Construction
Construction Lecture 2
HIGHWAYS
Highway requirements
Rigid pavements
Granular cement-bonded material overlain by
pavement-quality concrete (may be steelreinforced)
EN1304 Surveying & Construction
Pavement types
Flexible pavement
Wearing course
Surfacing
Basecourse
Roadbase
Surfacing +
roadbase
Cement-bound subbase
Concrete slab
Foundation
SUBGRADE
Formation
level
Wearing course
Basecourse
Roadbase
Foundation
Sub-base
Subgrade
Subgrade strength
In highway design the California Bearing Ratio
(CBR) test measures subgrade soil strength
CBR test:
Cylindrical plunger driven into soil at constant rate
Load measured at displacements of 2.5 and 5mm and
compared with reference very stiff soil
Maximum value of load/ref. load at the two
displacements quoted as percentage
100% matches the reference load
CBR>15%
150mm subbase
2.5%<CBR<15%
either
150mm subbase
+ capping
Subbase only
(dotted line)
CBR<2.5%
150mm subbase
+ capping
Penetration
(mm)
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
REFERENCE DATA
Load (kN)
0.34
0.43
0.51
0.60
0.68
0.76
0.84
0.91
0.98
1.05
Penetration
(mm)
2
4
6
8
10
12
Interpolate:
2.5
5.0
Load (kN)
11.5
17.6
Two choices:
22.2
1. 220 mm subbase
26.3
30.3 only
2. 150 mm subbase
33.5
+250mm capping
layer
13.03
19.90
Reference (kN)
13.03
19.90
CBR (%)
5.2
5.3
9
Aggregate
Crushed rock, slag or gravel with natural or crushed sand
Macadam
Mix of bitumen/tar + aggregate to form composite road material
10
1.0m
hardstrip
7.30m carriageway
3.65m
3.65m
Standard all-purpose
single carriageway
Centre line
1.0m
hardstrip
10.00m carriageway
5.00m
5.00m
Centre line
11
Balanced camber
Straight crossfall
12
Carriageway
Footway (1.8m)
2.5% (1 in 40)
Typical dimensions:
40mm stone mastic asphalt wearing course
60mm dense basecourse Macadam
150mm dense roadbase Macadam
Granular sub-base material
EN1304 Surveying & Construction
13
Transition curve
14
b
a
Superelevation
e = 100*b/a
120 100 85 70 60 50
2040 1440 1020 720 510 360
After M Rogers
15
Vertical Alignment
Roads normally comprise a series of sections with
straight-line gradients, between which are parabolic crest
and sag curves
Standard maximum gradients:
4% for motorways
8% for all-purpose roads
Exceptions agreed as special cases with the Highways Authority
Minimum gradient of 0.5% maintained for drainage purposes
L K pq
EN1304 Surveying & Construction
16
70
30
60
17
50
10
100 55
30
17
10
6.5
37
20
20
13
26
L K pq
After M Rogers
17
1
3
Embankment cross-section
Cutting cross-section
Whilst 1 in 3 is a standard slope for cuttings and embankments sideslopes, much steeper slopes may be achieved with reinforced earth
18
19
20
References
Highways: The location, design,
construction & maintenance of pavements
C A OFlaherty, Butterworth, 2002
Highway Engineering
Martin Rogers, Blackwell Science, 2003
http://www.pavingexpert.com
http://www.highwaysmaintenance.com
EN1304 Surveying & Construction
21
22
DRAWINGS
Drawings should be prepared before field course
In pencil on A4 paper
NOT CAD
Whats required?
Details given in lectures and Task Details document
Basis for all drawings is in the construction lectures
EN1304 Surveying & Construction
23
TASK 1: PIPELINE
Prepare an outline drawing of a suitable
precast concrete manhole at the start of
the sewer run
Sketch the bedding detail required for
such a pipe
Cover to pipe crown is 1 metre
Single lane highway runs above pipe
24
25
Formation level
Suitable
backfill
material
Varies
3. Dimensions in millimetres.
Formation level
300
Standard strength
pipes of concrete,
clayware etc
100
Suitable
backfill
material
Mix ST2
concrete
bed &
surround
Varies
150
100
As small as practical but not < 150
26
Assume:
Land cross-slope of 5%
Top of subgrade/capping layer 1m above existing
ground level
Flexible pavement construction
CBR of formation subsoil is 8%
Any fill used will be taken from the formation subsoil
EN1304 Surveying & Construction
27
Capping + subbase
28
29