Risk Management

What is risk?
You have some expected outcome
Of some event in the future

Risk is the deviation of the actual future


outcome from the expected outcome
Other definitions:

Hazard: something negative that can happen in


the future
Risk is the probability of the hazard

Why risk analysis?


What does knowing the risk of some hazard
buy you?

We know we can only care about future activities


We know (or hope) that our risk analysis provides
some actionable outcomes
What are we really trying to decide?

Is the following statement be useful?

The estimated damage by hazard X would be 2


million dollars
The risk of hazard X is 1%

Risk Examples
Lets say you know the risk of permanent injury/death
of a <insert you own very fun activity here> is
1/1000 instances.
Would you perform the activity? Why? Why not?
This activity was optional. What about:

Lets say you have a disease and there is a treatment


that works 25% of the time, does nothing 50% of the
time, and results in immediate death 25% of the time
Would you perform this activity? Why? Why not?
The consequence of not performing this activity is death
within five years. You must do it now, you cant do it five
years from now.

Why identify risks?


Decide if it is worth doing
something
What is to be gained vs what could be
lost

Avoid risks when possible


Control risks when necessary
Like metrics, the outcome of risk
analysis should be something
actionable
Focus on future events

Software Risks
Project risks

Schedule slips
Cost increases

Technical risks

The problem is harder to solve than you thought it


would be
Threaten quality and timeliness

Business risks

Market risk, strategic risk, sales risk, management


risk, budget risks

Again, why analyze risk? Four


treatments exist:
Do nothing

i.e. if you dont try, you can never fail

Risk sharing

spending a little now to reduce impact later

Risk retention

the real do nothing just accept the risk

Risk reduction

reduce the probability or impact

Risk Management Paradigm


control

track

plan

RISK
analyze

identify

Step 1: identification
Generic risks every project faces
Lots of checklists for these
over time, over budget, etc.

Product-specific risks
The server on a website goes down
The touch-screen on this self-checkout is
slow
etc

Step 2: Analysis
Estimate potential likelihood
100% of a risk means it is a constraint

Estimate potential impact


Low to High
A monetary amount
Consider the nature, scope, and timing;
examples?

Determine the risk exposure


Expose = probability x impact

Sort/prioritize risks
Decide which ones you will deal with

Risk Exposure Example


Risk identification. Only 70 percent of the software
components scheduled for reuse will, in fact, be integrated
into the application. The remaining functionality will have to
be custom developed.
Risk probability. 80% (likely).
Risk impact. 60 reusable software components were
planned. If only 70 percent can be used, 18 components
would have to be developed from scratch (in addition to
other custom software that has been scheduled for
development). Since the average component is 100 LOC
and local data indicate that the software engineering cost
for each LOC is $14.00, the overall cost (impact) to develop
the components would be 18 x 100 x 14 = $25,200.
Risk exposure. RE = 0.80 x 25,200 ~ $20,200.

Step 3: Risk planning


Risk Mitigation
How to avoid the risk

Risk Monitoring
What factors indicate the risk is
happening

Risk Management
What are our contingency plans?

Quiz review

What is risk? (formal definition)


Give two examples of project risks
Give two examples of technical risks
Give two examples of business risks
Explain the four treatments for risk:
do nothing
risk sharing
risk reduction
risk retention

How do you calculate risk exposure?

In-class Exercise
Calculate the risk of failing your class
because you slept through the final
apply the four risk treatments to this risk

Identify ten risks for your term projects


Calculate the risk exposure for each risk
Decide whether to, and how to, handle each
of the risks you identified using one or more
of the four risk treatments we dicussed

Due next class