InPlant Training
By-
Abhishek Bharti
A Road Project was going on under
R.C.D. , Giridih
Widening and
Strengthening of
Kowar Kodarma
Length Of Road= 79 km Road
The Road Passes
No. Of Culverts = 44 through many thickly
populated villages.
Width of the existing
No. Of Bridges = 2 crust is 3 m.
Which is to be
widened up to 7 m.
The improvement of
this road will uplift the
social and economic
condition of the area.
A typical road section consists of
four layers-
Granular Sub Base
(GSB)
Wet Mix Macadam
(WMM)
Bituminous macadam
(BM)
The
Semi dense bituminous concrete
materials
(SDBC)
used in the above
layers has to go
through various
quality control
checks
Some of the tests that are
done to ensure good quality
of the road are-
Water Absorption test
Aggregate Impact test
Flakiness Index
Sieve analysis
Bitumen content test
Designing of Pavement
A traffic census had been conducted previously at three
points on the road continuously for 7 days to get average
daily traffic. Number of CV/day is obtained from it, denoted
by P
N = {365*(1+r)^n -1}
*D*F*P(1+r)^x
r
Cumulative Traffic
is found out as
given in IRC 37
-2001.
From the
Cumulative Traffic,
and known CBR
value ; we use the
Pavement design
Catalogue and
obtain thickness of
all the layers
The portion to be widened beyond the
existing crust was excavated using the
excavator.
The GSB was brought from the mixing plant in Dumpers
and Dumped at the Site. It was then spread uniformly
ThewithGSB
the Motor
was Grader
then
compacted in layers
such that each layer did
not exceed 100 mm
compacted thickness.
Next the layer of
WMM was spread over
the GSB and was
compacted in layers.
To fill the voids
remaining, stone dust
was used, rolling was
continued until no more
dust could be forced
into the voids.
Sprinkling of water
is done with continued
rolling to obtain well
Compacted WMM is allowed to completely dry and
set before the next pavement is laid.
Surface of
WMM is swept
clean and
dust is blown
of using
compressed
air. Once the
surface is
clean, the
Prime coat is
sprayed over
the surface
using sprayer.
The surface is
allowed to
cure24for
After 24the Tack coat or binder is uniformly
hours
hours. over the surface. Emulsion is used as binder shall
sprayed
have temperature 20 c to 50 c.
Immediately after spraying the tack coat, the layer of
BM is laid over it. The BM is brought at site by a
Dumper, at that time the temperature of BM should be
120 c.