Anda di halaman 1dari 28

1

The McGraw-Hill Companies, Inc.,

Chapter 15
Materials Requirements
Planning
The McGraw-Hill Companies, Inc.,

OBJECTIVES

Material Requirements Planning (MRP)


MRP Logic and Product Structure Trees
Time Fences
MRP Example
MRP II and Lot Sizing

The McGraw-Hill Companies, Inc.,

Material Requirements Planning


Defined
Materials requirements planning (MRP) is a
means for determining the number of parts,
components, and materials needed to produce
a product
MRP provides time scheduling information
specifying when each of the materials, parts,
and components should be ordered or
produced
Dependent demand drives MRP
MRP is a software system
The McGraw-Hill Companies, Inc.,

Example of MRP Logic and Product


Structure Tree

Given
Giventhe
theproduct
productstructure
structuretree
treefor
forA
Aand
andthe
thelead
leadtime
timeand
and
demand
demandinformation
informationbelow,
below,provide
provideaamaterials
materialsrequirements
requirements
plan
planthat
thatdefines
definesthe
thenumber
numberof
ofunits
unitsof
ofeach
eachcomponent
componentand
and
when
whenthey
theywill
willbe
beneeded
needed
Product Structure Tree for Assembly A

A
B(4)
D(2)

C(2)
E(1)

D(3)

F(2)

Lead Times
A
1 day
B
2 days
C
1 day
D
3 days
E
4 days
F
1 day
Total Unit Demand
Day 10 50 A
Day 8
20 B (Spares)
Day 6
15 D (Spares)
The McGraw-Hill Companies, Inc.,

First,
First, the
the number
numberof
of units
units of
of A
A are
arescheduled
scheduled
backwards
backwards to
to allow
allowfor
fortheir
theirlead
lead time.
time. So,
So, in
in the
the
materials
materials requirement
requirement plan
plan below,
below,we
wehave
haveto
toplace
place
th
an
an order
orderfor
for50
50 units
units of
of A
A on
on the
the 99th day
day to
to receive
receive
them
them on
on day
day 10.
10.
Day:
A Required
Order Placement

10
50

50

LT = 1 day

The McGraw-Hill Companies, Inc.,

Next,
Next,we
weneed
needto
tostart
startscheduling
schedulingthe
thecomponents
componentsthat
thatmake
makeup
up
A.
A. In
Inthe
thecase
caseof
ofcomponent
componentB
Bwe
weneed
need44Bs
Bsfor
foreach
eachA.
A.
Since
Sincewe
weneed
need50
50As,
As,that
thatmeans
means200
200Bs.
Bs. And
Andagain,
again,we
weback
back
the
theschedule
scheduleup
upfor
forthe
thenecessary
necessary22days
daysof
oflead
leadtime.
time.
Day:

A Required
Order Placement
B Required
Order Placement

20

LT = 2
A
B(4)
D(2)

20

50
200

10
50

200

Spares
4x50=200

C(2)
E(1)

D(3)

F(2)
The McGraw-Hill Companies, Inc.,

Finally,
Finally,repeating
repeatingthe
theprocess
processfor
forall
allcomponents,
components,we
wehave
havethe
the
final
finalmaterials
materialsrequirements
requirementsplan:
plan:
Day:
A
LT=1
B
LT=2
C
LT=1
D
LT=3
E
LT=4
F
LT=1

Required
Order Placement
Required
Order Placement
Required
Order Placement
Required
Order Placement
Required
Order Placement
Required
Order Placement

20

20

50
200

10
50

200
100

55
20

400

55

400

20

200

100
300

300

200
200
200

A
Part D: Day 6

B(4)
D(2)

C(2)
E(1)

D(3)

40 + 15 spares

F(2)

The McGraw-Hill Companies, Inc.

Master Production Schedule (MPS)


Time-phased plan specifying how many and
when the firm plans to build each end item
Aggregate
Aggregate Plan
Plan
(Product
(Product Groups)
Groups)

MPS
(Specific End Items)

The McGraw-Hill Companies, Inc.,

10

Types of Time Fences


Frozen
No schedule changes allowed within this window
Moderately Firm
Specific changes allowed within product groups as
long as parts are available
Flexible
Significant variation allowed as long as overall
capacity requirements remain at the same levels

The McGraw-Hill Companies, Inc.,

11

Exhibit
Exhibit15.5
15.5

Example of Time Fences


Moderately
Firm

Frozen

Flexible

Capacity

Forecast and available


capacity
Firm Customer Orders

15

26

Weeks

The McGraw-Hill Companies, Inc.,

12

Material Requirements Planning System


Based on a master production schedule, a
material requirements planning system:
Creates schedules identifying the specific parts
and materials required to produce end items

Determines exact unit numbers needed

Determines the dates when orders for those


materials should be released, based on lead
times

The McGraw-Hill Companies, Inc.,

13

Aggregate
product
plan

Firm orders
from known
customers

Engineering
design
changes

Forecasts
of demand
from random
customers

Master production
Schedule (MPS)

Bill of
material
file

Primary reports
Planned order schedule for
inventory and production
control

Material
planning
(MRP
computer
program)

Inventory
transactions
From
FromExhibit
Exhibit15.6
15.6

Inventory
record file

Secondary reports
Exception reports
Planning reports
Reports for performance
control
The McGraw-Hill Companies, Inc.,

14

Bill of Materials (BOM) File


A Complete Product Description

Materials
Parts
Components
Production sequence
Modular BOM

Subassemblies

Super BOM

Fractional options
The McGraw-Hill Companies, Inc.,

15

Inventory Records File


Each inventory item carried as a separate file

Status according to time buckets

Pegging

Identify each parent item that created demand

The McGraw-Hill Companies, Inc.,

16

Primary MRP Reports


Planned orders to be released at a future time
Order release notices to execute the planned
orders
Changes in due dates of open orders due to
rescheduling
Cancellations or suspensions of open orders due
to cancellation or suspension of orders on the
master production schedule
Inventory status data
The McGraw-Hill Companies, Inc.,

17

Secondary MRP Reports


Planning reports, for example, forecasting
inventory requirements over a period of time
Performance reports used to determine
agreement between actual and programmed
usage and costs
Exception reports used to point out serious
discrepancies, such as late or overdue orders

The McGraw-Hill Companies, Inc.,

18

Additional MRP Scheduling Terminology


Gross Requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipt
Planned order release
The McGraw-Hill Companies, Inc.,

19

MRP Example
Item
X
A
B
C
D

X
A(2)
C(3)

B(1)
C(2)

On-Hand Lead Time (Weeks)


50
2
75
3
25
1
10
2
20
2

D(5)

Requirements
Requirementsinclude
include95
95units
units(80
(80firm
firmorders
ordersand
and15
15forecast)
forecast)of
ofXX
in
inweek
week10
10

The McGraw-Hill Companies, Inc.,

20
Day:

A(2)

ItIttakes
takes
22As
Asfor
for
each
eachXX

X
LT=2
Onhand
50
A
LT=3
Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

10
95

50 50

50

50

50

50

50

50

50

50
45
45

45
90
75 75

75

75

75

75

75

75
15
15

15
45
25 25

25

25

25

25

10

10

35

25
20
20

20
40

45
10 10

25

10
35
35
40

40
40
100

20 20

20

20

20

20

20
80
80

80
The McGraw-Hill Companies, Inc.,

21
Day:
X
LT=2

A(2)

B(1)

ItIttakes
takes
11BBfor
for
each
eachXX

Onhand
50
A
LT=3
Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

10
95

50 50

50

50

50

50

50

50

50

50
45
45

45
90
75 75

75

75

75

75

75

75
15
15

15
45
25 25

25

25

25

25

10

10

35

25
20
20

20
40

45
10 10

25

10
35
35
40

40
40
100

20 20

20

20

20

20

20
80
80

80
The McGraw-Hill Companies, Inc.,

22
Day:
X
LT=2

A(2)

C(3)

ItIttakes
takes33
Cs
Csfor
for
each
eachAA

B(1)

Onhand
50
A
LT=3
Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

10
95

50 50

50

50

50

50

50

50

50

50
45
45

45
90
75 75

75

75

75

75

75

75
15
15

15
45
25 25

25

25

25

25

10

10

35

25
20
20

20
40

45
10 10

25

10
35
35
40

40
40
100

20 20

20

20

20

20

20
80
80

80
The McGraw-Hill Companies, Inc.,

23
Day:
X
LT=2

A(2)

C(3)

B(1)

C(2)

ItIttakes
takes22
Cs
Csfor
for
each
eachBB

Onhand
50
A
LT=3
Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

10
95

50 50

50

50

50

50

50

50

50

50
45
45

45
90
75 75

75

75

75

75

75

75
15
15

15
45
25 25

25

25

25

25

10

10

35

25
20
20

20
40

45
10 10

25

10
35
35
40

40
40
100

20 20

20

20

20

20

20
80
80

80
The McGraw-Hill Companies, Inc.,

24
Day:
X
LT=2

A(2)

C(3)

B(1)

C(2)

D(5)

ItIttakes
takes55
Ds
Dsfor
foreach
each
BB

Onhand
50
A
LT=3
Onhand
75
B
LT=1
Onhand
25
C
LT=2
Onhand
10
D
LT=2
Onhand
20

Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release
Gross requirements
Scheduled receipts
Proj. avail. balance
Net requirements
Planned order receipt
Planner order release

10
95

50 50

50

50

50

50

50

50

50

50
45
45

45
90
75 75

75

75

75

75

75

75
15
15

15
45
25 25

25

25

25

25

10

10

35

25
20
20

20
40

45
10 10

25

10
35
35
40

40
40
100

20 20

20

20

20

20

20
80
80

80
The McGraw-Hill Companies, Inc.,

25

Closed Loop MRP


Production Planning
Master Production Scheduling
Material Requirements Planning
Capacity Requirements Planning

No
Feedback

Realistic?

Feedback

Yes
Execute:
Capacity Plans
Material Plans

The McGraw-Hill Companies, Inc.,

26

Manufacturing Resource Planning


(MRP II)
Goal: Plan and monitor all resources of a
manufacturing firm (closed loop):

manufacturing
marketing
finance
engineering

Simulate the manufacturing system

The McGraw-Hill Companies, Inc.,

27

Lot Sizing in MRP Programs

Lot-for-lot (L4L)
Economic order quantity (EOQ)
Least total cost (LTC)
Least unit cost (LUC)
Which one to use?
The one that is least costly!

The McGraw-Hill Companies, Inc.,

28

End of Chapter 15

The McGraw-Hill Companies, Inc.,

Anda mungkin juga menyukai