Resource Planning
Chapter 13
By Wajahat Ali Ghulam
1
Key Points:
Compile resource histograms to compare resource forecast and
resource availability.
Allocate resource to the critical activities first.
The cumulative resource manpower S curve is used for the earned
value calculation.
Resource Planning
Resource planning is forecasting the resources required to perform the
scope of work within the time plan. The resource constraint should be
considered after the network diagram, schedule bar chart and procurement
schedule have been developed, but before the cash-flow statement.
KEY RESOURCES
How many people do you
?need
PEOPLE
Man Power
Identify levels of
expertise required
OTHER RESORCES
Are facilities, materials, or
?supplies essential
Material
Is information or technology
?needed
MONEY
What is the total cost of
?project
Project network times are not a schedule until resources have been assigned.
Resource-Constrained Scheduling
Resource Estimating. 1
The resource estimate is linked directly to the scope of work
and bill of materials (BOM).
The next step is to consider the direct trade-off between the
resource requirement and the activitys duration.
Consider the following in the scope of work is to erect 12 tones
of steel and the estimator knows from past experience that the work can
be done in 150 man-hours per tone and the men work 10 hour shifts,
than the equation is:
(12 tonnes x 150 man-hrs per tonnes)
10 hrs per day
2. Resource Forecasting
To forecast the total resource requirement by discipline or interchangeable resource. An
interchangeable resource is when you have a pool of workers and any one of them could
perform the work.
Activity
Number
Resource
Type
Quantity per
day
Resource
Duration
Lead Time
100
Builder
200
Builder
300
Builder
Mon
1
Tue
2
100
200
4
3
Activity
Numbe
r
300
4
3
2
1
4
3
Wed
3
4
0
Thu
4
4
0
200
100
Fri
5
0
0
Sat
6
Sun
7
Mon
8
0
0
Tue
9
Wed
10
300
7
Resource Forest Bar chart and Histogram (the bar chart shows the number
of resources per
activity per day, and the histogram shows the total resource required per day)
3. Resource Availability
The next step is to quantify the resources available inside and outside the company.
The following points should be consider:
The
anticipated sickness and absenteeism rate allow for a 25% absentee rate based on
their past time sheets.
Additional 25%
25%
For absenteeism
Resource
Requirement
Planned resource
requirements
Time
Available From
Available To
Engineer
December 1
December 15
Engineer
January 2
January 31
Engineer
Christmas DAY
Resource Availability
0
December
1
15
Resource Availability Histogram
January
31
9
4. Resource Histogram
The resource histogram is a popular planning tool because it given a good
visual presentation which is easy to assimilate and understand. The
prerequisites for drawing the resource histogram are:
Early start bar chart (after considering the procurement requirements
which ensures the materials and equipment are available).
Resource Table
Activity No
Start Date
Finish Date
100
200
300
400
500
10
600
11
11
Activity
Number
Mon
1
Tue
2
Wed
3
Thu
4
Fri
5
Sat
6
Sun
7
Mon
8
Tue
9
Wed
10
100
200
300
400
500
600
Total
10
3
1
1
4
1
1
8
6
4
2
11
Thu
11
5. Resource Loading
The
The
ideal situation is when the resource requirement equals the resources available.
Unfortunately,
in the real world this seldom happens, because it is not always possible to
adjust supply with demand, so some form of rescheduling is required.
A resource overload is when the resource forecast requirement exceeds the available
resources, while a resource under load is when resource forecast is lower than the
available resource.
resource overload will lead to some activities being delayed, which could delay the
completion of the project.
While
a resource under load will under utilize the companys resource, which could have a
detrimental effect on the companys profitability.
12
The overload and under loads can now be identified and addressed
as follows:
Resource Smoothing: Assign resources to critical activities first, then
try moving the other activities to ease any overload and underutilization.
Time-Limited Resources Scheduling: The end date of the project is
fixed, so resources must be increased to address any overloads.
Rousers-Limited Scheduling: The maximum number of resources is
fixed, so the end date may need to be extended to address any
overload..
13
10
Mon
1
Tue
2
Wed
3
Thu
4
Fri
5
Sat
6
Sun
7
Mon
8
Tue
9
Wed
10
Thu
11
2-
2-
Available
0
Forecast
Available
14
6. Resource Smoothing
Resource smoothing is the process of moving activities to improve the resource
loading profile. The first step is to select the resource to be smoothed, because it is not
possible to smooth for more than one resource at a time. To decide which resource to
smooth consider:
The least flexible resource-this could be the resource that comes from overseas, is
difficult to get hold of, or is least available.
Resource smoothing levels the resource overload to meet the resource available. The
resource histogram can be leveled by moving activities away from the overloaded area by
either:
Moving non-critical activities within their float so that the end date of the project
is not affected, while making sure the network logic is maintained. This is similar to
assigning resources to critical activities first.
15
Activity
Number
Mon
1
100
Tue
2
Wed
3
Thu
4
Fri
5
Sun
7
Tue
9
300
Thu
11
6
3
500
3
1
600
Total
Running
Total
10
16
19
22
26
30
32
10
Resources per Day
Wed
10
400
<<<<Move
Mon
8
200
<<<<Move
Sat
6
8
6
4
2
0
9
16
10
11
Resources
Time
limited
Apply Additional
Resources
Time
17
A confined space will limit the number of people able to work there.
Where there are limited facilities, for example the number of bunks available
on an offshore platform.
Health & Safety requirements may limit the number of workers in a certain
area.
Restricted access might limit the movement of materials and equipment, e.g.
building a house on a mountain slope or downtown office block.
18
Resources
Resource
limited
Extend Project
Duration
Resources
Resource
limited
Time
!!)stress something must give(
Time
limited
!BANG
19
Time
Working Overtime: This will increase the number of work hours available without having to employ more
staff. However working overtime will increase the labor rate and may reduce productivity.
Working shifts: This will increase the utilization of machines, equipment and also increase the number of
manhours worked in confined spaces.
Increase Productivity: Education and training . However, this is really a long term strategy.
Job And Knock: When the workers have finished a job, they can leave the factory, although they will be
paid for the full day or shift.
Sub-Contractors: Using sub-contractors will increase the workforce in the short term. Using subcontractors can also be useful to compare the performance of your in-house workface.
Scope of Work: If it not possible to increase availability, as a last resort you may consider reducing the
scope of work to meet a fixed end date.
20
21
35
10
16
18
20
24
28
29
30
32
Cumulative
Resources
30
25
20
Cumulative
Resource S Curve
15
10
5
22
11
10
23
24
25
26
27
Resource-smoothed Gantt chart, resource table and labor histogram for bridge project
28
Resource-smoothed Gantt chart, resource table and labor histogram for bridge project
Question
Resource Smoothing
Activity
Labor
required in
Numbers of
men
1-2
2-3
2-5
2-4
3-4
3-7
5-6
6-7
4-7
2
3
4
4
3
4
2
2
1
10 19
3
0 0
4 4
3
4
4
9
13 25
27 27
13 13
5
23 23
6
10
Activities
Total float
Earliest
start
1-2
2-3
2-4
2-5
3-7
4-7
3-4
5-6
6-7
0
9
19
0
9
12
12
0
0
0
4
4
4
10
10
13
13
23
Latest start
calculation
19-6
25-2
27-8
25-3
27-2
Latest
start
0
13
23
4
19
22
25
13
23
Total float = Latest time of finish event earliest time of start event - duration
Latest start = Latest time of finish event - duration
31
Table
Earliest
-start
Activitie
s
1-2
2-5
2-3
2-4
3-7
3-4
5-6
4-7
6-7
Latest
start
Activitie
s
Latest
start
0
4
4
4
10
10
13
13
23
1-2
2-5
5-6
2-3
3-7
3-4
6-7
2-4
4-7
0
4
13
13
19
22
23
23
23
32
33
34
Advantages
Disadvantages
Thank You
36