set equal to the takt time Takt time is the cycle time needed to match customer demand for final product
Closeness Rating 1 2 3 4 5 6
Meaning of Rating Necessary Very Important Important Slightly Important Unimportant Undesirable
Example: AG Advertising
Using Closeness Ratings AG Advertising is moving into a new office suite having seven large, roughly equal size rooms, one for each department of the firm. Lisa, the manager, must now assign each department to a room. She has developed a grid of closeness ratings (on the next slide) for the 21 unique pairs of departments.
, one for each department of the firm. Lisa, the manager, must now assign each department to a room. She has developed a
Example: AG Advertising
A
5
B C D E F G
6 4
6 3
1
4 5
2
1 1
4
2 3
5
2
Example: AG Advertising
Unassigned Rooms of Office Suite
Example: AG Advertising
Layout Satisfying All Pairings of Departments with 1 Closeness Ratings
CR = 1
B F
D C G
Trying to satisfying all pairings of departments with 6 closeness ratings, we see that Dept. C needs to be moved
B F
D G C
Layout Satisfying All Pairings of Departments with 6 Closeness Ratings (note that we swapped Dept. D and Dept. F)
B D
F E
A G C
Problem
Given the following information, compute the takt time: Total time per shift is 480 minutes per day, and there are 2 shifts per day. There are 40 minutes rest breaks and a 30 minutes lunch break per shift.
820 min per day / 80 units per day = 10.25 minutes per cycle
Usage at each work center is 300 parts per day, and a standard container holds 25 parts. It takes an average of .12 day for a container to complete a circuit from the time a Kanban card is received until the container is returned empty. Compute the number of Kanban cards required if X = .20
N=? D = 300 parts per day T = .12 day C = 25 parts per container X = .20 N= 300 (.12)(1+.20) / 25 = 1.728 = 2
Determine the number of containers needed for a work station that uses 100 parts per hour if the time for a container to complete a cycle (move, wait, energy, wait, return) is equal to 90 minutes and a standard container holds 84 parts. An inefficiency factor of .10 is currently being used
Housekeeping
Maintaining a workplace that is clean and free of unnecessary materials. What are 5 important S
Sort
Straighten
Sweep
Standardize
Self Discipline
Capacity Planning
Capacity is the upper limit or ceiling on the load that an operating unit can handle. Capacity also includes
Equipment Space Employee skills
Capacity
Design capacity
maximum output rate or service capacity an operation, process, or facility is designed for
Effective capacity
Design capacity minus allowances such as personal time, maintenance, and scrap
Actual output
rate of output actually achieved--cannot exceed effective capacity
Strategy Formulation
Capacity strategy for long-term demand Demand patterns Growth rate and variability Facilities Cost of building and operating Technological changes Rate and direction of technology changes Behavior of competitors Availability of capital and other inputs
If annual capacity is 2000 hours, then we need three machines to handle the required volume: 5,800 hours/2,000 hours = 2.90 machines
Bottleneck Operation
Bottleneck Operation
Economies of Scale
Economies of scale
If the output rate is less than the optimal level, increasing output rate results in decreasing average unit costs
Diseconomies of scale
If the output rate is more than the optimal level, increasing the output rate results in increasing average unit costs
Evaluating Alternatives
Cost-volume analysis Break-even point Financial analysis Cash Flow Present Value Decision theory Waiting-line analysis
Financial Analysis
Cash Flow - the difference between cash received from sales and other sources, and cash outflow for labor, material, overhead, and taxes. Present Value - the sum, in current value, of all future cash flows of an investment proposal.
Decision Theory
Helpful tool for financial comparison of alternatives under conditions of risk or uncertainty Suited to capacity decisions