By
Abhishek Saini(151104)
Lovish Garg
Saumya Dutta
Majumder(151349)
Gunpreet Chugh
Project MANTHAN
Introduced to integrate the organisation using IT systems.
Workshops were conducted by the functional experts to gather knowledge.
Scope and objectives were decided by core group on basis of collective knowledge.
Synergy was to be created through upgrade of hardware, use of a common platform,
integration of all functional modules and open architecture.
Optimization and information analysis would cause a substantial savings to IOCL as
calculated by cost benefit equation.
Price Waterhouse associates was selected for task of implementing ERP across IOCL
in 29 months.
PWC submitted the CTP with some recommendations:
Implementation of suitable ERP software , add on software packages, installation and
commissioning of a robust communication network , installation and commissioning
of appropriate hardware and transition management.
Project MANTHAN
70 people were selected from various functional units of all the divisions to form the
core team.
SAP R/3 was selected in October 1999.
A huge extensive telecommunications network was required for new centralized
approach.
A multitiered approach was required for implementing a single bandwidth network.
Four stages were decided for project completion as conceptual design, detailed
design, construction and implementation.
Some challenges faced by organization are:
Many add-ons were very new and had never been implemented in India.
Little experience with computers among employees.
The Dilemma
The three-tier ERP architecture made challenging to identify where the
bottleneck was
The SAP application
The database server
Way of database implementation
Communications bandwidth constraints
No direct control over causal factors like communications bandwidth.
The end-users were growing discontent with the poor response time.
The Options
Continue with the implementation and simultaneously resolve issues
Core team displayed considerable enthusiasm
Eight year of implementation pressure from the top management
Competitors in advanced stages of their ERP implementation
Stop the implementation till the response time issue is resolved
This was an unexpected problem
Poor response times were jeopardizing the operations
Will have to come up with a plan to get the implementation back on track