Preliminary survey
Route Alignment
Profiling
Right of way
Compensation procedure
Construction of transmission
line
1.
2.
3.
4.
5.
Survey
Survey plays a very vital role in successful completion of line and
proper maintenance thereafter. Survey is the most important and
critical activity for the reasons as follows
Right of Way.
Surveys
Transmission line survey can be
divided into followings
1a. Reconnaissance
1b. Walk over survey
1c. Preliminary survey
2. Detailed survey
3. Check survey
1: 50,000
1: 25,000
Bee line
Identify possible routes (three routes)
Indicate the most feasible routes (Techno-economical
comparison)
66
C
13
10
14
66A
3
11
15
12
16
NW
NE
SW
SE
Comparison on
1.
2.
Length of route
No. of angle points with angle of deviation (type
of tower)
No. of crossing and nature (line railways high
ways and rivers etc.)
Big establishment like Military Civil aviation
Approach road
Reserved forest/sanctuary
Terrain of route
3.
4.
5.
6.
7.
Sl.
No.
Description
Unit
Type of Terrain
Prop-1
Prop-2
Prop-3
KM
61.299
61.528
63.104
a) Plain
100
100
100
b) Hill
No.
37
37
37
a) Reserved Forest
KM
b) Protected Forest
KM
c) Social Forest
KM
Mtr.
350
600
River Crossing
a) Major
b) Minor / Canal crossings
i) width
No.
2) 400 KV D/C
No.
Preliminary survey
Preliminary survey is conducted of the route
selected after walk over survey.
Preliminary Survey
Detailed survey
20 M
2M
TOPO MAP
Sending end
SS
AP
1
AP
2
AP
3
Bee
Line
AP
4
Receiving end
SS