Cairo
Presented by:
Fawzy, Heba
Raky, Hany
Gamil, Michael
Fathy, Osama
Saeed, Ahmed
Hafez, Ahmed
A00011955
700131790
700131786
010330516
700131676
700131482
American University in
Cairo
CONTENTS
American University in
Cairo
American University in
Cairo
Project Name:
CAIRO FESTIVAL CITY
Project Location:
NEW CAIRO Beside Police Academy
Project Size: 3 million square meters
Owner: AL-FUTTAIM GROUP
Consultant:
ENGINEERING CONSULTANT GROUP (E.C.G.)
Main Contractor:
Al Futtaim Carillion-Orascom Construction
Industries Joint Venture (JV VENTURE)
American University in
Cairo
1.2 OVERVIEW
2.
Carrefour Hypermarket.
American University in
Cairo
Selected Unit
And our model by using Primavera is as a sample one
floor from one building Building F of Festival village
Zone H which consists into (2) levels and the area of the
model floor equal 600 meter square.
American University in
Cairo
American University in
Cairo
2.1 INTRODUCTION
American University in
Cairo
Project
Project
WBS
WBS
Buildin
Buildin
g
g (F)
(F)
ElectroElectromechanical
mechanical
Works
Works
Civil
Civil works
works
Super
Super
Structure
Structure
Substruc
Substruc
ture
ture
Architectural
Architectural
Works
Works
Block
Block
Work
Work
Plaster
Plaster
Work
Work
Metal
Metal
Work
Work
Windows
Windows
Work
Work
Doors
Doors
Work
Work
Finishing
Finishing
Works
Works
Plumbing
Plumbing
Works
Works
Proofing
Proofing
Works
Works
Electrical
Electrical
Works
Works
American University in
Cairo
Project
Project
Activities
Activities
American University in
Cairo
American University in
Cairo
2.4 RELATIONSHIPS
SUCCESSORS RELATIONSHIPS
American University in
Cairo
2.4 RELATIONSHIPS
SUCCESSORS RELATIONSHIPS
American University in
Cairo
2.4 RELATIONSHIPS
PREDECESSORS RELATIONSHIPS
American University in
Cairo
2.4 RELATIONSHIPS
PREDECESSORS RELATIONSHIPS
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
3.0 RESOURCES
American University in
Cairo
3.1 INTRODUCTION
Resource Definition
The first step in resource modeling is to decide exactly what resources
are considered important enough to be modeled. While most resource
modeling is concerned with people or workers (such as welders or
computer programmers), it may also include other resources such as
machines (such as a computer of a particular specification), or space on
a project where space is restricted and where this restriction limits the
amount of other resources which can be deployed at any one time.
Often resources are specified in terms of the number of units of resource
required, e.g., 5 welders or 3 computer programmers. Alternatively,
resources may be specified in terms of the hours or days that a specific
resource is required, e.g., 40 welder hours or 24 computer programmer
days. Resources may be considered as consumable, such as materials
that may be used once and once only, or non-consumable, such as
people, which may be used again and again. The way in which
consumable resources are used is not critical as long as they are used
efficiently. However, the way in which non-consumable resources are
used can have a significant impact on the project. For example, there is
a significant difference between requiring 16 units of a non-consumable
resource for one week, thus requiring 16 units to be made available at
that time, and requiring 1 non-consumable unit for 16 weeks, thus only
requiring 1 unit which can be reused 16 times.
Resource Allocation
Resource allocation, also called resource loading, is concerned with
assigning the required number of those resources identified in the
previous step to each activity identified in the plan. More than one type
of resource may be attributed to a specific activity. From a practical
standpoint, resource allocation does not have to follow a constant
pattern; some activities may initially require fewer resources but may
require more of the same resources during the later stages of the
project.
Resource Leveling
Resource leveling is the process that ensures resource demand does not
exceed resource availability. The ideal scenario would be a buildup of
resource usage at the beginning of the project and a reduction at the
end of the project. However, the approach to resource leveling will also
depend on whether resources are dedicated to a particular project or
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
American University in
Cairo
Activit
y ID
A1000
Activity
Name
excavation
Completion
Activity Activity Cost
Planned Actual
Varian Completi Comment
%
%
Total
Total
on time
s
Complete Complet ce
Cost
Cost
(EGP) Variance
(Planned
e
(EGP)
(EGP)
)
(Actual)
on
74,375.0
schedule
74,375.00
100.00% 100.00%
0
0%
0
for Cost
and Time
Soil
replacement
120,375.0 120,375.
using
100.00% 100.00%
A1010
0
00
excavated
material
0%
46,063.0
Retaining wall 46,063.00
100.00% 100.00%
A1020
0
0%
under-ground
34,032.0
34,032.00
100.00% 100.00%
A1030
services
0
0%
19,975.00
19,975.0
100.00% 100.00%
0
0%
92,763.0
100.00% 100.00%
0
0%
A1040
A1050
P.C footings
A1060
up stand
columns
46,063.00
46,063.0
100.00% 100.00%
0
0%
A1070
water
insulation
215,688.0 215,688.
100.00% 100.00%
0
00
0%
backfilling
114,875.0 114,875.
100.00% 100.00%
0
00
0%
A1080
on
schedule
for Cost
and Time
on
schedule
for Cost
and Time
on
schedule
for Cost
and Time
on
schedule
for Cost
and Time
on
schedule
for Cost
and Time
on
schedule
for Cost
and Time
on
schedule
for Cost
and Time
on
schedule
for Cost
and Time
on
American University in
Cairo
A1110
A1120
A1130
A1140
A1150
Activity
Name
Planned Actual
Total
Total
Cost
Cost
(EGP)
(EGP)
Rebar columns
93,825.0 93,825.0
0
0
Pouring
concrete
columns
23,563.0 23,563.0
0
0
Dismantling
columns
7,650.00 7,650.00
Formwork
Formwork Slab 276,250. 276,250.
level
00
00
Rebar Slab
level
1,129,25 1,129,25
0.00
0.00
Pouring
410,950. 410,950.
A1160 concrete slab
00
00
Dismantling
14,875.0 14,875.0
slab Formwork
A1170
0
0
level
A1180
A1190
Masonry
144,500. 144,500.
00
00
Plaster for
ceiling
23,588.0 23,588.0
0
0
Installation of
Completion
Activity
%
Activity Cost
Completi Comment
Varianc
Complet
%
on time
s
e
Complete e (EGP)
Variance
(Planne (Actual)
d)
on
schedule
100.00% 100.00%
0
0%
for Cost
and Time
on
schedule
100.00% 100.00%
0
0%
for Cost
and Time
on
schedule
100.00% 100.00%
0
0%
for Cost
and Time
on
schedule
100.00% 100.00%
0
0%
for Cost
and Time
on
schedule
100.00% 100.00%
0
0%
for Cost
and Time
on
schedule
100.00% 100.00%
0
0%
for Cost
and Time
on
schedule
100.00% 100.00%
0
0%
for Cost
and Time
on
schedule
100.00% 100.00%
0
0%
for Cost
and Time
on
schedule
100.00% 100.00%
0
0%
for Cost
and Time
American University in
Cairo
Activit
y ID
Activity
Name
Planned
Total
Cost
(EGP)
water
148,750.
insulation
A1210
00
for terrace
A1220
A1230
water
insulation
for toilets
13,813.0
0
plastering 89,250.0
for walls
0
stone
507,450.
flooring for
A1250
00
terrace
ceramic
flooring for 8,628.00
A1260
toilets
A1270
ceramic
17,850.0
walling for
A1280
0
toilets
A1290
installation
32,406.0
of ceiling
A1300
0
board
Completion
Activity Activity
Cost
Actual
Completio Comment
%
%
Varianc
Total
n time
s
Complete Complet
e (EGP)
Cost
Variance
(Planned
e
(EGP)
)
(Actual)
on
148,750.0
schedule
100.00% 100.00%
0
0%
0
for Cost
and Time
on
schedule
13,813.00 100.00% 100.00%
0
0%
for Cost
and Time
on
schedule
89,250.00 100.00% 100.00%
0
0%
for Cost
and Time
Under run
456,705.0
cost &
100.00% 90.00% 50,745
10%
0
Behind
schedule
under run
for cost
0.00
0.00%
0.00%
8,628
0%
&on
schedule
for time
under run
for cost
0.00
0.00%
0.00% 20,613
0%
&on
schedule
for time
Under run
cost &
14,280.00 100.00% 80.00% 3,570
20%
Behind
schedule
under run
for cost
10,328.00 20.00% 30.00% 24,097
-10%
&Ahead of
schedule
for time
under run
for cost
9,722.00 20.00% 30.00% 22,684
-10%
&Ahead of
schedule
American University in
Cairo
Activit
y ID
Activity
Name
Planned
Total Cost
(EGP)
painting
A1310 ceiling board 13,813.00
for toilets
installation
of windows ,
A1320
757,031.00
doors and
vanity
installation
of
accessories
A1330
fixtures and
mirrors in
toilets
A1340
27,891.00
painting final
120,063.00
coat
Completion
Activity
Activity
Cost
Actual
%
Complet Comment
%
Varianc
Total Complet
ion time
s
Complet
e (EGP)
Cost
e
Variance
e
(EGP) (Planned
(Actual)
)
under run
for cost
0.00
0.00%
0.00% 13,813
0%
&on
schedule
for time
under run
for cost
0.00
0.00%
0.00% 757,031
0%
&on
schedule
for time
0.00
0%
34,064.0
100.00% 100.00%
0
0%
installation
119,064.
A1360 water supply 119,064.00
100.00% 100.00%
00
pipes
0%
0%
51,160
-30%
A1370
installation
sanitary
water
34,064.00
34,064.00
0.00%
27,891
0%
installation
drainage
pipes
0.00%
0.00%
120,063
A1350
0.00
0.00%
34,064.0
100.00% 100.00%
0
installation
of fire
51,159.0
A1380
102,319.00
fighting
0
pipes
20.00%
50.00%
under run
for cost
&on
schedule
for time
under run
for cost
&on
schedule
for time
on
schedule
for Cost
and Time
on
schedule
for Cost
and Time
on
schedule
for Cost
and Time
under run
for cost
&Ahead of
schedule
for time
American University in
Cairo
Activit
y ID
Activity
Name
Completation
Activit
Activity
Cost
Planned Actual
y%
Completi
%
Varianc
Total
Total Comple
on time
Complet
e (EGP)
Cost
Cost
te
Variance
e
(EGP)
(EGP) (Plann
(Actual)
ed)
installation
34,128.0
of HVAC
A1410
0
duct
0.00
0.00%
0.00%
A1420
installation 119,191.
of fan coil
00
0.00
0.00%
0.00% 119,191
0%
A1430
installation 34,159.0
of fans
0
0.00
0.00%
0.00%
0%
installation
102,255.
electrical
A1440
00
conduits
0.00
0.00%
0.00% 102,255
0%
installation
electrical 255,128.
A1450 wires and
00
cable
0.00
0.00%
0.00% 255,128
0%
installation
96,953.0
panel
A1460
0
boards
0.00
0.00%
0.00%
96,953
0%
installation 11,156.0
Receptors
0
0.00
0.00%
0.00%
11,156
0%
installation 54,984.0
A1480 Terminals
0
0.00
0.00%
0.00%
54,984
0%
0%
A1470
faade
276,250. 276,250. 100.00
plastering
100.00%
A1490
00
00
%
and painting
A1500
34,128
34,159
0%
-10%
Comments
underrun for
cost &on
schedule for
time
underrun for
cost &on
schedule for
time
underrun for
cost &on
schedule for
time
underrun for
cost &on
schedule for
time
underrun for
cost &on
schedule for
time
underrun for
cost &on
schedule for
time
underrun for
cost &on
schedule for
time
underrun for
cost &on
schedule for
time
on schedule
for Cost and
Time
underrun for
cost &Ahead
of schedule for
American University in
Cairo
Activity
Name
Planned
Total
Cost
(EGP)
A1510
landscape 50,000.0
Grading
0
A1520
landscape 34,106.0
Planters
0
landscape 28,688.0
A1530 light fixtures
0
A1540
Testing and
7,969.00
start up
Completion
Activity
Activity Cost Complet
Actual
%
%
Varianc ion time Comments
Total Complet
Complet e (EGP) Varianc
Cost
e
e
e
(EGP) (Planne
(Actual)
d)
under run
for cost &on
0.00
0.00%
0.00% 50,000
0%
schedule for
time
under run
for cost &on
0.00
0.00%
0.00% 34,106
0%
schedule for
time
under run
for cost &on
0.00
0.00%
0.00% 28,688
0%
schedule for
time
under run
for cost &on
0.00
0.00%
0.00%
7,969
0%
schedule for
time
American University in
Cairo
5.0 CRASHING
American University in
Cairo
CRASHED ACTIVITIES
American University in
Cairo
6.0 REFERENCES
American University in
Cairo
6.0 REFERENCES
www.festivalcitycairo.com