Anda di halaman 1dari 5

OF REHABILITATION FOR ULAR RIVER FLOOD CONTROL AND IMPROVEMENT OF IRRIGATION PROJECT

PROPOSAL

METHOD OF TRIAL COMPACTION (BASE A & BASE B)

Table of Contents Flow Chart Construction Method Location of Trial Compaction

ADHI-WASKITA-WIJAYA JO

METHOD OF TRIAL COMPACTION Flow Chart


START

Submit Laboratory test of Material Proposed Base Course A & B No Yes OK? Yes Preparation Work Setting Out Hauling Material on specified Water Content Test (OMC -3 ~ +2 %) Stock Material from Stock Pile at Crusher plant

Stripping of Existing Road Shoulder

Spreading Material by Grader with Thickness 20 cm

Check Thickness & Elevation

Compacting by Vibro Roller


Check Thickness & Elevation

Sand cone Test Base B > 97% of MDD, Base A 100% of MDD,

OK? Yes Finish

No

ADHI-WASKITA-WIJAYA JO

METHOD OF TRIAL COMPACTION


METHOD OF TRIAL COMPACTION (BASE A & BASE B)
1. Location
Location of Works : Public Road Heightening Works (Plan attached). Location of Material : Crusher Plant at Desa Paku which distance 7 KM from Project Area

If the existing ground is bad / soften, base A/ base B for sub grade will be executed thickly 30 cm (compacted). Installation of Peil schaal at left and right side for monitoring thickness of base A/ base B before and after compaction.

2. Equipment
Dump Truck 12 m3 Grader cater pillar Vibro Roller Dyna pack 12 ton Laboratory Apparatus Survey Apparatus : 3 unit : 1 unit : 1 unit : 1 Set : 1 Set

3. Material
Base Course Aggregates Class A 1. Los Angeles Abrasion 2. CBR Value 3. Plasticity Index 4. Specific Gravity 5. Gradation 1. Los Angeles Abrasion 2. CBR Value 3. Plasticity Index 4. Specific Gravity 5. Gradation

Base Course Aggregates Class B

4. Sequence of Works
Trial Base A/ base B will be executed with compaction by 6, 8 and 10 passing for each layer Route of hauling material for trial base A/ base B like enclosure. Before spreading material, will be checked of field moisture content, Measuring thickness of base A/ base B before and after compaction. Execution Trial Base A/ base B.

ADHI-WASKITA-WIJAYA JO

METHOD OF TRIAL COMPACTION

1. Survey shall be determine location of Trial base A/base B approved by Engineer

Ass. Surveyor Theodolite

2. Stripping Top Soil by Grader

3. Spreading material base A/ base B from stone crusher plant

ADHI KARYA

4. Compacting by Vibro Roller

5. After trial base A/ base B finish, density test could be executed

Density Test

ADHI-WASKITA-WIJAYA JO

METHOD OF TRIAL COMPACTION Plan of Trial Base A & Base B

6 passes 3m

8 passes

10 passes

15 m

15 m B PLAN

15 m

Measure of settlement at each layer

Field density and natural moisture content

Base A Base B Sub grade

20 cm 20 cm Existing Flood Dike

SECTION A - A

3m Peil schaal
Base A ( 20 cm) Base B ( 20 cm) Sub grade

SECTION B - B

ADHI-WASKITA-WIJAYA JO