Link Road Connecting Kaliamman Street to Poonamalle

Road via Nerkundram Road

Presented By:
Naveen Jaiswal-Highway Engineer
Date: 26.08.2014

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

Tender Accepted

11.10.2013

Negotiation Meeting

15.10.2013

Letter of Intent

01.11.2013

Kick off Meeting

14.11.2013

Time Period

6 Months

Inception Report

Submitted

Traffic Report

Submitted

Feasibility Report

Submitted

Revised Feasibility Report :

Submitted

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

Report

Progress

Inception report

Submitted & Approved

Traffic surveys

Submitted & Approved.


It is observed that the project Corridor has reached it maximum
capacity and additional lanes are required immediately.
As there is a restriction in the available ROW, a full length elevated
corridor, to increase the no. of lanes, is the solution.

Feasibility Report

Submitted on 26.03.2014.
Project feasible subject to availability of land
Minutes of Meeting received on 21.07.2014 instructing to submit
revised feasibility report

Revised Feasibility
Report

Submitted on 05.082014 incorporating the comments of the


Minutes of Meeting of Feasibility Report

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

1.

Project Location & Existing Alignment

2.

Background

3.

Issues in the Project Corridor

4.

Objectives

5.

Most Feasible Alignments

6.

Proposal

7.

Comments of Feasibility Report & Response

8.

Conclusion & Recommendations

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

Chennai City -TAMILNADU State

Poonamalle
Road

Kaliamman
Street

Study Corridor
1. Link Road Connecting Kaliamman
Street to Poonamalle Road via
Nerkundram Road in Chennai.

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

Project Road: Starting at


Kaliamman Koil Street and
Ends
at
Poonamalle
Highway

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

1.

Lack of uniform corridor width,

2. Road encroachments.
3. Road side Parking/halting/stopping.

4. IPT Mode Prevalent.


5. Lack of Designated and regulated Parking
6. Lack of pedestrian facilities and city drainage.

7. Lack of comprehensive Management Schemes.

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

1. Large

number

of

commercial

establishments

and

substantial number of residential building.


2. There are a number of sharp curves needed to be improved.
3. There are public amenities like Children Park, Hospitals,

Cremation Ground and Religious structures


4. Road width is insufficient to the cater the traffic
5. Connectivity of the Link Road

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

1.

Improving operational efficiency

2. Remove Bottlenecks
3. No/min Disturbance to road side properties
4. Mobility for all Pedestrian, NMT and 2 wheeler.

5. Lane space Utilization Flyover Vs. At Grade


6. Assurance of traffic flow during construction.
7. Economy & Aesthetics

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

MOST FEASIBILE ALIGNMENTS

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

This alignment is proposed on the existing alignment with minor changes in


the existing curves and with following realignments:
Realignment from ch.740 to ch.1080 (to avoid the serpentine stretch) and
After Ch. 1870 of project road
The total length of the Proposal is 2045 m

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

This alignment starts at the Kaliamman koil Street-Project Road junction and
follows the existing alignment upto Chainage 1170 and then passes through open
land along the Metro Depot and finally meets the Poonamalle High Road.
The total length of the proposal is about 1770 m

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

This alignment takes off from Kaliamman koil Street-market Road Junction and
follows the Market Road upto chainage 1375 and then realigns at the project road
upto chainage 1870 and the follows the Alternative 1A upto Poonamalle. Steep
curves and serpentine stretch have been avoided.

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

This alignment takes off from Kaliamman koil Street-market Road Junction
and then follows alternative 1B as it passes through open land along the Metro
Depot and finally meets at Poonamalle.
The total length of the alignment is 1753m

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

PROPOSAL

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

Proposed
Cross section

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

1. In this proposal 4-lane elevated corridor takes off from Kaliamman


koil Street-market Road Junction and then follows alternative 2B as it
passes through open land along the Metro Depot and finally meets
at Poonamalle.
2. Total estimated cost of construction for 4-lane flyover is Rs.
1,72,39,58,544.
3. The total length of the alignment is 1753m

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

SL.
NO

PARAMETERS

Technical Parameters
i Total Length

1753 m

ii Design Speed (Posted Speed)

50 kmph

iii Total no. of curves

iv No. of curves compliant to IRC standards

Social and Cultural Parameters


i

No. of hotspots (religious structures)


affected

Environmental Parameters
i Proposed Right of Way
ii Area of Land to be acquired

20 m
17500 sqm

iii No. of trees to be shifted

76

iv No. of utilities to be shifted

33

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

Merits
1. It is smaller in Length as compared to other proposals.
2. Land Acquisition will be least.
3. 4-lane elevated corridor to ease the traffic congestion

4. Market road will be utilized.

Demerits
1. Cost of the proposal is highest
2. Integration with existing alignment is not possible

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

Comments of Feasibility Report

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

Points to be addressed as per Minutes of Meeting


1. The consultants were requested to study both at-grade and
elevated proposal for the selected option.
2. The consultants were requested to segregate the area details of
land acquisition and structures to be affected due to L.A.
3. The consultant was requested to study the proposal of Highways
Department in the Kalliamman Street in conjunction with the

proposed proposal.

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

Points 1: At-grade vs Elevated proposal


The alignment passes through boundary of church and if we go at

grade it will require larger area at ground and demolition of


structures in the church area will become unavoidable. Whereas if
we go elevated, demolition may be avoided by options various pier

position.
The alignment passes through the built up area and hence at grade
may increase the demolition which may be avoided in case of
elevated proposal.

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

Points 2: Land acquisition & Structures affected


ROW proposed: 20 m
Total Area Required: 17500 sqm (Lump sump)
Total no. of structures affected: 19

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

Points 3: Proposal of Highways Department in


conjunction with the proposed proposal.
As per the data collected and information obtained no such proposal
are in conjunction with the proposed proposal.

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

Proposal though being highest on cost requires least land acquisition


and solves the problem of traffic congestion to the maximum
Based on economic benefits in terms of savings in VOC and savings in
travel time cost for passenger and goods vehicles of all the alternatives
Proposal 5 is recommendate.
An economic internal rate of return of 27.17% (more than 12% of
discounted rate) and positive value of INR 19,777.30 Lacs as NPV of
net benefits indicates the economic viability of project road for the
proposed improvement of proposal 5 i.e. 4 lane elevated corridor.

VKS INFRATECH MANAGEMENT PVT. LTD.


Consulting Engi neers Planners & Managers

THANK YOU