Contents
3/17/15
3/17/15
Doha Metro
Red Line
Green Line
Passenger
Rail
Freight Rail
Doha
Bahrain
High Speed
Rail
Qatar
Regional
Passenger
Rail
Light Rail
Transit
Lusail
West Bay
Gold Line
Blue Line
Qatar Integrated Rail Project (QIRP)
3/17/15
Doha Metro
Metro Network
Phase 1
Total Length:
131 km
Underground
63km
Elevated
48 km
At Grade
20 km
No. of Stations:
3/17/15
48
Doha Metro
Metro Network
Phase 2
Total Length:
100 km
Underground
37km
Elevated
53 km
At Grade
10 km
No. of Stations:
3/17/15
44
Long Distance
Passenger & Freight
Total Length:
400 km
Phase 1
135 km
Phase 2
173 km
Phase 3
92 km
Passenger:
No. of Stations:
7
Freight:
No. of Yards
5
No. of Depots
1
No. of intermodal Yards 1
3/17/15
39 km
4
No. of Stations:
No. of Depots:
3/17/15
38
1
9 km
1
No. of Stations:
3/17/15
15
How?
3/17/15
10
Qatar
National
Strategy
Qatar
National
Development
Framework
2012 - 2032
Transport
Master Plan
for Qatar
Other
Other Plans
Plans
Other
Other Plans
Plans
Qatar
Qatar Rail
Rail
Mission
Qatar Rail
Development
Program
(QRDP)
3/17/15
11
3/17/15
12
201
4
201
5
201
6
3/17/15
201
7
201
8
201
9
202
6
Q4 2019
Q1 2026
13
Project Status
3/17/15
14
Current Status
Lusail
The project is LIVE
Developing with
Lusail City Program
Will integrate with
Doha Metro
3/17/15
15
Current Status
Doha Metro
Enabling Works LIVE
PMC Contracts
awarded
U/G D&B Tenders
being evaluated
Architectural
Branding ready for
approval
3/17/15
16
Current Status
Long Distance
Obtaining land
approvals
Coordinating and
implementing GCC
requirements
Tendering for Civil
Design Consultant
Currently 25
interested parties
for detailed design
3/17/15
17
Business Opportunities
3/17/15
18
Business Opportunities
from Rail - approx. 150200
3/17/15
20
approx. 75 Projects
approx. 100 Projects
approx. 75
Projects
approx. 100
Projects
USD 25 bn out of 38 bn
revenues directly linked
to rail projects
3/17/15
21
3/17/15
22
Next steps
3/17/15
23
20142015
20162017
20182019
20202021
Q2 2013
Q4 2013
Q1 2014
Q1 2014
Q4 2015
Q2 2014
Q2 2017
Q4 2019
Start of Operations
3/17/15
24
Rolling Stock
2013
Prequalification
Issue RFP
Tender Period
Tender Evaluation
Phase
Issue Letter of Award
Implementation and
Delivery Phase
Delivery 4 x 3 Car for
System Tests
Start of Operations
3/17/15
20142015
20162017
20182019
20202021
February 2013
April 2013
6 months
3 months
Q1 2014
70 months
April 2017
October
2019
25
Systems Program
2013
Prequalification
Issue RFP
Tender Period
Tender Evaluation
Phase
Issue Letter of Award
Implementation and
Delivery Phase
Start of Operations
3/17/15
20142015
20162017
20182019
20202021
February 2013
April 2013
6 months
3 months
Q1 2014
70 months
October
2019
26
Next Steps
Approve Architectural
Branding
Finalise tender
evaluations (main Civils
U/G packages)
Appoint D&B Contractors
E/L Packages
Mitigation of risks
Targeted recruitment
Keep Doha Moving!!
3/17/15
27