Chapter 3
Project Management
OBJECTIVES
Structuring Projects
Project Management
Defined
Project is a series of related jobs usually
directed toward some major output and
requiring a significant period of time to
perform
Project Management are the
management activities of planning,
directing, and controlling resources
(people, equipment, material) to meet the
technical, cost, and time constraints of a
project
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All
5
Gantt Chart
Vertical
VerticalAxis:
Axis: Horizontal
Horizontal bars
bars used
used toto denote
denote length
length
Always
AlwaysActivities
Activities of
of time
time for
for each
each activity
activity or
or job.
job.
or
or Jobs
Jobs
Activity 1
Activity 2
Activity 3
Activity 4
Activity 5
Activity 6
Time Horizontal
HorizontalAxis:
Axis: Always
AlwaysTime
Time
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All
6
Pure Project
A pure project is where a self-contained team
works full-time on the project
are ignored
Lack of technology transfer
Team members have no functional
area "home"
Functional Project
A functional project is housed within
a functional division
President
Research and
Engineering Manufacturing
Development
Example,
Example, Project
Project “B”
“B” is
is in
in the
the functional
functional
area
area of
of Research
Research and
and Development.
Development.
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All
9
Structuring Projects
Functional Project:
Advantages
A team member can work on
several projects
Technical expertise is maintained
knowledge
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All
10
Structuring Projects
Functional Project:
Disadvantages
Aspects of the project that are not
directly related to the functional
area get short-changed
Motivation of team members is
often weak
Needs of the client are secondary
Research and
Engineering Manufacturing Marketing
Development
Manager
Project A
Manager
Project B
Manager
Project C
Structuring Projects
Matrix: Advantages
Structuring Projects
Matrix: Disadvantages
1 Project 1 Project 2
Network-Planning Models
Construction
3. Determine the critical path
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
D(2)
G F 1
E(5)
Hint:
Hint:Start
Startwith
withLF=15
LF=15
Determine late or
orthe
thetotal
totaltime
timeofofthe
the
starts and late ES=4 project
project and
andgogo
finish times EF=6 backward
backwardin inthe
the
network
networkfrom
fromGGto toA.
A.
ES=0 ES=2 ES=3 D(2)
ES=9 ES=14
EF=2 EF=3 EF=4 LS=7 EF=14 EF=15
LF=9
A(2) B(1) C(1) F(5) G(1)
ES=4
LS=0 LS=2 LS=3 EF=9 LS=9 LS=14
LF=2 LF=3 LF=4 LF=14 LF=15
E(5)
LS=4
LF=9
Immediate
Task Predecesors Optimistic Most Likely Pessimistic
A None 3 6 15
B None 2 4 14
C A 6 12 30
D A 2 5 8
E C 5 11 17
F D 3 6 15
G B 3 9 27
H E,F 1 4 7
I G,H 4 19 28
Example 2. Expected
Time Calculations
ET(A)=
ET(A)=3+4(6)+15
3+4(6)+15
Immediate Expected 66
Task Predecesors Time
A None 7 ET(A)=42/6=7
ET(A)=42/6=7
B None 5.333
C A 14 Immediate
Task Predecesors Optimistic Most Likely Pessimistic
D A 5 A
B
None
None
3
2
6
4
15
14
E C 11 C
D
A
A
6
2
12
5
30
8
F D 7 E C 5 11 17
F D 3 6 15
G B 11 G B 3 9 27
H E,F 1 4 7
H E,F 4 I G,H 4 19 28
I G,H 18
Opt. Time + 4(Most Li kely Time) + Pess. Time
Expected T ime =
6
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All
26
G B 11 D
E
A
C
2
5
5
11
8
17
H E,F 4 F
G
D
B
3
3
6
9
15
27
I G,H 18 H
I
E,F
G,H
1
4
4
19
7
28
Ex 2. Expected Time
Calculations
Immediate Expected ET(C)=
ET(C)=6+4(12)+30
6+4(12)+30
Task Predecesors Time
A None 7 66
B None 5.333
C A 14 ET(C)=84/6=14
ET(C)=84/6=14
D A 5
E C 11 Immediate
Task Predecesors Optimistic Most Likely Pessimistic
F D 7 A
B
None
None
3
2
6
4
15
14
G B 11 C
D
A
A
6
2
12
5
30
8
H E,F 4 E
F
C
D
5
3
11
6
17
15
I G,H 18 G B 3 9 27
H E,F 1 4 7
I G,H 4 19 28
Example 2. Network
Duration = 54 Days
C(14) E(11)
A(7) H(4)
D(5) F(7)
I(18)
B G(11)
(5.333)
Example 2. Probability
Exercise
What
What isis the
theprobability
probability of
of finishing
finishing this
this project
project in
in
less
less than
than 53
53 days?
days?
p(t < D)
D=53
t
TE = 54
D - TE
Z =
∑ cp
σ 2
Pessim. - Optim. 2
Activity v ariance, σ = (
2
)
6
path.)
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All
31
p(t < D)
t
D=53 TE = 54
D - TE 53 - 54
Z = = = -.156
∑σ cp
2 41
p(Z
p(Z<< -.156)
-.156) == .438,
.438, or
or 43.8
43.8 %
% (NORMSDIST(-.156)
(NORMSDIST(-.156)
There
There isis aa 43.8%
43.8% probability
probability that
that this
this project
project will
will be
be
completed
completed in in less
less than
than 53
53 weeks.
weeks.
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All
32
Ex 2. Additional Probability
Exercise
What
What is
is the
the probability
probability that
that the
the
project
project duration
duration will
will exceed
exceed 56
56
weeks?
weeks?
Example 2. Additional
Exercise Solution
p(t < D)
t
TE = 54
D=56
D - TE 56 - 54
Z = = = .312
∑σ cp
2 41
p(Z
p(Z >> .312)
.312) == .378,
.378, or
or 37.8
37.8 %
% (1-NORMSDIST(.312))
(1-NORMSDIST(.312))
McGraw-Hill/Irwin © 2006 The McGraw-Hill Companies, Inc., All
34
Time-Cost Models
Basic Assumption: Relationship
between activity completion time and
project cost
Assumptions/Limitations
Project activities can be identified as entities
(There is a clear beginning and ending point
for each activity.)
Project activity sequence relationships can be
specified and networked
Project control should focus on the critical
path
The activity times follow the beta distribution,
with the variance of the project assumed to
equal the sum of the variances along the
critical path
Project control should focus on the critical
path
Question Bowl
Question Bowl
Question Bowl
A project starts with a written description of the
objectives to be achieved, with a brief statement
of the work to be done and a proposed schedule
all contained in which of the following?
a. SOW
b. WBS
c. Early Start Schedule
d. Late Start Schedule
e. None of the above
Question Bowl
For some activities in a project there may
be some leeway from when an activity can
start and when it must finish. What is this
period of time called when using the Critical
Path Method?
a. Early start time
b. Late start time
c. Slack time
d. All of the above
e. None of the above
Question Bowl
How much “slack time” is permitted in the “critical
path” activity times?
a. Only one unit of time per activity
b. No slack time is permitted
c. As much as the maximum activity time in the
network
d. As much as is necessary to add up to the total
time of the project
e. None of the above
Answer: b. No slack time is permitted (All
critical path activities must have zero slack
time, otherwise they would not be critical to
the project completion time.)
Question Bowl