GALADARI MANUFACTURING PLANT VISIT

26 August 2013

The following slides show the practices


being carried out at Galadari off site
painting yard
Painting is being carried out outside of
shaded areas and in existing shaded areas
where the netting has been removed or is
defective and has not been repaired.
Temperature control and wind born debri is
therefore not being controlled during the
painting process
48 hours notice given to Galadari rectify this
unacceptable practice.

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Note - top line of shading missing and


piles of empty paint tins and rubbish left

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Missing top row of shade netting

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Damaged and missing shade netting

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Painting being carried out (fully in the open) with


no shade netting in place at all to protect the work

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Painting being carried out (fully in the open) with


no shade netting in place at all to protect the work

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Painting being carried out (fully in the open) with


no shade netting in place at all to protect the work

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

The following slides show the extent of


stock piles of fabricated steel work that
cannot be painted because the paint area
is full
Note also that non of this pre primed
steelwork has been stacked correctly and
is in the main stacked metal to metal
causing extensive paint damage and
scuffing and scratching to the finished
product

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Very poorly stacked materials

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Numerous scratches and damage to paint

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Numerous scratches and damage to paint


surfaces

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

The following slides show very poor


quality of workmanship to paint finish
and the results of damage when the
steelwork is being moved

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Defective paint application

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Defective paint application and movement

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Defective paint application

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Defective paint application and movement

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

The following slides show the poor


housekeeping of the paint area and
the temporary office accommodation
and storage areas

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Rubbish and healthy hazards in


areas of temporary
accommodation and stores

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Rubbish and healthy hazards in areas of temporary

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Paint stores not being kept to required temperature

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Health and Safety


Paint stores being used as eating area
Rest area and mess room very dirty.
Air con unit badly supported

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

The following slides show


that the existing paint area
is full to capacity and stock
of primed steelwork is not
being worked on with more
stock coming.

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Top and bottom view of


the existing paint area
full to capacity

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

Views of the stock of


steelwork not being worked
on because of the lack of
painting space

GALADARI MANUFACTURING PLANT VISIT


26 August 2013

END OF REPORT