Requirement of Hydraulic System

To fulfill the water requirement of the Under Ground Stations


To discharge the Seepage & Sewage of the Under Ground

Stations
To fulfill the water requirement of Stations Utilities
For Fire Suppression System
Hydraulic System Components

PTM Supply System


Raw Water Pumps and Treated Water Pumps
Seepage System
Sewage System
Service Pumps

PTM SUPPLY SYSTEM


BORE WELL PUMPS
Installed

at Shastri Park Depot at different locations.


Ratings from 7.5 KW to 10 KW
Supply ground water to PTM Tanks

BOOSTER PUMPS
Installed

at PTM Room
Ratings from ..
Supply Water from PTM Tanks to Different U/G Stations

VALVES AND PIPES


Requires

to divert the Water supply if there is any


problem in long distance pipe

PTM SUPPLY ARRANGEMENT

Raw Water Pumps and


Treated Water Pumps
Raw Water Pump transfer the water from Raw
Water Tank (RWT) to Treated Water Tank (TWT)
through Water Treatment Plant
Water Treatment plant is nothing but is the
combination of Dual Media Filter, Iron Remover
Filter and Softener

Water Treatment Plant with


RWP & TWP

STATION BORE WELL


Some Stations are provided with Bore well

Supply that fulfills the Water Requirement of


Station during Emergency Period.

Normally due to the high level of Hardness of


local water it is recommended that keep the
Stations Bore well OFF.

SEEPAGE SYSTEM
It is combination of two or more pumps installed at
every underground station to discharge the
seepage water from Seepage Pit to Municipal
Storm Water.
Their operation based on the level sensors signals
installed in the seepage pits
Their Master/Slave operation decided on the basis
of their run-hour recorded by the BMS
Some of the Seepage Pumps are also installed in
between the tunnels to extract accumulated water
inside the tunnel (i.e. between NDI & RCK; RCK &
PCK; BRKR & MDHS etc.)

SEEPAGE SYSTEM

To Municipal Storm
Water Main
UHL

SEEPAGE
PIT

VHL

HL
LL

SEEPAGE PUMP

SERVICE PUMPS

It is combination of two or more pumps installed at


every underground station to discharge the
Sewage/Toilet water from Sewage Pit to Municipal
Sewers/Gutters.

Their operation based on the level sensors signals


installed in the sewage pits.

Their Master/Slave operation decided on the basis


of their run-hour recorded by the BMS

SEWAGE SYSTEM

To Municipal Storm
Water Main
HL

SEWAGE
PIT
LL

SEWAGE PUMP

SEWAGE SYSTEM

These Pumps are installed at few stations (at this


time only at RCK)

They supply the soft water to the station service


tanks to fulfill the stations requirements

Other stations soft water requirements are fulfilled


by gravitational flow of soft water

SERVICE PUMPS

ONE SIDE
SERVICE
TANK
To Municipal Storm
Water Main
HL

TREATED
WATER
TANK

LL

SEWAGE PUMP

OTHER SIDE
SERVICE
TANK