Isolated
Phase
Busduct
(IPBD)
The Isolated Phase Busduct, most commonly used for large power
GENERATOR
Generator shall be Installed in non-hazardous area and it should located close to their
associate step-up transformer so as to minimize the length of heavy current connection.
TRANSFORMER
Oil filled power transformer shall be installed outdoor in a fence-in area of the
substation. The fence shall have two lockable gates.
Each transformer shall have a minimum of 1M clear space all round.
With large transformer of 100MVA and above, a blast wall between transformer bay
shall be provided.
SWITCHGEAR
Switchgear should be installed when the switchgear civil and building work are
complete so as to minimise the ingress of dust and dirt during or after erection.
Switchgear foundation as per manufacturer drawing and shall be level within the
manufacturer specified tolerence.
Substation floor shall be smooth and level to permit the handling of equipment on roller.
One separate common oil pit is required for Generator Transformer, Unit Transformers, and Station
Transformer. The criteria for sizing the Common Oil Pit shall be as follows:
The volume of new common oil pit will be 125% of the volume of oil of the transformer which
contains the largest volume of oil in transformers.
The oil pit will be closed type of water-proof concrete construction.
The oil pit will be connected to individual pit under each transformer and drain line of each
transformer will be at least 150 mm dia pipe with a minimum slope of 1:96 as per TAC Regulation.
Transformer fire/drainage of oil will be considered for only one transformer at a time.
Level of pit will be so selected that there would not be accumulation of oil/water/oil-water
Minimum Clearance between adjacent panels in a row shall be less then 200
All the cable entry holes in the substation floor or walls shall be suitable
sealed. Where such cable entry holes are required to be gas tight and/or fire
resistant, multi-cable transits blocks shall be installed, or silicone foam, weakmix concrete(in floors only) or a chemical compound with subliming heat
resistant and fire retardant properties may be used.
Instrumentation and control system interface panels should be located in the
same switchroom as the associated switchboard.
When air conditioning is provided to cool and dry the substation air in relation
to the outside air, provisions shall be made to avoid warm, humid outside air
entering directly on to electrical equipment, causing condensation.
A smoke detection system compising very early smoke detection apparatus
(VSEDA) should be installed in substations. A common alarm shall be routed
from each substation direct to the plants central fire and gas alarm system, i.e.
independent of the substation alarm annunciator.
One hand-held extinguisher shall be provided near each door. No fixed or
automatic firefighting facilities shall be provided.
Package Substation
For inter plant connections, the cables shall be routed through an overhead cable bridge
pipe cum cable bridge. For isolated but long outdoor cable route with very few cables,
the cables may be directly buried subject to the approval of the Owner.
For underground crossing of railways, road etc. additional protection shall be provided in
the form of hume pipe or concrete encased rigid steel conduits (duct bank).
A.C. and D.C. circuit will not be run in same cable.
Cables for redundant equipment system shall be run in separate trays, as far as possible.
Erection of cabling work shall be executed keeping in view all necessities and
requirements of fire fighting codes for Generating Stations having an adverse industrial
environment.
Cable bending for LV cable shall be 8D and HV cable 20D for single core cable and
12D for multicore cable.
When measurement for cables and wires are proposed, the length measured accordance
with the layout and drawings and shall be increase by 5% of the total length.\
HV& LV single core cables shall be laid trfoil group with 150mm clear space between
trefoil.
On tray or rack HV cable shall be segrgated from the LV cables.
Cable and cable support shall not be fixed directly of indirectly to plant, equipment of
process pipes which may require removal or replacement.
Cable racks or trays shall be bonded and connected to the common earth grid.
No sub zero level vault/trench shall be provided below control building/ switchroom in
the main plant building areas.
Cable entry from outdoor underground/ cable route to the building if any shall be above
the finished floor level of the building.
As a standard load carrying cables shall be laid in the single layer formation and shall only
laid in double layer with client approval.
Cable Installation shall be carried out as per IS:1255.
Cable shall be laid on the cable tray strictly in line with cable schedule.
Power & control cables shall be laid on separate tiers. In horizontal tray stacks, HT (11kv)
cables shall be laid on topmost tier and cable of subsequent lower voltage grades on lower
tiers of trays. Single core cable in trefoil formation shall be laid with a distance of four
times the diameter of cable between trefoil center lines and clamped at every two meter.
Cable Installation
Cable shall be laid on the cable tray strictly in line with cable schedule.
Power & control cables shall be laid on separate tiers. In horizontal tray stacks, HT (11kv)
cables shall be laid on topmost tier and cable of subsequent lower voltage grades on lower
tiers of trays. Single core cable in trefoil formation shall be laid with a distance of four
times the diameter of cable between trefoil center lines and clamped at every two meter.
Bending radii for cables shall be as per manufacturers recommendation and IS 1255
Where Cable cross roads/rails tracks, cable shall be laid in hume pipe/PVC pipe.
Joints less than 250meter run of cable shall not be permitted.
Control cable termination inside equipment enclosure shall have suffcient lengths so that
shifting of termination in terminal blocks can be done without requiring any jointing.
Separation- At least 300mm clearance shall be provided between HT power and LT power
cables. LT power and LT control/ instrumentation cables.
All cables associated with the one unit shall be segregated from cables of other units.
Cable Installation
Minimum number of spare cores required to be left for interconnection in control cables
shall be as follows:
2C,3C----NIL
5C ----1
7C-10C2
14C and above---3
trestle or only cable trestle. Supporting of inter plant cable trays from building
structure shall be avoided as far as possible.
Space for accommodating additional cable trays, which may come in future,
shall be provided in the cable route.
All openings in the floor and wall for cable access shall be sealed after
installation of the cable system with non inflammable materials. Thickness of
such materials shall be equal to the thickness of floor/wall. Sealing work shall be
carried out with approved sealing compound having fire withstand capability for
atleast one hour.
IE Rules
IE Rules
Rule No. 64
The following minimum safety working clearance shall be maintained for the bare conductor
or live point of any apparatus outdoor substation.
12kv-2.6meter
36kv-2.8meter
245kv- 4.3meter
420kv -6.4meter
800kv- 10.3 meter
Where transformer are used, suitable provision shall be made either by connecting with earth a
point of the circuit at lowest voltage.
A substation or switch station with apparatus having more than 2000litres of oil, shall not be
located in the basement where proper oil draining arrangement cannot be provided.
Where substation or switchstation with apparatus having more than 2000litres of oil is
installed whether indoor/outdoor, the baffle wall (4 hours fire rating) shall be provided
between apparatus.
Provision shall be made for suitable oil soakpit and where use of more than 9000litres of oil in
any one oil tank.Provision shall be made for drainge away or removal of any oil which may
leak or escape from the tank.
IE Rules
Special precaution shall be taken to prevent the spread of oil fire resulting from
the ignition of the oil from any cause and adequate provision shall be made for
extinguish any fire which may occur.
Spare oil shall not be stored in any such substation.
Only dry type transformer shall be used for installation inside the residential /
commercial buildings.
Transformer shall be protected by an automatic high velocity water spray
system or CO2.
Rule 67
All non current Carrying metal parts associated with HV/ EHV installation shall
be effectively earthed to ground system or mat which will
Limit the touch and step potential to tolerable value.
Limit the ground potential rise to tolerable values so as to prevent danger due
to transfer of potential through ground, earth wire, cable sheath, pipelines etc.
Maintain the resistance of the earth connection to such as value to make
operation of the protective devices effectively.
IE Rules
In case of star connected system with earth neutral or delta connected system
with earthed artificial neutral point.
The neutral point of transformer and generator shall be earth by connecting it
to earth system as define in rule (61). All electrical equipment shall be earthed
atleast from two distinct location.
Earth leakage protection device shall be provided below 5kw load.
In case of appreciable harmonics current flowing in the neutral connection so
as to cause interference with communication circuit, the generator or
transformer neutral shall be earthed through suitable impedance.
In case of delta connection system the neutral point shall be obtained by the
inserting grounding transformer and current limiting resistance,
Earthing system
Load condition Normal cont./ short duration/ intermittent
Permissible voltage drop
Short circuit data
Installation condition
Economic condition
Data cable joint and termination
Drum length
b) Drawing in ducts
c) Laying on racks in air
Choice of System
The choice of any of the systems given under above depends on the actual installation
conditions, initial cost of laying, maintenance and repair charges, desired ease in
replacement of any cable or adding new cables. The relative meri.ts and demerits of the
above systems are summarized in Appendix B if IS 1255
Single-core cables should not be laid individually in steel ducts but instead, all
three cables of the same system should be laid in one duct.
Cable Over Bridges -On bridges, the cables
Laying on Racks in Air
6.5.1 Inside buildings, industrial plants, generating stations, substations and
tunnels, cables are generally installed on racks fixed to the walls or supported
from ceiling. Racks may be ladder or perforated type and may be either
fabricated at the site or pre-fabricated.
Considerable economy can be achieved using standard factory made racks. The
necessary size of the racks and associated structure has to be worked out takjng
into consideration the cable grouping and permissible bending radii.
The vertical distance between the two racks should be minimum 0.3 m and the
clearance between the first cable and the wall (if racks are mounted on wall)
should be 25 mm. The width of the rack should not exceed 0.75 m in order to
facilitate installation of cables.
should preferably contain only one layer of cables. Stacking cables one above
other in 2 or 3 layers on one rack or tray reduces their current carrying
capacity to a very great extent. More than one tier trays are permissible if the
cables present cannot be accommodated in a single tray.
Ungalvanized steel work of cable rackingltrays should be painted with a coat.
of primer and thereafter finished with suitable anticorrosive paint.
Only single-core cables laid on horizontal racks need be clamped at suitable
intervals. Multi-core cables need not be clamped.
The distance between the vertical clamps should not be more than 2 m.