AJEYA.B.P
GANESH HARIGE
RAJESH CHATRA
ESHAN
Co-guide:
G.V.Girish
Motivation and Objectives
• i. From the point of view of Technical /commercial
knowledge /cost reduction/ Availability of time,
the organization suggested to take this topic,
which is considered to be useful and meaningful
• Materials
• Idle Materials
•Transportation
•Time
• Quality • Cost
• On Time Delivery • Defects
Improves
Falls
• Morale • Inventory
• Overburden • Waste
– Unnecessary Walking
– Step 1: We first want to figure out how to prevent passing defective parts
to the customer (surgeon). But this is just a temporary band aid.
– Step 2: But this is not enough. Next, we want to prevent from making
defective parts in the first place.
1 5
6
2 4
UNPROCESSED : 3
PROCESSED
WORKPIECE WORKPIECE
• Moving material around the plant does not add any value.
• “Where’s the factory?”
• Even if space reduction will not reduce the rent, it will have benefits on our
production activities.
time vs process
4000
2971 3009
3000
time
2000 time
1000
38
0
value added in min non value added total min
time 38 2971 3009
process
Existing wet liners layout
The following is the existing layout which shows the motion of wet liners for
various operations
This table shows the Existing operational distance
8 Phosphading 1440
Time Vs Process
3726 3776
4000
3000
time in min
1000 s
50
0
Value Added Non Value Total in min
Time Vs 50 3726 3776
process
process
Existing Air Cooled Liners layout
The following is the existing layout which shows the motion of air cooled liners
for various operations.
Observations
• To start machining they need minimum 150-200 pieces hence it’s
taking more time for waiting.
• If there is fast dispatch, company will stop this process and send
the workers for fast dispatch, for this waiting time increases.
• One shift working time is 8hours, but workers works only 6.5 hours
shift.
• They are taking more time to change setting of machine.
• Transforming the pieces from one machine shop to another
machine shop.
• There is not smooth flow of pieces. Process goes in zigzag shape.
• Due to Semi finish and heat treatment delay waiting time
increases.
• They are committed to do minimum 140 liners per shift but they
are not achieving it.
• Due to power fluctuation and labor problem waiting time of
liners increases.
• They are not delivering the product to customer in schedule time
Suggestions
Proposed Layout for Wet Liners
• In the existing layout the various operations are
carried out in two machine shop If they implement U-
shaped .All the machines can be provided in the
shop floor instead of two shop floors, hence save the
space
• Eliminating the Workers leads in reducing the Labor
cost (Existing 8 labors are working, by applying U-
shaped layout; we can reduce up to 3 workers).
• Implementing another CNC machine (In existing 2
operation are done in one CNC machine in Machine
shop 01) production can be increased.
Proposed
Component motion distance
Sl. no Operation Distance (meter) Total ( meters)
1 Rough O.D 3.5+1.5+1.5+2+ 12
3.5
2 1st I.D 1.5+0.5+1.5 3.5
3 Jig size O.D 1.5+1.5+3.5 6.5
4 2nd I.D 1.5+2.5 4
5 O.D pre finish 2.5+2+3.5 8
6 Rough honing 2+3.5 7
7 Finish turning 2.5+2+5 9.5
O.D
8 Finish Honing 2.5+0.5+1.5 4.5
9 Honing 1.5+0.5+2 4
10 Total 59
• If Liners are moved in linear form then,
Considering the highest value added time in operation
In Wet Liners 4th operation is taken as Bottle Neck,
First component = 46 min
For second component it takes time 8 ‘40’’ to come out.
8’40’’ * 100 = 840 + 46 min =886
• At present the time taken to prepare a 100 wet liner component
is 5765 min ,After implementing lean technique the time
required to prepare a 100 wet liner component is 888 min
• In Air Cooled Liners 7th operation is taken as Bottle Neck,
For first component = 56 min
For second it takes time 9 min to come out
9 * 100 = 900 + 56 = 956 min
• At present the time taken to prepare a 100 Air Cooled liner
component is 3776 min. After implementing lean technique the
time required to prepare a 100 wet liner component is 956 min.
Proposed Bar Chart for Wet Liners and
Air Cooled Liners
Time vs Process
1500
Existing Cost Analysis Pie Chart Proposed Cost Analysis Pie Chart :
Others
10%
Material Others 10%
Profit Material Material 26% Material
30%
9% Labour Labour
Profit 18%
Electricity Consumables Consumables
13% Electricity Electricity
Profit Profit
Electricity 13% Labour 20%
Others Others
Consumables
Labour Consumables
13%
25% 13%
Air Cooled Liners
Profit
10% Profit
16% Material
others Material Material Material
10% 32% 30%
labor others labor
Electricity Consumables 10% Consumables
10% Electricity Electricity
Electricity
others 10% others
Consumables
10% Profit Consumables Profit
labor labor
10% 24%
28%
Conclusion