TPM

List of approved TPM Pillars & Improvement Team


Routes
Manufacturing

Note: Changes Summary page 3

Revision: 06

Page 1

Date: May 2013

Document Type: TPM Standard

HMESC: 01.10.13.041

Filename: List of approved TPM Pillars & Improvement Team Routes

HMESC: 01.10.13.041

Revision 06, May 2013

Issued By: C. Kerr

Contents
The purpose of this file is to document the approved and
latest versions of:
Driving
Pillar

System, Organisation & Change Management Contents

Routes

Improvement

Routes

Kaizens
RCFAs

Page 2

HMESC: 01.10.13.041

Revision 06, May 2013

Summary This Revision (May 2013)


Safety (SHE) Pillar

Environmental Steps added (note for already Bronze Breweries)

DS and Org & C Mgt

New HPO model and route

FI Pillar

New FI Pillar Step 5 for Energy and Water including roadmap to 2020 E&W vision

AM

No change

Project & Early Equipment Mgt Pillar

No change

PM Pillar

Removed Breakdown Reduction, Route - recommend to use RCFA or Kaizen. Removed Minor
Stoppage Reduction Route recommend to use MSAS. Removed Speed Loss Routes
recommend to use Kaizen.

PQ Pillar

Quality Roadmap, linked to Bronze, Silver Gold

T&E Pillar

New PD Pillar is under construction,. Will be issued by end Q2 2013

Early Product Management Pillar

Page 3

Under construction. Will be issued end Q2 2013

HMESC: 01.10.13.041

Revision 06, May 2013

Safety Pillar Contents

Pillar Route
Improvement Routes
Reduction of accidents, incidents and near misses team route
Operational Risk Reduction (ORR) team route

Page 4

HMESC: 01.10.13.041

Revision 06, May 2013

TPM Safety Pillar Route

Page 5

HMESC: 01.10.13.041

Revision 06, May 2013

1. Introduce management of change (MOC) for all changes ,m/c


modification, chemical,
2. Define safety aspects & communication in DCS & perform safety
promotion
3. Develop approach on emergency planning & response
4. Define all safety aspects, controls in contractor management
5. Imbed basic safety training for all employees & advanced training for
1. Assess with T&E Pillar know
H&S experts
how on safety, perform training
6. Integrate / optimize safety, 5S,
to close the gaps
hygiene, audits
2.
Extend information coming from
7. Manage the plan of best practices,
safety pyramid e.g. near
horizontal expansion (internal &
misses
external sources)
3.
Develop cultural, behavioural
8. Monitor implementation &
aspects (including maturity
effectiveness of long term actions
checks, PPE audits, unsafe acts,
1.9. Prepare,
plan
&
perform
hazard
Systematically update risk
conditions, observations)
identification
&
risk
assessment
assessment & reduce residual risk
4. Define critical safety behaviours
across the site
5. Analysis & address behavioural
2. As priority define & implement risk
anomalies via training & Poka
management for risk of death &
Yoke devices
serious injury
6. Introduce checklist to audit
3. Prepare operational risk
safety standards application
reduction
team roll out plan
7. Define rewarding system both
for site & execute
for safety results & contribution
4. Ensure safety approval e.g. of CILTs,
to improve safety
OPLs, SOPs & maintenance stds to
8. Define sanction system for
ensure safe working practices
breaches
with safety
safety experts
discipline
5. Introduce safety VM, signage &
1. Select
& train
/
physical e.g. walkways, PPE,
champions in all departments
machine Poka Yoke
2. Perform accident & incident
6. Review work permit & LOTO
analysis to establish root
procedures
cause(s) via 5Why
7. Improve ergonomics &
3. Prepare & execute
environmental conditions light,
1. Assess all current activities performed countermeasures plan
noise, temp
4. Start horizontal expansion of
for safety
actions
to similar areas
2. Introduce & assess safety pyramid, formalise
KPIs

TPM Safety Pillar Route

Use the safety system


established to further
improve safety

Focus on people via


safety competences,
culture
&
behaviours

Hazard identification &


risk management

Systematically analyse
accidents & incidents

1
Page 6

3. Assess conformance to (HeiQ) Rules, Standards & Procedures via


HeiQuest & legal requirements. Make gap analysis on both & prepare
Identify safety priorities
action plan to close actions
& restore, achieve
4. Define visitor & contractor safety induction program
5. Define, review work permit system, LOTO & PPE procedures
basic conditions
6. Perform accident, incident (vertical) deployment, define priorities,
set targets & prepare improvement action plan
7. Ensure safety aspects
are included
5S activities & audits
HMESC: 01.10.13.041
Revision
06, Mayin
2013
8. Introduce safety tagging system to identify unsafe conditions

TPM SHE Pillar Route

New

ENVIRONMENT

SAFETY

Page 7

HMESC: 01.10.13.041

Revision 06, May 2013

TPM SHE Pillar Route - Environmental Steps

New

1. Map Solid Waste, Waste Water, Water & CO2 emission current
status
2. Make gap analysis to set priorities
3. Monitor data & solve anomalies
4.Identify improvement opportunities (Renewable Energies, Waste &
Waste
Water reduction, recycling, etc.)
5. Define new standards & visual management
6. Benchmarking & good practice sharing
7. Integrate/optimise SHE management system

1. Assess all current activities performed for environment


2. Implement a monitoring system for all KPIs and PIs & set
targets
3. Evaluate data collection system and data quality
4. Identify priorities via vertical deployment
5. Identify training gaps for all employees, visitors &
contractors
6. Achieve/restore basic conditions via 5S, tagging, audits
7. Systematically analyse accidents, incidents & near misses
8. Assess/establish environmental key systems (air & noise
emission
control, spill protection, hazardous chemicals transportation
& storage,
waste disposal system, other systems)
9. Hazard identification & risk management
10. Focus on people via competences, culture & behaviors
11. Include environmental aspects into existing systems (MOC,
DCS,
emergency, long term action plans, etc.)

Page 8

HMESC: 01.10.13.041

Revision 06, May 2013

Reduction of Accidents, Incidents and Near Misses


Team Route

Page 9

HMESC: 01.10.13.041

Improve management
system to hold the gains

Revision 06, May 2013

Reduction of Accidents, Incidents and Near


Misses
1.Review
& update as necessary
reward & recognition system to
Team Route
hold the gains

1.Determine the root cause(s)


using
5 Why analysis
2.Apply countermeasures r(using
hierarchy of control approach)
reviewing all aspects of man,
method, machine, material,
management & environment.
Where possible implement visual
management (VM) solutions,
poke yoke devices (refer to HeiQ)
3.Update workplace standards
4.Formulate requirements (with
Line Mgt) for implementation at
the workplace
5.Train people in new standards

2.Define critical behaviours


required to hold the gains
3.Integrate new standards in
workplace standards, 5S, CILTs,
PM systems ....
4.Update DCS/ MCRS system with
trigger points & analyse anomilies
5.Update risk assessment as
necessary
1.Assess & restore compliance with
workplace standards / rules,
standards & procedures in HeiQ
2.Perform safety tagging on
identified critical area(s) to
identify physical anomalies,
hazards - e.g. ergonomics, design,
wrong tools, PPE, fall, contact,
projection of material, chemical,
mobile vehicles, particular
environments...
3.Review 5S status & restore & / or
define new standards e.g. VM...
4.Understand behavioural aspects
(e.g via behavioural audits)
including records on PPE audits,
unsafe acts, conditions,
observations. Highlight & action
anomalies
5.Assess know how on safety of
critical areas, accident, incident
mode(s) & near
misses.
Highlight &
action anomalies
6.Review existing risk
assessment

1.Understand the current situation


by analysing all the historical
data, team assignment letter &
deployment of safety data (all
safety pyramid data, reference
HMESC 01.41.12.110)
2.Improve data collection as
necessary
3.Identify critical areas related to
accidents, incidents, near misses
under investigation
Note: at end of each step summarise
4.Identify clearly the accidents,
impact on problem and key
incidents, near misses mode(s)
Revision 06, May 2013
Page 10
learning'sHMESC: 01.10.13.041to attack

Operational Risk Reduction Team Route (ORR)


6
5
4
3
2
1

Page 11

Standardisation

Define & implement


countermeasures for
risks

Detailed Risk
Assessment

Identification of hazards
& hazard controls

Restoring Basic
Conditions

Data Collection

HMESC: 01.10.13.041

Revision 06, May 2013

Operational Risk Reduction Team Route (ORR)


6

Standardisation

Define & implement


countermeasures for
risks

Detailed Risk
Assessment

Identification of hazards
& hazard controls

Restoring Basic
Conditions

Data Collection

1.Make communication/machine
board
2.Define safety audit combined
with AM/5S audit
3.Develop indicators &
monitoring system

1.Investigate risks & define


countermeasures
2.Prepare an implementation plan
3.Update Operational Standards
4.Train personel
5. Monitor behaviour of people & analyse
anomalies
6. Residual risk calculation & conclusions
1.For each risk estimate
7. Long term actions coming from
frequency, probability and
conclusions
severity
2.Calculate Risk level incl. Assess
risk reduction by hazard
controls)
1.Identify all hazards on area
3.Make
a list of priority risks
2.Make a link between tasks, zones,
1.Restore the work area(s)
risks
according to latest existing
3.Identify existing hazard controls
safety standards (e.g. PPE,
shutdown...)
2.Carry out tagging , reinforce 5S
& define new, missining
standards as required
1.Analyse assignment letter
(standards should be visual)
2.Collect data about composition of the
3.Train personel
crew and list all activities
3.List tools and products ( e.g. chemicals) to be used
4.List energies operating the equipment
5.Define indicator and set the target

Note: at end of each step summarise


impact on problem and key
learning'sHMESC: 01.10.13.041
Page 12

Revision 06, May 2013

Driving System
Organisation & Change Management Contents
HPO Model & Route

Page 13

HMESC: 01.10.13.041

Revision 06, May 2013

The Leadership Team


Note: Leadership Team replacing the Steering
Committee in our TPM Architecture

HPO

HPO
HPO

Concept
Concept

Ldr Team

Leadership Team

Driving
Driving System
System
Process
Process

Results
Results

HPO - High Performance Organisation Model /


Route
... a tool / method for the Leadership Team
Page 14

HMESC: 01.10.13.041

Revision 06, May 2013

HEINEKEN HPO Principle: Model Overview

New
Business
Results

Future Business Situation

Current Business Results

What is required of our organisation in


the future
1.Company requirements
2.Social, political, legal expectations
3.Competitive pressure
4.Expectations of employees
5.Then the Hard Numbers

What the organisation delivers now


1.Extend to which Company
requirements are met
2.Social, political, legal conduct
3.Position relative to competition
4.Extend to which employee expectations
are realised
5.Then the Hard Numbers results

Business (Operating) Strategy


1.Vision, mission
2.Strategy
3.Operating principles, underlying
values & assumptions
4.Objective & goals (KPIs)

Structure

Rewards

Decision
Making

Tasks

People

Information

Culture
How the organisation really operates
1.Attitude towards strategy & goals
2.Actual distribution of power & rewards
3.Actual work people do/dont do
4.Other norms that explain how things
get done (or not)

Organisation Design
Elements
* Source: Hanna-High Performance Organizations

Page 15

HMESC: 01.10.13.041

Revision 06, May 2013

HEINEKEN HPO Principle:


Defined Theme & Assessment Loop
(Step 1) Define the theme

Future
Business
Situation

(Step 2) Identify Gaps

New
Current
Business
Results

(Step 5) Know & Assess

Business
(Operating)
Strategy

Design
Elements (DE)
(Step 4) Identify Issues

Page 16

HMESC: 01.10.13.041

Revision 06, May 2013

Culture
(Step 3) Examine

HEINEKEN HPO Principle: Re-Design Loop &


Consolidate Key Findings to
prepare for Implementation

New
Current
Business
Results

Future
Business
Situation

(Step 9) Prepare for


implementation

Page 17

Business
(Operating)
Strategy

Design
Elements (DE)

(Step 6) Define new

(Step 7) Changes to

HMESC: 01.10.13.041

Culture
(Step 8) Predict
impact of DE

Revision 06, May 2013

HEINEKEN HPO Route (1)

New
Steps 6 8
ReDesign
Process

Steps 2 5
Assessmen
t Process

Page 18

HMESC: 01.10.13.041

Revision 06, May 2013

HEINEKEN HPO Route (2)

New

1.Know the current business (operating) strategy formal & unwritten to identify if they are a reason(s) for the critical issues identified in the d
2. Assess the fit between the actual operating strategy & what the busines
situation
requires in the future
(Vision, Mission, Strategy, Operating Principles, underlying values and
assumptions,
Objectives & Goals (KPIs))
1. Assess one by one the critical cultural aspects & behaviours in respect of
the 6 design elements (this identifies the design strengths &
opportunities )
2. At the level of design element (if possible) cluster the issues by common
problems
3. Prioritise the issues to be solved
1. With the team examine how each result (good or bad) is achieved & ask
which organisational cultural aspects / behaviour(s) can be responsible
for it?
2. Confim at the GEMBA what the people say & what you see (focus on
observable behaviour)
3. Prepare a statement of positive behaviours we want to keep
4. Priortise the critical cultural aspects / behaviour(s) that need to
investigated further
1. Describe the future situation in terms of hard numbers, company
requirements social, political, legal expectations, competitive pressure &
expectations of employees
2. Identify the current results
3. Perform a gap analysis - determine which results need to improve &
which should be maintained (good & on track)
4. Prioritise the gaps to define the order in which they will be addressed
1. Define the theme & boundary, assemble the right group of people
2. Identify & map the entities that interact with the boundary
3. Describe the existing tranactions (formal processes) & relationships
between the boundary & each entity
4. Map the influence of the different entities on the boundary results
Page 19

HMESC: 01.10.13.041

Revision 06, May 2013

HEINEKEN HPO Route (3)

New
1. Prepare a comprehensive summary of the changes to be implemented
1. Revised operating strategy
2. Detailed list of changes to the design elements
3. Communication plan
4. Major changes expected in organisational culture

1. Identify the positive & negative impacts the new design elements will
have on the organisational culture
2. Re-visit & adjust the design of the 'Diamond' in order to avoid the
predicted negative impacts

1. List the tasks that need to be performed in order to fulfill the new
operating strategy
2. Develop the other 5 design elements to reinforce the high performance
of these tasks. (Ensure all new design elements are cross-checked to fit
with new operating strategy)
1. Assemble again the team members to discuss, confront each other &
eventually reach a consensus on each point (as below) of the new
operating strategy
1. Purpose, vision & mission statement
2. Competitive strategy
3. Operating Principles
4. Objectives & goals
5. Underlying values & assumption

Page 20

HMESC: 01.10.13.041

Revision 06, May 2013

Focused Improvement Pillar Contents

Pillar Route
Improvement Routes
Changeover Time Reduction
Team Efficiency
Energy Reduction

Page 21

HMESC: 01.10.13.041

Revision 06, May 2013

TPM Focused Improvement Pillar Route

Page 22

HMESC: 01.10.13.041

Revision 06, May 2013

1. Understand the current situation


TPM Focused Improvement Pillar Route
2. Develop from standard &

1. Create vision & roadmap towards


implement the DCS that fits
E&W corporate targets (e.g . 2020
your site in pilot area
BaBF)
3. Create plan to expand & follow
2. Define & install E&W audit system to up system effectiveness
RBC on general weaknesses
3. Understand current situation,
measurement system & analysis
deviations
4. Close gap to benchmark (UBM) via
appropriate tools & routes
5. Challenge consumption to
technological limits via appropriate 1. Perform detailed productivity
tools & routes
deployment (linked to PCM)
6. Prepare business case for equipment2. Develop the resource &
extension, modification,
productivity plan (priorities,
replacement
to achieve
targets & links to other pillars)
world class E&W levels
3. Improve resource saturation by
1. List & deploy out of production
improvement activities & team
activities
routes
2. Standardise indirect tasks, create
vision & plan to improve
1. Restore basic conditions - list all
3. Improve effectiveness of
planned activities with respect to
remaining out of production
start-up, changeover, shut down
time (overmanning)
& cleaning and ensure that
4. Set-up daily/weekly meetings for
standards & SOPs are defined
organisational losses
and followed
2. Define visual management
standards for the site,
1. Restore the measurement system
investigate innovations for Poka
& data collection
2. Deploy production cost & set prioritiesYoke, identify good practices
3. Perform high level loss deployment 3. Deploy line/machine losses and
define priorities for improvement
4. Deploy volume & productivity
and improve the standards e.g.
(machine & labour)
by using the appropriate route
5. Link losses to costs and calculate
4.
Manage horizontal expansion of
potential savings
solutions and long term actions
6. Set vision and targets
7. Make an improvement plan and assignto achieve world class level

New
Step
5

Page 23

improvements to all pillars


8. Continuously support Driving System by
HMESC: 01.10.13.041
Revision
06, May
2013
accurate measurement
of results
and
loss
deployments

Changeover Time Reduction Team Route

Page 24

HMESC: 01.10.13.041

Revision 06, May 2013

Changeover Time Reduction Team Route

Page 25

1.Finalise machine standards


and provide training
2.Establish a pre & post check
1.Identify all key failure points
verification system
during
3.Track the changeover & run up
run up after changeover
performance on DCS
2.Analyse settings and
4.Identify the constraints that
adjustments related to key
limited further changeover time
failure points
reduction
3.Convert adjustments to settings,
5.Define good/best practices for
visualise set points, do Poka Yoke 1.Sequence
the tasks to optimise
horizontal expansion
the c/o
4.Standardise and control the
remaininginternal
adjustments,
visualise
1.Identify
& external
tasks 2.Improve VM (visual management)
&(also
Pokapre
Yoke
of tools and change parts
and post)
2.Re arrange the tasks in pre, post 3.Challenge individual tasks on
micro level to further reduce the
and internal
c/o time, implement Poka Yoke
3.Reduce variation by defining
solutions
current best standard (v1) with
pre and post checklist and internal 4.Implement countermeasures for
sequences and task time reduction
c/o procedure
5.Re-define
the new best standard
4.Convert internal to external tasks
(v3)
(analysis), challenge VA versus
NVA
1.Prepare study team and operation
5.Convert internal to external tasks
team
(countermeasures)
2.Perform the study, observe the
1.Confirm
deployment
andstandard
project
6.Re-define
the new best
changeover
scope
(v2) (line & machine level),
3.Collect data and observations &
introduce KPIs
visualise the changeover process
2.Understand the vision for
4.Summarise initial findings and
changeover
observations on macro level
3.Restore basic conditions on all
5.Introduce performance tracker
standards (establish base line)
with step results
4.Check for current good
practices available internally &
externally
5.Set the team target
6.Create project plan Revision 06, May 2013
HMESC: 01.10.13.041

Team Efficiency Improvement Team Route

Note: at end of each step summarise


impact on problem & key learnings

Page 26

HMESC: 01.10.13.041

Revision 06, May 2013

Team Efficiency Improvement Team Route


1. Define the final standard of the crew
2. Intergrate new situation in Skill
Management System
3. Define performance indicator to measure
results
4. Introduce the follow up of the results &
integrate in DCS to ensure perfect
1. Define the system to follow up
execution
results
2. Record anomalies
3. Investigate all anomalies, define
& implement countermeasures
4. As required update standards &
re-train personnel
1. Ensure the best availability of
information to perform tasks
effectively
2. As required review decision
making process (RACI matrix)

1. Identify the focus area, list crew &


structure
2. Restore basic conditions on
standards already in place
3. List all tasks & measure saturation
of resources
4. Define performence indicator & set
improvement target

Page 27

HMESC: 01.10.13.041

1. Classify all tasks list ed &


idenfify improvement
opportunities
2. Deeply analyse priority tasks &
define countermeasures via:
3. Measure & improve MTBT
4. Re-calculate th ideal crew
5. Create the best standard (s) &
train personnel
6. Identify opportunities to
further improve via VM, Poke
Yoke...
7. Measure saturation of
resources
8. Review standards of non
production activities of the
team

Revision 06, May 2013

Energy Reduction Team Route


5

Page 28

Define standards to
maintain results

Monitor results and


investigate deviations

Restore basic conditions

Understand current
situation

HMESC: 01.10.13.041

Revision 06, May 2013

Energy Reduction Team Route


1. Update working procedures
2. Set up a monitoring system
3. Update the maintenance
plan
4. Define the trigger points
and the standard procedure
in case of deviation

1. Define technological limit for


energy consumption; ideal
conditions
2. Identify losses due to non-ideal
conditions
3. Define causes to be not at the
ideal conditions
4. Improve current conditions with
countermeasures and improve
standards
5. Train operators and technicians
with new standards
6. Identify indicators and set up a
monitoring system
1. Split main area into working
areas
2. Deploy energy consumption
based on current level of
measurement or QA matrix
3. Set priority & define critical
sub areas
4. Set target for main area or sub
area according to level of
measurement

Note: at end of each step summarise


impact on problem and key
Page 29
learnings HMESC: 01.10.13.041

1. Monitor results and identify


deviations
2. Find root causes by using
5Why
3. Define countermeasures and
implement them
4. Train operators and
technicians

1. Inspect critical area and tag


abnormalities
2. Solve abnormalities
3. Restore all working
procedures including
maintenance procedures
4. Train operators and
technicians

Revision 06, May 2013

Autonomous Management Pillar Contents

Pillar Route
Team Route
Detailed Actions for AM Team Step 4
Detailed Actions for AM Team Step 5
Detailed Actions for AM Team Step 6

Page 30

HMESC: 01.10.13.041

Revision 06, May 2013

Und
e
revis r
i on

Page 31

HMESC: 01.10.13.041

Revision 06, May 2013

Route for AM Step 4


8

Check de results and


move to the next
inspection category

Finalise the
inspection program

Approximately one category per 2-6 months and when the


training of the technology is considered completed go to sub
step 3 for the next one
1. Establish inspection standards
2. Assess inspection skills and update skills matrixes
3. Perform self-audit
1. Define the maintenance standard for each wear or
consumable components
2. Conduct general inspection
3. Hold team meetings, list abnormalities and prepare
action plans
4. Correct abnormalities

General inspection

Specific training
on technologies
and component

General training

Preparation
of the training

Machine parts
classification

1. Definitions of assemblies, sub-assemblies and wear and


consumable component s of the machines
2. Prioritisation of technologies and parts using the L-Matrix

Step launch gate

1. Basic conditions check (micro-stoppages level, reduced


lubrication time and other criteria as per next sheet)
2. Priority check (priority of the line, ABC classification, etc.)

Page 32

1. Establish general inspection categories based on different


technologies (e.g. nuts, bolts, lubrication systems,
pneumatics, hydraulics, etc.)
2. Prepare training materials (checklists, manuals, etc.)
3. Skills matrix preparation and scheduling of training
4. Train future Level 4 operators

HMESC: 01.10.13.041

Revision 06, May 2013

Detailed actions for AM Team Step 5


7
6

Material losses
reduction

2
1
Page 33

Safety Risk reduction

Energy losses
reduction

Finalise Control
Points

Quality losses
reduction

Analysis of the
machine process

Step launch gate

HMESC: 01.10.13.041

Revision 06, May 2013

Detailed actions for AM Team Step 5


7

Finalise Control
points

Safety Risk reduction

Energy losses
reduction

Material losses
reduction

Quality losses
reduction

Analysis of the
machine process

1. Definitions of failure modes for quality, material losses,


energy consumption, change over (if relevant) and safety
2. Study of the interaction between Material and Machine

Step launch gate

1. Check of completion of step 4 activities


2. Creation of the team
3. Planning of activities

Page 34

1. Identify controls on critical components and carry out training


concerning all other relevant KPIs (e.g. changeovers, stocks, etc.)

1. Generic training about safety implications on machines


2. Define critical components based on risks assessment
3. Define control points and updated CILTs
1. Generic training about energy consumption
2. Define critical components based on specific consumption,
energy theoretical efficiency (zero losses), etc
3. Define control points and updated CILTs
1. Prepare specific training for the machine
2. Define critical components based on material balance
3. Define Q-Points and updated CILTs
1. Define critical components (give priorities based on loss
deployments)
2. Prepare specific training material for the machine
3. Define Q-Points (using the methodologies and the tools of the PQ
Pillar, e.g. QM-QX matrixes) and updated CILTs

HMESC: 01.10.13.041

Revision 06, May 2013

Detailed actions for AM Team Step 6


4

Page 35

Improvement of
organisation items

Reduction of walking
pattern

ECRS of CILTs and all


other team activities

Step launch gate

HMESC: 01.10.13.041

Revision 06, May 2013

Detailed actions for AM Team Step 6


4

Improvement of
organisation items

Reduction of walking
pattern

ECRS of CILTs and all


other team activities

Step launch gate

Page 36

1. Collect all organizational activities already executed by


the team or that could be delegated (holidays
management, vacancies, lunch breaks, movement of
materials, administrative tasks
2. Training to manage the organizational3
Training
for soft skills improvement
3. Definition of new procedures and training

1. Analyze all movements of production team members (e.g.


spaghettis charts or other team efficiency tools)
2. Investigate the opportunity and feasibility of layout
modifications
3. Fine tune the result of the ECRS

1. Collection of all activities carried out by the Production team (CILTs, 36


inspections, production operations, quality checks, administrative tasks,
etc.)
Carry out an ECRS exercise

1. Check of completion of step 5 activities


2. Creation of the team
3. Planning of activities

HMESC: 01.10.13.041

Revision 06, May 2013

Project & Early Equipment Pillar Contents

Project & Early Equipment Pillar Route


Improvement Routes
Project Implementation Team Route

Page 37

HMESC: 01.10.13.041

Revision 06, May 2013

Project & Early Equipment Management Pillar Route

Page 38

HMESC: 01.10.13.041

Revision 06, May 2013

Project & Early Equipment Management Pillar Route


1.Install a performance control
system
2.Use standards for all equipment
specification & ordering
3.Proactive feedback equipment
knowledge to supplier
4.Usage of information within
HEINEKEN for best practices
1.Minimum TPM requirements
including templates (CILT, SOP, TBM)
2.Improvement record database
3.Design standards / specifications
4.Implement MP function Checklists
5.Feedback loop to knowledge
database
1.Define & maintain 3 year
investment plan. (Brewery master
plan)
2.Classify projects based on risk
assessment and define project
approach & organisation
3.Manage execution of project plan

1.LLC for decision making


2.Learn from past experience
3.Deploy potential operational losses

Note: at end of each step summarise


impact on problem and key
Page 39
learnings HMESC: 01.10.13.041

Revision 06, May 2013

Project Implementation Team Route

Page 40

HMESC: 01.10.13.041

Revision 06, May 2013

Project Implementation Team Route

1. Review team
2. Create layout, workflow and
specification
3. Understand improvement
requirements
4. Detailed cost planning
5. Detailed activity planning /
supplier
6. Design review basic
engineering
7. Procurement
8. P&EEM Workshops
9. Change control procedure
10.Organisation & Maintenance
planning
11.Manufacturing

1. Project initial report


2. Team organisation
3. Scenario definition
4. Objectives and Preconditions
5. Equipment planning
6. Feasibility Cost estimate
7. Milestone planning
8. Initial risk assessment
9. Design Review
10.Scenario Report

Note: at end of each step summarise


impact on problem and key
Page 41
learnings HMESC: 01.10.13.041

1. Review team
2. Installation Risk assess. &
mitigation plan
3. Installation standards &
Procedures
4. Defect detection and LOI
5. Commissioning
6. Transfer and Acceptance
Protocol
7. Operation Optimising Phase
8. Site Acceptance Test
9. Project evaluation
10.Closure of project

1. Review team
2. Set up LOR
3. Understand existing situation
of plant
4. Equipment planning & MP
data availability
5. Risk Management
6. Basic cost planning
7. Activity planning
8. Design review
9. Investment application

Revision 06, May 2013

Planned Maintenance Pillar Contents

Planned Maintenance Pillar Route

Spare Parts Management Detailed Steps (Pillar Step 3.4)

Improvement Routes
Maintenance Standards Team Route

RCFA/Kaizen
Breakdown analysis
Minor stop analysis
Kaizen Sheet

Page 42

HMESC: 01.10.13.041

Revision 06, May 2013

TPM Planned Maintenance Pillar Route

Page 43

HMESC: 01.10.13.041

Revision 06, May 2013

TPM Planned Maintenance Pillar Route


1. Define predictive maintenance
technologies
2. Select equipment and part,
define operators and tasks
3. Develop diagnostic
technologies devices
4. Define predictive maintenance
plan
5. Train maintenance people
6. Manage predictive
maintenance plan
1. Implement Systematic
Breakdown Analysis
2. Review Maintenance
Information System
3. OTIF execution of current
maintenance system
4. Spare Part management
system review
5. Implement Systematic Minor
Stop & Alarm reduction
1.
2.
3.
4.

Note: at end of each step summarise


impact on problem and key
learnings
Page 44

Update machine list


Classify equipment (ABC)
Define failure seriousness level
Define maintenance goals and
OPI loss deployment
5. Establish basic maintenance
processes conform HeiQ
requirements (spare parts, work
order and TBM system)

HMESC: 01.10.13.041

1. Design and implementation


of budget control and
reporting system
2. Maintenance cost
deployment
3. Define best machine
maintenance practice
1. Review maintenance planning
procedure & execute teams
to review periodical
maintenance plans
2. Develop high visibility AM/PM
system
3. Improve PM system of critical
subassemblies through
FMECA and RCM
1. Restore machine's basic
condition and critical
maintenance backlog
2. Define system for horizontal
expansion of solutions
3. Support AM Teams
4. Execute improvement
activities to improve weak
points of equipment
5. Implement 5S in the
maintenance area
6. Define maintenance
organisation vision and train
maintenance workers

Revision 06, May 2013

TPM Planned Maintenance Pillar


Step 3.4 Spare Part Management
1.
2.
3.
4.

Yearly ABC analysis of spare parts


Procedure for stock control
Stock level modification procedure
Implement performance measurement and DCS
1. Authorisation process for PO
2. Management of repairable
parts
3. Return policy for parts not
used during shutdown
maintenance
4. Effective purchasing

1. Decision making policy for keeping parts on stock


2. Decision making policy for stock level & order size
3. Define the required spare parts for each machine based on
maintenance strategy

1.
2.
3.
4.

1.
2.
3.
4.
Note: at end of each step summarise
impact on problem and key
learnings
HMESC: 01.10.13.041
Page 45

Classify spare parts


Eliminate obsolete parts
Organise (5S) the warehouse
Monitor the time required to
retrieve a part from the
warehouse

Evaluation of stock level & turn over using ABC-X matrix


Evaluation of cost & losses
Define targets
Define spare part store concept

Revision 06, May 2013

page 46

Rem
oved

Note: Phase out:


No longer part of PKE
and ME trainings.
Recommendation is to
use Kaizen or BDA

Page 46

Note: at end of each step summarise


impact on problem
and 01.10.13.041
key
HMESC:
learning's

Revision 06, May 2013

page 47

Rem
oved

Note: Phase out:


No longer part of PKE
and ME trainings.
Recommendation is to
use Kaizen.

Note: at end of each step summarise


impact on problem and key
learning'sHMESC: 01.10.13.041
Page 47

Revision 06, May 2013

Minor Stop Reduction Team Route


1. Collect & communicate OPLs
2. Review CILT & SOP
3. Identify opportunities for
horizontal expansion
4. Close team / next failure mode

1. Identify root causes using 5Why


2. Define countermeasures and set
priorities
3. Introduce follow up of results on
selected failure modes

Rem
oved
1. Plan & implement
countermeasures
2. Communicate improvements
using OPL
3. Repeat step 3 to find
additional causes
4. Follow up results

Note: Phase out:


No longer part of PKE
and ME trainings.
Recommendation is to
Kaizen
or MSAS.
1. use
Define
critical
area
2. Understand working principle
3. Restore basic conditions &
describe failure mode

1. Analyse Pillar data


2. Perform additional data
collection
3. Pareto overview and failure
mode selection
4. Target setting
Note: at end of each step summarise
impact on problem and key
Page 48
learnings HMESC: 01.10.13.041

Revision 06, May 2013

Maintenance Standards Team Route

Note: at end of each step summarise


impact on problem and key
learnings
Page 49

HMESC: 01.10.13.041

Revision 06, May 2013

Maintenance Standards Team Route


1. Group tasks into task lists.
2. Create SMPs / OPLs & Train
maintenance executers.
3. Implement parts in spare part
management system.
4. Schedule tasks lists in
maintenance system (AM / PM).
5. Create LCC estimate

Component by component:
1.Define criticality
2.Define maintenance strategy
3.Define preventive and corrective
task
4.Define resource for task
5.Check for opportunities to cluster
tasks

Note: at end of each step summarise


impact on problem and key
learnings
Page 50

1. Choose machine based on current


losses and criticality.
2. Define target & starting point for
team
3. Breakdown machine in assemblies,
subassemblies and components
4. Collect current maintenance
standards
5. Collect supplier recommendations
6. Collect breakdown history
7. Identify similar standards of other
brewery

HMESC: 01.10.13.041

1. Estimate & evaluate total


downtime and resources
required.
2. Estimate & evaluate total part
consumption / maintenance
budget.
3. Compare new versus existing.

1. Use maintenance practices &


breakdown history to Identify
Maintenance Significant Items.
2. Identify remaining maintenance
significant Items (wear &
consumable components)
3. Define known failure modes
4. Identify AM/PM components

Revision 06, May 2013

Breakdown Analysis Sheet

Page 51

HMESC: 01.10.13.041

Revision 06, May 2013

Minor Stop Sampling & Analysis Sheet

Page 52

HMESC: 01.10.13.041

Revision 06, May 2013

12 Step Kaizen Sheet:

Page 53

HMESC: 01.10.13.041

Revision 06, May 2013

Progressive Quality Pillar Contents

Pillar Route
PQ Pillar Roadmap
Improvement Routes
Extract Loss Reduction Team Route
Packaging Material Loss Reduction Team Route
Defect Reduction Team Route
Microbiology Defect Reduction Team Route

Page 54

HMESC: 01.10.13.041

Revision 06, May 2013

Page 55

HMESC: 01.10.13.041

Revision 06, May 2013

1.-World Class Quality Vision


Reliability

Product Stability

Capability

Reliable
Machines & Process

Reliable &
Predictable Process

Capable Process
Guaranteed Quality

UCL

USL

LCL

LSL

Bronze

Silver

Out of
Control

Page 56

HMESC: 01.10.13.041

Revision 06, May 2013

New

Gold

2.-Quality Roadmap: Structure

Heineken World Class Quality

New

Page 57

HMESC: 01.10.13.041

Revision 06, May 2013

Quality Excellence

3.-Quality Roadmap: Composition


New
4

Quality Assurance

Quality Control
Page 58

4
3

HMESC: 01.10.13.041

Revision 06, May 2013

4.-Quality Control Phase: Details

Quality Control

New

Page 59

HMESC: 01.10.13.041

Revision 06, May 2013

5.-Quality Assurance Phase: Details

Quality Assurance

New

Page 60

HMESC: 01.10.13.041

Revision 06, May 2013

6.-Quality Excellence Phase: Details

Quality Excellence

New

Page 61

HMESC: 01.10.13.041

Revision 06, May 2013

Page 62
lity

HMESC: 01.10.13.041
)

nce
(Pers
onne
l)

Improve

Qua

nce
nel)

Mai
nten

(Pers
on

Mai
nten
a

l)

Quality
Excellence

INTERNAL QUALITY SCOPE

lity
(Tec
hn o
logis
ts

uali
ty
(Tec
h no
logis
ts)

olog
ists)

onne

Mai
nten
ance
(Pers

Quality
Assurance

Maintain

(Tec
hn

Qua

Quality Control

7.-People Development
EXTERNAL SC SCOPE

Suppliers Customers & Consumers

New

Revision 06, May 2013

Gold

Silver

Bronze

Page 63

ADVANCED
PKE

New

Methodology Expert Workshops (ME)


(focus in a specific tools, techniques or systems for achieve Silver level)

Tools & Techniques

QUALITY
PKE

Quality Control

Quality Assurance

Quality Excellence

8.-Quality Roadmap: PKE Training / ME

HMESC: 01.10.13.041

Revision 06, May 2013

Extract Loss Reduction Team Route

Page 64

HMESC: 01.10.13.041

Revision 06, May 2013

1. Monitor and check achieved


results. If there are anomalies
check analysis in step 3,
further analyse and implement
countermeasures
2. Investigate if further
1. Define the new standards and
improvement can be achieved
process factors to guarantee
by using known GPs in the
the desired process capability
critical areas. Recommend
based on Pillar priorities and
2. Integrate the new standards in
ease and effect whether to
AM CILTs and PM maintenance
implement (Pillar to decide)
systems
3. Based on Pillar priorities,
3. Update your DCS/ MCRS system
check if there is a requirement
with proper trigger points and
to further improve (Pillar to
RACI matrixes
decide). If so, compare data of
4. Monitor results regularly
critical area with situation of
best in class breweries and
technological limit
1. Determine root cause of loss
4. Implement countermeasures to
using 5 Why analysis
reduce the gap from the
2. Related to root cause, implement
benchmark/technological limit
countermeasures. FIRSTLY
5. Standardise
counter measures should come
6. Train and implement new
from Good Practices. Use the list
standards
in HeiQ
1.
Tag and list physical anomalies
3. Update the standards
(related to the loss)
4. Train and implement new
2. Tag and list deviations versus
standards
process & equipment
standards, basic recipes and
1. Analyse the existing historical data
existing work instructions/ SOP
and check data integrity
(operational standards)
2. Map the whole process within scope
3. Prioritise the tags and process
of team
anomalies
3. Identify all possible loss points
4. Standardise the solutions
4. Verify your existing measurement 5. Train and implement new
system
standards
5. Define your critical area/ priorities based on ease and effect matrix
6. Further quantify losses in your critical area (when possible)
7. Describe the link between extract losses and the process
If: univocal link between loss and process --> simply define the
phenomena
(problem description)
Note: at end of each step summarise
If: more complex link between loss and process --> use the QA
impact on problem and key
matrix to define theRevision
phenomena
(check
HMESC:
01.10.13.041
06, May
2013 first if standard thesis list is
Page 65
learnings
available for your specific loss!)

Extract Loss Reduction Team Route

Packaging Materials Loss Reduction Team Route


We a Note:
r
to co e consid
mbin
ering
Pack
e
agin Defect
gM
&
Rou aterials
tes

Page 66

HMESC: 01.10.13.041

Revision 06, May 2013

Packaging Materials Loss Reduction Team Route


1. Review CILTs, OPLs, SOPs,
planned maintenance tasks,
training
2. Confirm or review Packaging
specifications
3. Define trigger points
4. Quantify all economical
benefits
5. Ensure horizontal expansion
(within the plant and outside.
Submit new possible Good
Practices to HeiQ)
1. Re-classify remaining
packaging material losses
2. Understand and describe
losses circumstances
3. Identify root causes of losses
4. If packaging material is
conform to specifications but
Material is still a root cause,
involve supplier and
stakeholders in order to
improve the specifications
5. Define priorities of solutions
1. Plan team activities according
to assignment letter (focus on
specific packaging item / line
2. Identify potential economical
benefits considering
packaging value, extract
losses and other losses
3. Analyse the existing historical
data
4. Map the whole process
5. Identify all possible loss
points
6. Collect packaging material
Note: at end of each step summarise
specification
impact on problem and key
HMESC:
01.10.13.041
7.
Set a data collection Revision
system 06,
Page 67
learnings
8. Prepare a Pareto analysis

We a Note:
re co plan (assign
1. Define
to co action
ns
m
eringdates)
binesetiddue
actions
Pack and
D
e
a
f
e
ging planned
ct &corrective
2. Implement
Ma
actionsRoute terials
s

3. Train and implement new


standards
4. Measure results on packaging
1. losses
Compare the process in your
5. Identify
and eliminate
root
critical area
with the available
causes
remainingand
losses
processofstandards
Good
Practices (HeiQ, eRoom, etc.)
2. Plan the implementation of
Good Practices not already in
place
3. Analyse (5Why) the reasons for
not implementing remaining
Good Practices
4. Apply Good Practices
5. Verify compliance of machine
settings with process
standards
6. Verify compliance of packaging
material to specifications and
involve supplier and other
stakeholders (Buying, Quality,
etc.) in case of nonconformance. Look for supplier
Route Causes
7. Tag physical anomalies of
machines (related to the loss)
8. Manage the tags and process
anomalies
9. Standardise the solutions
May 2013(update CILTs, OPLs, SOPs,
machine settings standards,

We a Note:
r
to co e consid
mbin
ering
Pack
e
agin Defect
gM
&
Rou aterials
tes

Note: at end of each step summarise


impact on problem and key
learning's
Page 68

HMESC: 01.10.13.041

Revision 06, May 2013

Microbiology Defect Reduction Team Route


6
5
4
3
2
1

Page 69

Improve the
management system to
hold the gains

Analyse every defect

Implement improvement
actions

Find out root causes for


recurring defects

Restore basic conditions


on
critical area & set
standards

Identify the origins of


defects

HMESC: 01.10.13.041

Revision 06, May 2013

1. Redefine the conditions that


ensure microbiological quality
(PIs that influence micro FTR)
2. Update checklists and
standards to maintain the
defined conditions
3. Define actions on departures
from standards (both micro and
those that influence micro)
4. Improve the control systems
(define alarms in DCS and
reactions to alarms)
5. Revise and establish new basic
conditions

Microbiology Defect Reduction Team Route

1. Determine the root cause of all


deviations from the micro
standard
2. Organise the defect analysis
(use the tools available in the
Microbiology overview as guide
3. Define how to analyse each type
Analyse every defect
of deviation (Out of Specification
actions)
1. Define action plan (from step
4. Train all people on how to
3: who, what, where, when,
identify and investigate
how)
deviations
2. Standardise countermeasures
Implement improvement
5. Implement the system and
(new std, OPL, work
continuously
follow
up results
actions
1. Pinpoint
probable
sources
of
instruction etc)
infection using trajectory
3. Introduce training system for
analysis to compare numbers
new standards
and types of microbes at each
4. Record and plot results to
stage
Find out root causes for
establish the effect of new
2. Perform 5 why analysis to
standards
recurring defects
understand root causes of
1. Identify critical areas (divide
defects
into sections/subsections)
3. Attribute root causes to 4M
Restore basic conditions
2. Perform initial cleaning and
4. Produce final QA matrix from
tagging
on
5Why
3.
Tag anomalies versus
critical area & set
1. Ensure reliable Micro lab (complies
deviations from microbiology
standards
with LSS, lab standards, secure
related process/equipment
sampling plan, etc.)
standards, work instructions,
2. Analyse FTR Microbiology results
cleaning programmes,
Identify the origins of
3. Rank failures according to section
prerequisite programmes etc
defects
and make Pareto graph
(check against the
4. List and describe defect modes
Microbiology Knowledge
(e.g. Failure Raka Ray)
Overview in HeiQ)
5.
Produce
a
preliminary
QA
matrix
Note: at end of each step summarise
(if necessary) and set targets
impact on problem and key
HMESC:
01.10.13.041
Revision
May 2013
Page 70
6. Set up data collection
system06,
(e.g.
learnings
Trajectory analysis, Micro ID)

6
5
4
3
2
1

Improve the
management system to
hold the gains

Training & Education Pillar Contents

Pillar Route
Improvement Routes

Page 71

Competence Gap Reduction (CGR)

HMESC: 01.10.13.041

Revision 06, May 2013

Und
e
revis r
i on

Page 72

HMESC: 01.10.13.041

Revision 06, May 2013

Competency Gap Reduction Team Route (CGR)

5
4
3

Page 73

Evaluate results at 4
levels

Carry out the


learning program

Formulate
requirements for
implementation at
work place

Design learning
situation and
develop learning
materials

Detailed analysis
learning /
development needs

HMESC: 01.10.13.041

Revision 06, May 2013

Competency Gap Reduction Team Route (CGR)


5

Evaluate results at 4
levels

Carry out the


learning program

Formulate
requirements for
implementation at
work place

Design learning
situation and
develop learning
materials

Detailed analysis
learning /
development needs
Note: at end of each step summarise
impact on problem and key
learning's

Page 74

5.1
5.2
5.3
5.4

Evaluate the Learning Program on Relevance by the learners


Test the learners on the newly acquired skills
Test the (changed) performance at the workplace
Evaluate the Operational Result

4.1 Create customized check-list


4.2 Execute the program

3.1 Define all relevant conditions that may influence the application of skills at
work
related to learners
3.2 Define all relevant conditions that may influence the application of skills at
work
related to immediate supervisors
3.3 Define all relevant conditions that may influence the application of skills at
work
related to Organisation and Management
2.1 Design Learning Situation
Take into account the 70 20 10 Learning Philosophy
2.2 Develop Learning Materials
2.3 Select participants

1.1 Analyse CGR assignment letter


1.2 Identify which skills have to be developed
1.3 Develop learning objectives
1.4 Define output in Competency Development and Improved
Operational Result
1.5 Develop Evaluation criteria and method(s)

HMESC: 01.10.13.041

Revision 06, May 2013

Und
cons er
truct
i on
Early Product Management Pillar Contents

Pillar Route
Improvement Routes

Page 75

New Product Introduction (NPI)

HMESC: 01.10.13.041

Revision 06, May 2013

Revision Management
Revisio
n
No.

Date:

Documen
t
type:

Issued
by:

Oct 2011

STD

C. Kerr

Jan 2012

March 2012

May 2012

Jan 2013

Revision Comments
Creation document.
New Safety Pillar Route; 5 steps introducing overall management system
approach.
New P&EEM Pillar Route and Project Implementation Team Route.
New visual identity, only use master for slide ID, update various routes from
EFESO to new visual identity+added banner not to be used yet.
New PM Pillar Route, BDA sheet, Minor Stop Sheet. New Changeover Route.
Extract loss and Micro Defect Reduction Routes updated.
SHE Pillar ENV Steps added for already Bronze Brerweries
Org & C Mgt - HPO Model & Route

May 2013

New FI Pillar Step 5; reviewed sub steps including roadmap to 2020 E&W vision.
PM Pillar Breakdown, Minor Stoppage & Speed Loss Reduction Routes removed;
instructiojn is to use RCFA, MSAS or Kaizen only.
Quality Roadmap linked to Bronze, Silver, Gold...

Page 76

HMESC: 01.10.13.041

Revision 06, May 2013