Presentation Sequence
Based on the cost and schedule of past and planned projects of lower
or similar complexity, the review panel believes that the NGAO project
cost and schedule are not reliable and may not be realistic.
Contingencies are also too tight. In particular, the time of 18 months
allocated for manufacturing and assembly and 6 months for integration
and test, is probably optimistic by a large amount.
Clarification: Reviewers thought our lab and telescope I&T durations were
smaller by 2x than our plan (they are 6 & 12 months, respectively).
3
During PD, we will revise the basis of estimate to move more items from
engineering judgment and analogy to direct vendor quote basis
Reviewers felt that the laser procurement needs more time & should start
much earlier. We agree.
WBS dictionary
Major deliverables
Estimates of labor hours
Estimates of non-labor dollars (incl. tax & shipping) & travel dollars
Basis of estimate (e.g. vendor quote, CER, engineering judgment)
Contingency risk factors & estimates
Descope options
Goal of Comparison:
Increase confidence in the NGAO cost estimate
Products
Updated cost estimation data base to take advantage of comparison information
Cost comparison presentation (this presentation)
Approach
Identify differences between systems
Identify differences in assumptions
Identify similarities & differences in effort & procurement estimates, &
resolve/justify these differences
As appropriate update the NGAO cost estimate
Identify other support for NGAO estimates
Respond to reviewer sense that methodology good, but not fully executed
NFIRAOS used as shorthand for the full TMT 1st light AO configuration
Updates to TMT cost estimate since 2006 (globally < 5%) not incorporated
6
Cost Comparisons
(in FY08 $ as reported at the SDR)
30 m versus 10 m
~ 3x physical size of AO system
3x smaller image more sensitive to image motion & vibrations
3x more perspective elongation more laser power for same performance
&/or better detectors
9x LGS focus change with zenith angle (1.4 m from zenith to 65)
Physical paths for laser beam transport much longer
9x4x3m
(blue) box
3.8 m
9
10
11
12
> $1M
> 5 wy
AO System Comparison
3.1
m
Entire assly is
~ 0.5 x 0.5 m
MCAO vs MOAO
NFIRAOS DMs need to be developed
NGAO DMs are commercially available
ROM for MEMS64 (being developed for GPI)
18
RTC Comparison
19
The SDR reviewers questioned whether 100W would be adequate for the highest order
correction
After re-assessment we believe that 100W has sufficient margin by a factor of at least 1.5
20
21
I&T Comparison
NGAO has more labor in all but one category than NFIRAOS
NFIRAOS laser lab I&T includes a full off-telescope system test
NFIRAOS tel. I&T only covers to beginning of science commissioning
~ 25% of NGAO AO telescope I&T is for science commissioning
NGAO estimate takes into account past experience with a detailed breakdown
Possibility that we are not comparing apples to apples
NFIRAOS may cover some under system eng. & I&T contingency
NGAO assumes that each subsystem is complete & has met its requirements prior to lab I&T (presumably also
true for NFIRAOS)
22
Contingency
Comparison
$7.7M NGAO contingency
$22.0M NFIRAOS contingency
Laser: NGAO 19% contingency too low. 50% would require $2M more.
I&T: NGAO plan has ~1.7x more labor excluding science commissioning
23
Conclusions
NGAO is traceably less expensive than NFIRAOS & we
understand why
Some areas identified that require more work:
Contingency rates need to be re-evaluated
At minimum should be increased for laser & potentially for RTC