Optimization
Process
Summary
RET report
BFD/AAV audit
OPTpcs
Change requests
1.
Process for identifying and approving the requests needs to be worked out between the local
market engineers and HSPA+ assigned resources
1.
Exit criteria
Responsibilities
Region
Market
Market to submit & Region to
validate/approve
RNC/OSS SME
To make sure if all the required features in all sites and RNCs
implemented as planned.
RET Verification
Feeder Loss
Feeder Loss is an important design aspect maintain coverage, capacity & performance
Large feeder losses will reduce CPICH and the effective coverage area of the cell
- Other inconsistent values may affect Power Control & RTWP
Identify sites with more than 3dB loss, using the Feeder
Loss Dashboard link given below
If high feeder loss is accurate, identify site for possible mitigation for a
long solution as below
Feeder modification
RRU implementation
Note: These long term solutions will not be implemented during this period of optimization.
Prioritize clusters
Prioritize clusters = (% of bad CQI) * ( HS traffic)
-1st priority = quality clusters From high to low traffic
-2nd priority = RSCP clusters From high to low traffic
Note: All problem areas in the cluster even with planned
new
sites will still need to be analyzed and optimized to its
full potential
Exceptions
- Bad CQI Sites at coverage edges
For Regions
Only
2nd Priority
1st
Priority
KPIs
CQI
TPIM KPIs
1
Voice Access Failure rate (%)
<= previous round value
2
PS Access Failure rate (%)
<= previous round value
3
Voice Drop Rate (%)
<= previous round value
4
PS Drop Rate (%)
<= previous round value
5
Actual MAC-HS Cell Thpt (Mbps)
>= previous round value
6
Voice Traffic in Erlangs
>= previous round value
7
HSDPA Pay Load-RLC layer (MB)
>= previous round value
8
3G Leakage (% of 3G calls ending on 2G)
<= previous round value
9
% of 3G initiating calls on 2G (CDR Based)
<= previous round value
Note: These KPIs(1-8) are available in TPIM under the content browser by running the report NSN
HSPA KPIs. TPIM (9) can be found: http://dev.reportcenter.internal.t-mobile.com/Reports/Pages/Folder.aspx
under National Performance Reports E2E 3G Leakage Reports
All entry & exit criteria should be measured on a one week average for comparison
The same criteria will be used to monitor the cluster performance during optimization
Above listed TPIM KPIs are expected to be maintained or improved
Justification needed for 8&9 if value degraded by 2% ( to be validated from trial)
KPIs
Boomer Index: The UMTS PRACH Delay propagation measurements are compared against the
co-located GSM cell radius. A calculation is then performed based on a weighted average
Of HHO distances between the cell and its neighbors. Any instance where the 3G cells radius
exceeds the 2G cells radius >= 1.5 is flagged
DL Capacity Index: The Average Power per user is calculated taking into account Voice
Power/RL, RT SHO & Cable loss. Any cell where the Avg Power/User is > 27dBm is flagged
UL Capacity :uplink noise rise. Busy hour minus least busy hour
1
2
3
4
5
6
SHO
PRACH
Power/user
Boomer Index
RTWP
Mode
Priority
Configuration
Details
Function
Scanner (MS1)
Dual
Mandatory
Dual-mode scanner
Dual-mode scanner
Voice Long
(MS2)
UMTS
Additional
DCR, Quality
HSPA (Rocket)
(MS3)
UMTS
Additional
DL and UL Coverage Analysis using Scanners RSCP, Ec/Io and UEs TX Power and
BLER. Identify weaker coverage areas and provide solutions to improve
Pilot Pollution Analysis using Scanner data Identify areas of where there is no
single dominant pilot. Improve the servers coverage and reduce the interferers.
Identify the boomer cells and control them. Identify areas with high SHO overhead and
provide solutions to reduce it
Pilot pollution analysis for data should be done little more aggressively than for voice. Voice
can manage with multiple servers, but for the best data performance it needs only one dominant
server.
CQI target for areas of higher throughput requirement For hotspot areas to achieve
better data performance a higher CQI should be targeted (say, => 25).
HSPA Cell Change Analysis Correlate the cell change locations with Too Many
Server locations. Try to find solutions to reduce the number of cell changes in the
driven area.
Event Failure Analysis Identify and resolve any drops, blocks, IRAT failures, etc that
may have happened in the drive.
Sample:
For Dallas= SODA_C01a_S14_K01_D01_05252010_001.log
Progress Reporting
Week
HSPA+ Project Progress
Ending
July 1st 2010
CQI Optimization Progress Tracking
24
Week
Data Source: CQI Dashboard from Liberty Report
HSPA+ Project Progress
Ending
Center
July 1st 2010
re CQI samples (Range 0-10) Total More Than 5% Of A
Week
Data Source: CQI Dashboard from Liberty Report
HSPA+ Project Progress
Ending
Center
July 1st 2010
Trending Cells Where CQI (Range Of 0-10) Total >5%
Cluster
<empty>
CQI distribution
reporting based
upon Asset
clusterdefinition.
Begin vs End of
project comparison
in terms of CQI
distribution (graph
2)
Modulation Distribution
Similar
reporting based
upon the used
modulation
technique in
the cluster.
FSC reported
WoW report for
CQI
Program Tracker
Regional Level
Market Level
Activities List
Carolina
8CO0517C
Cluster: CR_01
HSPA+
Before
Priority
Critical
Important
Needed
Expected Cost
Other
$
After
Antenna Tilts
< 30 Days
30-60 Days
Parameters
Other
Implementation Time
60 90 Days
90 180 Days
Before Stats
POPS:
R99 Traffic:
HS Traffic:
CQI AVG:
Ec/Io AVG:
RSCP AVG:
Neighbors
6-12 months
12-24 months
After Stats
POPS:
R99 Traffic:
HS Traffic:
CQI AVG:
Ec/Io AVG:
RSCP AVG:
Drive Test
Other notes of interest:
______________________________________________________
______________________________________________________
______________________________________________________
______________________________________________________
______________________________________________________
______________
HSPA+
High Cost Site Mod Package
Before
After Maps
Three
RSCP and
levels compound
array at Ec/Io =12db
-92 dBm indoor RSCP
-97 dBm indoor RSCP
-105 dBm indoor RSCP
50% loading/or preferably TPIM traffic
Other information on Map
Store Locations
BANS
POPS
Solution Type
This box lists the most common
solutions that would fall into the
high cost site mod category.
Other Solutions can be written in
under the other category
Priority
Priority is based on customer
impact against other sites that
need modifications.
Expected Cost
On Air Sites
Carolina
8CO0517C
Cluster: CR_01
Answers the question of what has been completed to date to improve the
performance of the area in question
Implementation Time
The forecasted amount of time it will take to implement this solution from the
date of approval
Before Stats
Lists basic KPIs before any
optimization had been performed
on the area in question
After Stats
Lists basic KPIs after the low
cost optimization changes had
been completed.
This is NOT a prediction of
performance after this package
is implemented