This section should be used to summarise the key points of relevant risks identified by the team discussion
Procedure/Work Guideline Reference:
Measures in place for recovery What action to be taken if the control fails
CONTROLS IN PLACE?
Yes
No
o Pipes movement while being driven on graded road causing slipping/unsecured load.
oClear understanding of the location and the equipment on that location (topsides and buried). o Certified lifting equipment (crane, shackles, wires, etc...) o Tag lines used by comptent rigger o Balance the pipes while moving them with side boom oOne comptent banksman only to give instructions to crane driver wearing yellow vest oNo personnel to stand under suspended loads oBarrier around lifting area. oVHF Radio communications to be available (for all steps of the job) oInspect All sets before use oGas test o Use hot work enclosure (tent) and barriers/signs where applicable o Use PPE for hot work (i.e. welding mask, welding gloves) o Earthed welding sets inspected by electrical dep oCompetent fire watcher to be appointed o No flammable materials at the work site oFire watcher to inspect site 30mins after welding o Organize worksite (cables, machines, welding space, etc..) oHearing protection o Fire Extinguisher o Load stoppers on trailer o Secure loads by tight slings o No metal-to-metal contact by (wood packing oTry and park the trailer on a level surface, where possible. oRemoval of securing devices only once by experienced one
o Fire extinguisher shall be in place o Medical Kit in place oContact Radio Room
Area: Location: Talk Leader: . Person Supervising: . Job: Date & Time: Attendees
Area Operator
1 2 .. 3 .. 4 .. 5
Reviewed by (initials): Talk leader .. H.O.D. Office . ...
6.... 7 8 9 10.
Action required: Update procedures Update risk assessments Other (Raise remedial action form or change requests as necessary)
If the answer to any of these questions is NO, then the safety of people is at risk The talk leader should confirm the understanding of the group by asking open questions on the above points
If so, the work may be hazardous and care should be taken to ensure the work is done safely
Remember, everyone is responsible for: Using the correct tools for the job Being aware of the hazards around them and remaining vigilant to change Using the correct PPE for the job Making themselves aware of, and working within, the requirements of the PTW system, Procedures, Risk/MSDS/Manual Handling Assessments