Integrated Project Management

-2667990 Asset accounting-29.pptx

PS Master Data

-3-

667990 Asset accounting-29.pptx

Business Scenario : Investment Project E-99##

-4-

667990 Asset accounting-29.pptx

Business Scenario : Customer Project T-200##

-5667990 Asset accounting-29.pptx

Phases in a Project

-6-

667990 Asset accounting-29.pptx

Copyright 2010 Deloitte Development LLC. All rights reserved.

SAP Project System


Structures

Part 2 Project Structures


Overview of the basic data used in a project and what this data is used for:

WBS elements

Activities

Documents

PS texts

Milestones

-8-

667990 Asset accounting-29.pptx

Understand the Project Builder, and the various options it provides for working with
basic data

Workbreakdown Structures
The project definition is an outline of all objects created within a project.
The project definition contains data that affects the entire project (start and finish
dates, for example, and organizational data).

The work breakdown structure (WBS) shows the individual elements of a project
in a hierarchical structure. A WBS is the operative basis for planning further steps
in a project. Here the focus is on planning, analysis, description, control, and
monitoring costs, basic dates, and budgets.

-9-

667990 Asset accounting-29.pptx

- 10 -

667990 Asset accounting-29.pptx

Work Breakdown Structures : Structure

- 11 -

667990 Asset accounting-29.pptx

Work Breakdown Structures : Functions

- 12 667990 Asset accounting-29.pptx

The Project Builder

- 13 -

667990 Asset accounting-29.pptx

Work Breakdown Structures Operative Indicators

- 14 -

667990 Asset accounting-29.pptx

WBS: Organization and Responsibilities

- 15 667990 Asset accounting-29.pptx

WBS: Maintenance Options

- 16 667990 Asset accounting-29.pptx

WBS : Hierarchy Graphic

Activities and Networks


Activities

describe the various tasks and work involved in the project, and the
temporal and causal relationships between these tasks.
Here,

the focus is on planning, analyzing, describing, controlling, and evaluating


costs, scheduled dates, resources, and material requirements.
the Project Builder and the project planning board, you can create both WBS
elements and activities, and maintain data for these.

- 17 -

667990 Asset accounting-29.pptx

In

- 18 -

667990 Asset accounting-29.pptx

Activities and Networks: Structure

- 19 -

667990 Asset accounting-29.pptx

Activities and Networks: Functions

- 20 -

667990 Asset accounting-29.pptx

Different ways of Defining Activities

- 21 667990 Asset accounting-29.pptx

Network Graphic

- 22 667990 Asset accounting-29.pptx

Relationships

- 23 667990 Asset accounting-29.pptx

Mass Change

- 24 667990 Asset accounting-29.pptx

Sales Pricing

- 25 -

667990 Asset accounting-29.pptx

PS Texts, Documents, Milestones : Assignments

- 26 667990 Asset accounting-29.pptx

Milestones

Copyright 2010 Deloitte Development LLC. All rights reserved.

SAP Project System


Planning

Planning Business Scenario


The different planning methods will be demonstrated for projects with and
without network activities:
If projects have activities , then dates , costs , payments, capacity requirements
and material requirements can be planned automatically

If projects do not have activities , you can plan dates, costs and payments
manually

Revenues can be planned using billing elements or the SD documents assigned


to the project

- 29 -

667990 Asset accounting-29.pptx

- 30 667990 Asset accounting-29.pptx

Aspects of Planning

The Project Planning Board and Simulations


The

project planning board is a tool that enables you to process the entire project
structure (WBS elements, activities and the objects assigned to them) in an
integrated environment.
You

can simulate projects at various stages, and use this information for planning:

To estimate costs, deadlines, and capacities during the quotation phase

- 31 -

667990 Asset accounting-29.pptx

To compare various options during the course of the project. You can then use the best
option in your operative project.

- 32 -

667990 Asset accounting-29.pptx

The Project Planning Board : Objects

- 33 -

667990 Asset accounting-29.pptx

The Project Planning Board : Integration

- 34 -

667990 Asset accounting-29.pptx

Icons used in Project Planning Board

- 35 667990 Asset accounting-29.pptx

Simulation : Process

- 36 -

667990 Asset accounting-29.pptx

Simulation: Data Transfer

You

can schedule dates manually for WBS elements (as basic dates).

You

can also use activities to schedule automatically.

- 37 -

667990 Asset accounting-29.pptx

Scheduling

- 38 667990 Asset accounting-29.pptx

Dates in Projects

- 39 -

667990 Asset accounting-29.pptx

Basic Dates for WBS Elements

- 40 667990 Asset accounting-29.pptx

Scheduling

- 41 -

667990 Asset accounting-29.pptx

Basic Dates : Effects on Scheduling

Resource Planning
Resource planning refers to the following:
Planning internal processing by means of internal processing activities.
You can evaluate capacity requirements for work centers, and use the project
planning board to level capacities.
At the same time, you can also use the project planning board to distribute the
work among employees (workforce planning).

- 42 -

667990 Asset accounting-29.pptx

Planning external services by means of external processing or service activities.


In this case, purchase requisitions are generated in Purchasing (at the latest,
when the activity is released).
The purchasing department then procures the services in question externally.

- 43 667990 Asset accounting-29.pptx

Resource Planning

- 44 667990 Asset accounting-29.pptx

Internal Processing

- 45 -

667990 Asset accounting-29.pptx

Distribution of Work among Workforce

- 46 667990 Asset accounting-29.pptx

External Processing

Material Requirement Planning ( MRP )


You plan material requirements by assigning material components to activities.
Material requirements form the basis for procurement - whether the material is to
be produced in-house (production) or procured externally (purchasing).

- 47 -

667990 Asset accounting-29.pptx

You can assign material components to activities manually.


Alternatively, you can use the BOM-PS interface to assign BOM components
automatically to activities.

- 48 667990 Asset accounting-29.pptx

Materials in Projects

- 49 -

667990 Asset accounting-29.pptx

Integration with MM and PP

- 50 -

667990 Asset accounting-29.pptx

Procurement using Requirements Planning

- 51 667990 Asset accounting-29.pptx

Direct Procurement

- 52 667990 Asset accounting-29.pptx

BOM PS Interface

- 53 667990 Asset accounting-29.pptx

BOM PS Interface

Planning Costs and Revenues


You also plan costs in your projects:
Manually for WBS elements - using structure-oriented planning, cost-elementbased detailed planning, or unit costing
Automatically - using the costing data of the assigned activities
You plan revenues for projects by means of structure-oriented planning, revenueelement-based detailed planning, or PS billing plans. By assigning SD documents
to WBS elements, you can update planned revenues automatically for projects.
You can either plan payments manually using detailed planning, or write them
automatically to the project using the quantity structure of the network or billing
plans.

- 54 -

667990 Asset accounting-29.pptx

You can store different cost planning, revenue planning and payment planning
scenarios in CO plan versions, and evaluate these at a later point in time.

- 55 -

667990 Asset accounting-29.pptx

Cost Planning in Projects

- 56 -

667990 Asset accounting-29.pptx

Planned Costs in Networks

- 57 -

667990 Asset accounting-29.pptx

Planning Revenues - Methods

- 58 -

667990 Asset accounting-29.pptx

Project T- 200##: Incoming Orders and Billing Plan

- 59 -

667990 Asset accounting-29.pptx

Copyright 2010 Deloitte Development LLC. All rights reserved.

SAP Project System


Budgeting

Budget : Business Scenario

You allocate budgets for the various work packages in your investment project

You use the investment program to budget the top WBS element

You then distribute the budget of the top WBS elements among the level 2 WBS
elements

- 61 -

667990 Asset accounting-29.pptx

- 62 -

667990 Asset accounting-29.pptx

Cost Planning and Budgeting

- 63 -

667990 Asset accounting-29.pptx

Distributing Budget from the Investment Program

- 64 667990 Asset accounting-29.pptx

Budget Overview

- 65 667990 Asset accounting-29.pptx

Availability Control

- 66 -

667990 Asset accounting-29.pptx

Copyright 2010 Deloitte Development LLC. All rights reserved.

SAP Project System


Execution

Execution: Business Scenario


You use various business transactions to post actual data ( actual dates, actual
costs and actual revenues ) in both your projects

- 68 -

667990 Asset accounting-29.pptx

You can use the information system to evaluate aggregated actual data in the
project structure

- 69 -

667990 Asset accounting-29.pptx

Aspects of Project Execution

- 70 -

667990 Asset accounting-29.pptx

Basic Dates for WBS elements

- 71 667990 Asset accounting-29.pptx

Confirmation Options

- 72 -

667990 Asset accounting-29.pptx

Individual and Collective Confirmations

- 73 -

667990 Asset accounting-29.pptx

Cross Application Time Sheet ( CATS )

- 74 -

667990 Asset accounting-29.pptx

Cost Integration Using Account Assignment

- 75 -

667990 Asset accounting-29.pptx

Cost Integration using Assignment

- 76 -

667990 Asset accounting-29.pptx

Internal Activity Allocation

- 77 667990 Asset accounting-29.pptx

The Purchasing Process

- 78 667990 Asset accounting-29.pptx

Milestone Billing

- 79 667990 Asset accounting-29.pptx

Milestone Billing

- 80 -

667990 Asset accounting-29.pptx

Copyright 2010 Deloitte Development LLC. All rights reserved.

SAP Project System


Period End Closing

Period End Closing Business Scenario


You calculate overheads for your projects. You then settle projects. You use
Schedule Manager to perform period- end closing.

You draw up a results analysis for your customer project ( T-200## ) , and you
settle the project to a profitability segment.

You settle your investment project ( E-99## ) to an asset under construction /


asset

- 82 -

667990 Asset accounting-29.pptx

- 83 -

667990 Asset accounting-29.pptx

Period End closing : Procedure

- 84 667990 Asset accounting-29.pptx

Schedule Manager

- 85 667990 Asset accounting-29.pptx

Overheads

- 86 667990 Asset accounting-29.pptx

Settlement

- 87 -

667990 Asset accounting-29.pptx

Generating a Settlement rule for a WBS

- 88 -

667990 Asset accounting-29.pptx

Settlement Rules for Activities

- 89 667990 Asset accounting-29.pptx

Archiving Steps

- 90 -

667990 Asset accounting-29.pptx

Copyright 2010 Deloitte Development LLC. All rights reserved.

SAP Project System


Reporting

Reporting : Business Scenario

- 92 -

667990 Asset accounting-29.pptx

You use the Structures and Controlling Information systems to evaluate key
figures for your project

- 93 667990 Asset accounting-29.pptx

Information Systems

- 94 -

667990 Asset accounting-29.pptx

Information Systems: Degree of Detail

Structure Information System


The structure information system evaluates the structural and logistical aspects of
projects, but it is also possible to display costs, revenues, and other data in the
structure.
Benefits

is possible to edit all objects interactively (create, change, display, confirm)

Flexible

selection of columns for fields to be displayed

You

can customize icon toolbars in line with the functions used

You

can save all settings in profiles or overview variants

- 95 -

667990 Asset accounting-29.pptx

It

of using this information system:

- 96 -

667990 Asset accounting-29.pptx

Structure Overview and Individual Overviews

- 97 -

667990 Asset accounting-29.pptx

Functions in the Structure / Dates Info System

- 98 667990 Asset accounting-29.pptx

Editing All Objects

- 99 667990 Asset accounting-29.pptx

Graphical Evaluation

- 100 -

667990 Asset accounting-29.pptx

Importing and Exporting Data

- 101 667990 Asset accounting-29.pptx

Progress Analysis

- 102 -

667990 Asset accounting-29.pptx

Progress Analysis : Measurement Techniques

The Controlling Information System


The controlling information system evaluates, above all, the commercial key
figures of projects.

- 103 -

667990 Asset accounting-29.pptx

The following types of report are available here:


Hierarchy reports
Cost element reports
Line item reports (ABAP List Viewer)

- 104 667990 Asset accounting-29.pptx

Hierarchy Reports

- 105 667990 Asset accounting-29.pptx

Going to other Reports

- 106 667990 Asset accounting-29.pptx

Cost Element Reports

- 107 -

667990 Asset accounting-29.pptx

ABAP List Viewer ( ALV ) for Line Items

- 108 -

667990 Asset accounting-29.pptx

Copyright 2010 Deloitte Development LLC. All rights reserved.

Anda mungkin juga menyukai