KAKATIYA DEVELOPMENT AREA DRAFT

MASTER PLAN 2031 &


WARANGAL ZONAL DEVELOPMENT
PLAN PRESENTATION
Kakatiya Urban Development Authority, Warangal
June2013
Vishwanath Sista, Advisor, KUDA
EXISTING SCENARIO
KUDA-1,805 sq.km. includes WMC 120 sq km;
171 Villages in Warangal & Karimnagar
districts
WMC is a tri.city with Kazipet- railway
Junction ; Hanamkonda- central part ;
Warangal- oldest part-oldest city and 2nd
Largest Municipal Corporation in Telangana;
biggest center of Agriculture Produce and
trade
KUDA Area is basically rural in character
KUDA MASTER PLAN: Broad Vision: ensure
an equitable and efficient development area
MASTER PLAN CONSISTS OF:
A broad land development map
Primary and secondary Circulation network
Development Promotion Regulations based on which,
further detailing by way of
implementation strategies,
Zonal development plans,
specific projects,
open space development and environmental
conservation, housing,

19 Planning Zones have been delineated for


preparation of ZDPs.
11 in WMC & Urban spread & 8 for the mandal HQs.

KUDA Master Plan focuses on Warangal city and


its urban spread and the 8 Mandal Hqs.
Urban Spread and population
distribution
Warangal City: 5.3 lakhs in 2001- increased to 6.3 lakhs in
2011, registering average decadal growth of about 19 %. City
population 48.42 % of the KUDA population
Urban Spread (Greater Warangal Municipal
Corporation area):513 sq km including WMC Area of 80 sq
km. and 50 surrounding villages -2001 population:7,33,278 ;
8,75,242 in 2011 Census, with a decadal growth of 19.36 %.
urban spread share is 64.30 % of KUDA Population.
KUDA population was 10.8 lakhs in 2001Census and 13 lakhs
as per 2011 Census. Urban pop. 47% & rural 53%
Population projection for 2031: 24 lakhs KUDA Area
WMC: 10.8 lakhs; Urban spread (-WMC): 8.4 lakhs and
rest of KUDA: 4.8 lakhs
Total employment :10.74 lakhs (Primary
Existing Land Use-Warangal City
Sl Extent (in
Land use Percentage
No. Ha.)
1 Residential 2886 35.92

2 Commercial 224 2.79

3 Industrial 46 0.57

4 Public & Semi-Public 792 9.86

5 Circulation/Roads 722 8.98


Vacant/Agriculture/O
6 2831 35.24
pen Spaces/Parks
7 Water Bodies 552 6.87

TOTAL 8033 100


Existing Land utilization Non-
Municipal Corp. of Kakatiya
Development Area in 2012
Sl. Area
Land use %age
No. (in Ha.)
Agriculture/vacant/
1 1,59,259 92.11
Forests, etc
Water Bodies / Nalas,
2 9049 5.23
Canals
3 Settlements & Hamlets 3707 2.14
4 Others 873 9.52
100.0
TOTAL 1,72,888
0
Future Growth Trend And
Master Plan Approach:
Warangal Urban Spread would be a compact
urban agglomeration, with the Hyderabad
National Highway as central spine and remaining
areas of Kakatiya Development Area would
continue to exhibit rural character and
predominantly have agriculture-based
activities.
Warangal agglomeration and the KUDA Area
are in proximity of Hyderabad
Metropolitan Region, and thus the
impact would continue to influence the
developments and growth direction of KUDA
Area.

In the regional context, Warangal and KUDA


Area can be termed and developed as a
counter-magnet to Hyderabad
Metropolitan Region given the proximity
and the strong transportation linkages
between the two.
Hence, instead of proposing a rigid and mono-
characteristic land use plan, and plot specific /site
specific land use and zoning, a broad range and
spectrum of development uses and
activities are proposed in not only in the urban
spread but also in the Agriculture Zone , in a scaled
down manner.

This Master Plan proposes a strong and definite


structure by way of a grid type circulation
network which would be to not only ensure
hierarchy of development activities to ensure - smooth
and efficient movement and serve the other
infrastructure network for water supply, drainage,
sewerage, electricity and communication Network.

The first order development proposals focus


Proposed Structure and
Circulation network
Keeping in view the Circulation pattern of the
Master Plan of 1971, the existing road pattern,
the trend of developments and the propensity
for future growth and direction of growth, the
Circulation pattern in this Master Plan 2031 is
suggested, basically in grid pattern format
that can be extended further in the
Kakatiya Development area in future.
The structure of Warangal urban spread
has become radial - concentric with
Hanamkonda as the nucleus of
development and the following
highways and main roads radiating out,
viz.

Warangal Karimnagar State Highway;


Warangal-Hasanparthi Main road;
National Highway to Mulugu; Warangal-
Narsampet Highway;Warangal-
Khammam Highway; and Warangal-
Zaffergadh Main Road respectively.
This is contained through the Master Plan Northern
Ring Road & eastern Ring road.
Keeping the above structure in view, the
Circulation pattern is integrated and
extended towards the south and west of
Warangal in this Master Plan 2031.
The proposed Circulation network consists of a well-
defined grid of Primary Roads,
Secondary Roads arterial roads, and
Ring roads/ Bypass roads.
The Primary Circulation network comprises of all
existing highways, the proposed ring roads, loop
roads, grid roads defining the various sectors and
other major roads. These are 30 meters and above in
width. These form the basis for the future mass
The secondary circulation network comprises of
link roads and new roads linking the
Primary roads. The Right-of- way of these
Secondary roads ranges from 30 meters to 18 meters.

The existing village roads especially in the rest of the


KUDA Area would continue to be serving as the network
between the villages, the Mandal Headquarters and
Warangal as well as the villages.

These are forming part of the secondary network and


are minimum 18 meters in width. The sub-arterial and
feeder road network form an important component of
circulation within the localities and colonies.
Mass Rapid Transit System for
Warangal
This Master Plan advocates the development and
operation of suitable Mass Rapid Transit
System (MRTS) for Warangal.

All primary roads of the Master Plan would be


the mass transit corridors. Initially, a Bus Rapid
Transit System (with exclusive bus lanes) may be
planned and designed with APSRTC being
responsible for the design, operations and
maintenance.

In the second phase, the mass transit system


should switch over to a combination of BRTS
and Light Rail Transit System (LRTS)
THE MASTER PLAN

This Master Plan advocates the


development of an exclusive and
dedicated Mass Transit System either
adjoining to the existing BG Railway line
through the South Central railway or
alternatively, between Hyderabad and
Warangal along the National Highway No
202 under the provisions of the Andhra
Pradesh Tramway Act,2008.
Development of a Regional Rail
Freight and Logistics hub at
Hasanparthy:
A freight container and logistics hub at

Hasanparthy has been proposed over an extent of


about 300 acres by the active participation of the
South Central Railway, the Container Corporation of
India and the private land owners under PPP mode.
This would be a major economic base for Warangal
since this has regional impact.

The other traffic and transport proposals would


flow out of the above basic circulation network and
structure. In this Plan specific locations for bus
terminals or truck terminals & logistics
hubs have been proposed in the Government lands
Proposed Broad land use for
Kakatiya Development Area:
Sl
Land use category Extent in Ha Percentage
No.
Urban Spread (including Warangal Municipal Corporation
Area)
General Development
1 19,342 49.98
Promotion Zone
2. Multiple Use Zone 8270 21.37
3. Public & Semi-Public Zone 2496 6.45
Work Center/Manufacturing
4. 1830 4.73
Zone
Central Heritage & Open Space
5. 1033 2.67
Zone
6. Circulation network* 5727.6 14.80
Sub Total 38,700 100
Percentage of Urban spread to
21.44 %
total Kakatiya Development area
Proposed Broad land use for
Kakatiya Dev. Area:
Sl
Land use category Extent in Ha Percentage
No.
Rest of Kakatiya Development Area
Agriculture Zone
(including vacant lands,
6. 1,29,352 91.22
water bodies, forest
lands, etc.)
7. Multiple Use Zone 8956 6.31
Heritage & Open Space
8. 7048 4.97
Zone
9. Circulation network* 2367 1.66
7. Settlements & Hamlets 3707 2.51 %
78.56 % of
Sub-Total 1,41,800 Developmen
t Area
TOTAL for entire Kakatiya
1,80,500 100
Development Area
Need for development of basic
industries for Warangal:
1. Excepting for the Railway Diesel Loco Shed at Kazipet,
there are no basic industries in Warangal.
2. Being the third largest agglomeration in the State,
certain basic industry activities, which are anchor
industries, are required for Warangal to increase the
industrial base.
3. This would give rise to other support and ancillary
including tertiary sector activities besides generating
large scale employment opportunities.
4. To encourage these, enabling have been
incorporated in the development regulations for
facilitating these in the Kakatiya Development Area.
Generation of Public Open
Spaces, amenities and utilities:
1) As the urban agglomeration increases the demand for
public open spaces , amenities and public utility areas
become crucial for ensuring the quality of life.

2) Since these are demand driven, no specific sites or


plots, unlike in the past plans, have been indicated.

3) Both the Warangal Municipal Corporation and KUDA


will generate these areas by way of development of
Government lands and through land assemblage
permissions.

4) Land Pooling Schemes will be encouraged in a big way,


with a development-frienfly procedure through
licensed developers, so that sizeable chunks of plots
Utilization of Government lands
All vacant Government lands should be placed at
the disposal of the MP Steering Committee of the
UDA and the first and basic responsibility of the
UDA/Govt. shall be to facilitate organized public
open spaces and public utilities sites. Then only
the lands for other Master Plan functions should
be utilized.
In the absence of the above, earmarking sites
specifically for open spaces and public utilities in
private lands becomes a futile exercise. Hence no
specific areas excepting the heritage and open
spaces zones that are environmentally critical for
their protection and preservation , have been
Proposed Development
Promotion Regulations
The land development in the Kakatiya Development Area
in this Master Plan 2031 is broadly categorized as
follows:

General Development Promotion Zone (GDPZ)


Multiple Use Zone (MUZ)
Public & Semi-Public Use Zone (PSPUZ)
Heritage and Open Space Zone (HOSZ)
Agriculture Zone (AZ)
The land use and zoning of activities are
not site specific or plot specific. These
are area-wise, so as to give a certain
City Central Open Space and
Heritage Area
The natural assets : major hillocks / hill ranges, large water bodies
and areas of outstanding natural beauty are proposed as Heritage
and Public Open Space Zone (HPOZ), to preserve these for
generations to come.

The areas around the major water bodies and hillocks of


Padmakshigutta, Balasamudram, Bhadri Tank, and the Warangal Fort
area and certain areas of outstanding natural beauty within the KUDA
Area are designated under this zone.

Only recreational, parks gardens, playgrounds, exhibition grounds,


melas, jatras, Theme Parks, tourism related developments,
archaeological related activities are permissible.

A City level Civic Plaza is proposed in 10 acres of area within the


Central Heritage Zone (Bhadri tank and its environs) of Warangal city
limits wherein city level civic centre activities like town
Land development regulations
through
land pooling schemes
group housing schemes

Layouts
Adoption of incremental development concept
giving a one-stage approval have been
suggested.
Master Plan Implementation
Strategy:
To implement the major infrastructure facilities of
the Master Plan costs money.
Since there is no dedicated funding of the Master
TheimplementationoftheMasterPlanisacollective,
collaborative and continuous effort onpartofboth
thepublicagenciesaswellastheprivateinitiative.
InthecaseofKakatiyaUDAarea,aparticipatory
implementation mechanism through active private-
public sector participation.
Fortheimplementation,financingandmanagement
strategyofthephasingandprogrammingoftheMaster
PlanofKakatiyaUDAarea,a Steering Committee may
be constituted tooverseetheimplementationofthe
variousdevelopmentprojectsandforensuringinter-
departmentalcoordinationsoastoachievethetargets
setbytheMasterPlan.
Master Plan Steering Committee
Members:
(i) Collector (Warangal District) Chairman
(ii) Commissioner, Warangal Municipal Corporation Vice-Chairman
(iii) R & B Deptt. Supdt. Engineer Member
(iv) APTRANSCO Supdt. Engineer Member
(v) Supdt. Engineer, Public Health Department in Warangal District- Member
(vi) Two eminent persons from Warangal (to be nominated by Chairman)-
Members
(vii) A nominee from the Municipal Administration & Urban development Dept.
-Member
(viii) Vice-Chairman, KUDA Member-Convener

The Master Plan Steering Committee through the Kakatiya UDA


and Warangal Municipal Corporation should take up the broad
programming and phasing of developments in the Master Plan
Master Plan Implementation
Cell in KUDA and WMC
Both the Warangal Municipal Corporation and
KAKATIYAUDAneed to constitute separate
and exclusive Master Plan Implementation
Cells in their offices, for undertaking and
preparing detailed project plans, preparing
RoadDevelopmentPlans,preparebudget and
coordinating with the functional agencies at
theoperationallevel.
WARANGAL PLANNING
ZONE

DRAFT ZONAL
DEVELOPMENT PLAN
Main City of Warangal (WMC Area)
delineated into 5 Planning Zones
Warangal Fort MainRailwaylineinnorth;WarangalMunicipal
1
Planning Zone limitsineast,southandwest

Warangal Planning MainRailwaylineinsouth;Pothanaroadonwest;


2
Zone WarangalMunicipallimitsonnorthandeast

Hanamakonda Waddepalliroadonwest;HanamkondaMainroad
3
Planning Zone onsouth;WarangalMunicipalboundaryoneast

NITCampusboundaryoneast;Warangal
Kazipet Planning
4 Municipalboundaryonwestandsouth;and
Zone
Waddepalliroadoneast

Pothanaroadoneast;Hanamkondamainroad
Central Area Heritage
5 onnorth;MainRailwaylineonsouthandNIT
Planning Zone
Campusboundaryoneast

1) The preparation of Zonal development Plans (ZDPs) for these Planning


Zones are required to be taken up by KUDA at the earliest, keeping this
overall Master Plan structure in view.

2) The ZDPs would essentially be area development plans with emphasis


on action-oriented implementation strategies and are basically meant
to be action plans, plans for development of the various areas and
implementation plans and not just detailing out specific land uses and
further road network.

3) This Zone, viz., Warangal City proper is the oldest settlement in the
KUDA area. The zone is admeasuring 19.60 sq km and consists of
Municipal wards 1,2,3,4,5,6,7, 19(P), 20 21,23, 24 and consists of some
of the most densest portions of Warangal.
Thetotalpopulationofthezonewasabout1.30 lakhsin2001and1.70
lakhsin2011,registeringjustabout31%increase.Thepopulationgrowthis
steadyinviewofthecomparativelylessproportionofpopulationin-migrationto
thiszone.Thepopulationincreaseismainlyduetonaturalgrowth.The
expectedpopulationofthezoneforthePlanperiod2031isabout2.7 lakhs.

Salient characteristics of the zone:


This zone is the soul of Warangal.ItisfromherethatWarangalgrewfroma
settlementofabout10,000in1941toamunicipalCorporationwithmorethan6
lakhstoday.Itisanimportantpartofthecityintermsoftradeandcommerce,
withthelocationofthewholesaletrade,businessandtransportationfacilities.

Interdependence of Zone on other parts of the city


BeingfunctionallythecentralpartofWarangalCity,allthebusiness,tradeand
commerceareconcentratedhere.Themovementpatternto&fromKazipetand
HanamkondatoWarangalisthemajortrafficgeneratingactivity.Besides,
commutermovement,thegoodsvehiclesdestinateatwithWarangalmainly
neartheOldgrainMarket.Fromheresmallvehiclesferrythemerchandiseto
themainmarketsofBattalaBazar,BeatBazaar,thejewelleryshopsstreet,
etc.
Existing Land use 2013 in the
Warangal Zonal Area
Sl No. Land use Extent (in Ha.) Percentage

1 Residential 614.3 31.08

2 Commercial 138.15 6.99

3 Industrial 11.38 0.57

4 Public & Semi-Public 196.03 9.86

5 Circulation/Roads 178.71 8.98

Vacant/Open
6 700.74 35.24
spaces/Parks

7 Water Bodies 136.63 6.87

TOTAL 1976 100


GROWTH PROSPECTS FOR THIS ZONE:
Sincethepopulationisstabilised,withnotmuchappreciableincreaseinthe
housingstockandthetendencyofnon-residentialactivitiesinvadingtraditional
residentialareasoftheinnercity,theincreaseinpopulationdensityisexpected
tobemoderateasseenfromtheexpectedpopulationofjustabout2.60lakhs
in2031anincreaseofabout90,000inthe20yearplanperiod.

However,thiszonewouldcontinuetobethenucleusofWarangal-attracting
traffictoandfromthiszoneinviewofthecity-widebusiness,tradeand
commercialactivitiesconcentratedintheInnercity.Thereforethefocushasto
beonredevelopmentandrejuvenationoftheinnercitytofacilitatethisthriving
activity.
It is this aspect that the Draft Zonal development Plan mainly addresses
in the proposals.
PROPOSED LAND USE
TheproposelanduseissimilartotheoneproposedintheDraftRevisedMasterPlan.
There is no change in the land use proposals for reasons cited in the forgoing pages.
Only some of the specific sites that are institutional in character have been separately
highlighted.OtherwisetheproposedlanduseisthesameastheMasterplan.

TABLE- PROPOSED LAND USE ALLOCATION


Sl No Category Extent (in Ha.) %
GeneralDevelopmentZone
1 972.32 48.71

2 MultipleUseZone 300.9 15.07


3 InstutionalZone 191.15 9.57
4 WaterBodies&OpenSpaceZone 269.14 13.48
5 WorkCentreZone 37.94 1.9
6 CirculationNetwork 224.5 11.24
Total 1996 100
CIRCULATION SYSTEM
Agoodcirculationnetworkinthezonefacilitatesthepromotionandthrivingoffunctional
activities of the Inner city. In the ZDPCirculation network proposals, a system of Inner
Circular road and 6 major radials have been envisaged within and outside the zone.
Theseconnecttheproposed36m(120ft.)Warangal Loop Roadabout55%ofwhich
passes in the peripheral area of this Warangal Planning zone, while the remaining
alignmentencirclestheFortWarangalZone.

Proposed Inner Circular RoadTotallengthapprox.7.3km.andtheproposed


Rightofwayvariesfrom24m(80ft.)to30m(100ft.).Thealignmenttheproposed
InnercircularRoadisalongtheexistingroadsintheInnercityandisfeasibleforroad
wideningatthementionedstretchesbelowasfollows:

StartsfromWarangalStationgoeswestalongthe60ftstationroadgoesparallelto
railwaytracktomeettheBattalaBazarroad;goesalongthe80ftwidePothana
roadgoesalongthisEyeHospitalRoad;goesalongMGMroadtillVenkataramana
junction,andmeetstheStationroadinfrontofStation.
Radial roads: 6 Radial roads radiate out from the Inner Circular
Road,viz.
1)The36meterswideHunterroad;
2)The 30 m (100ft) wide MGM Road leading to Hanamkonda Chowrastha
andbeyondtoKazipet;
3)The24m(80ft.)wideKothwadaRoad;the30m(100ft.)widelinkroadto
MuluguRoad;
4)The30m(100ft.)wideKashibuggaroadleadingtoNewGrainMarketat
Enumamula;
5)The30m(100ft.)wideNarsampetroad
6)ThustheInnercityofabout1sqkmiscircumscribedbythisInnercircular
road.

Warangal Loop Road:


ThenorthernpartoftheproposedWarangalLoopRoaddelineatedinthe
DraftRevisedmasterPlanalongexistingroads,isof45metersRightofway.
ThisloopRoadisusefulinweaningawaythegoodstrafficwhichis
predominantlybringingintheagriculturalproduceandgoodstotheInnercity
Improvements to certain existing roads:
From the survey carried out in the zone, the following major existing roads are proposed to be widened as
follows:
Road name Proposed width MarketStreet 12m(40ft.)
A) INNER CITY ROADS Mandirroad 12m(40ft.)
MainWarangal-Narsampet 36m(120ft.) IndiraGandhiRoad 12m(40ft.)
Highway RadhikaTheaterlane 12m(40ft.)
JPNRoad 18m(60ft.) MarkandeyaStreet 12m(40ft.)
OldGrainMarketroad 18m(60ft.) HanumanTempletoMosqueroad 9m(30ft.)
StationRoad 18m(60ft.) YellamaTemple-Girmajipetroadjunction 9m(30ft.)
(RabindranathTagore
Vegetablemarketroad 18m(60ft.)
Road)
A) OTHER ROADS IN ZONE
NarsampetRoadstretchin 36m(120ft.)
DoctorcolonyRoadanditslinkwiththe 33m(110ft.)alongthe
innercity HTPowerLine;and24
AutonagarRoad
Charbowliroad 12m(40ft.) m(80ft.)inrestof
alignment
BandelliStreet 12m(40ft.) LaxmiMegaTownshipMainroad 18m(60ft.)
MandiBazarroad 12m(40ft.) AutonagarRoad 24m(80ft.)
YellammaBazarRoad 12m(40ft.) VasaviColonymainRoad 12m(40ft.)
Girmajipetroad 9m(30ft.) RoadfromCKMArts&ScienceCollege 18m(60ft.)
GroundtoEnumamulaMarket
PinnavariStreet 9m(30ft.)
DeshaipetColonymainroad 12m(40ft.)
SH-240.(Warangal- BattalaBazarstretchupto
RoadlinkingCKMCollege(South)to 18m(60ft.)
KhammamRoad)Battala hunterRoadjunction-15m KhasibuggaroadjunctionviaChinna
BazarRoad;(Swami (50ft.) WaddepallyTank

VivekanandaRoad) Restofalignment18m(60 HTLine-RTAOfficeJn.LinkRoadto 30m(100ft.)


NarsampetroadJnnearlabourColonyvia
ft.) SRColony
JUNCTIONS IMPROVEMENT:
Along with the road development of the above-mentioned major roads, the following major road
junctionsarerequiredtobeimprovedanddevelopedasperstandards:

PochamaMaidanjunction
MGMHospitalJunction
HeadPostOfficejunction
VenkataramanaJunction
KhasibuggaRoadjunction
HunterRoadJunction
JPNRoad-StationRoadjunction
BattalaBazarStationRoadjunction
WarangalCrossRoadsjunction
AutonagarJunction
FortRoadpetrolpumpJunction
AmruthacentreJunction
WarangalStation-Ramkynction
Govt.PolytechnicRoad-MGMHospitalRoadJunction
AutonagarJunction

Besidestheabovetheminorroadjunctionsarerequiredtobeimprovedwithadequatesplayand
turningradiusforvehicleswhenWMCistakinguptheroadimprovementworks.
IMPROVEMENT OF THE WARANGAL STATION AREA:

(A)Warangal Rail Terminal

-Vehicular Parking: Parkinglotsinthestationneedtobereorganized/replannedinorderto


catertofuturedemand.
-Station localBus Terminal: Suchaterminalapartfromthemainbusstand,wouldbean
importantnodeforthepublictransportationsystem;henceabusterminalisneededinside
thestationpremises.
-Para-transit andTaxi Interchange: Presentlyallautorickshawsarewaitedoutsideclogging
theroadinfrontoftherailwaystation.Aregulatedautostandandtaxifacilityinsidethe
Stationpremisesisnecessaryforservingthecommuters/tourists/visitorseffectingduring
religiousfestivalsandotherevents.

(B) Redevelopment of the Station Area:

OneofthecharactersticfeaturesisthattheareaonthewestsideofWarangalStationhasbecome
congestedduetolocationoftheBattalaBazar,BeatbazaarandtheJewelryStreet,plusthefruit
marketandvegetablemarketlocatedintheareaoftheOldGrainMarket.Thereforerelocationof
certainactivitiesandrealigningthetrafficintheInnercitywouldbeoneofthesolutions,viz.theOld
GrainMarketthatisstrategicallylocatedintheoldcity,theIndianOilDepotlocatedrightnextto
WarangalStationthesetwobemadeintomultipurposenodeswithalargepartasopenparking
andupperfloorsforvariouspublicamenitiesandfacilitieslikelocalwardoffices,e-sevacenters,
locatingtwoorganizedComplexesforhousingtextiles,handloomsandtheotheroneforjewelry
andrelatedfancyitems
ThefruitandvegetablemarketcouldbeshiftednearoradjacenttotheNewGrain
MarketatEnamamula.AportionoftheexistingIndianOilDepotsitewouldalsobe
neededforMRTSStationTerminalfortheproposedMRTSLinefromMadikondato
WarangalintheRevisedMasterplan.LikewiseapartoftheOldGrainMarketcanbe
usedforexpansionoftheWarangalBusStation-havingbothcity-wideservicesas
wellasdistrictservices
Withthesechanges,theroadnetworkofBattalaBazar,BeatRoad,etchastobe
reworked/widenedandhaveasystemofone-ways/pedestrianstreetsandundertaken
bybothWarangalMunicipalCorporationandWarangalPolicedepartmentin
consultationwiththeRailwaysandAPSRTC,

PARKING PROBLEMS IN THE INNER CITY

BattalaBazarisundertremendouspressure,intermsofitsexistingparkingdemand,
whichaccountsfor28%ofthetotalparkingdemand.StretchesofWarangal
chowrasta,JPNRoadandSVNRoadtogetherhave24%oftotalparkingrequirement
toovercomethedeficiencyinparkingdemand,off-streetlocationsinshapeofparking
complexesarerequiredtobedevelopedasparkingslotsalongwithup-gradationof
on-streetparkingservices.
urgencyofframingaparkingpolicyforthecityforformulationandimplementationofa
Transportation Management Plan forthiszone.-Developmentandmanagementof
off-streetparkingfacilityatappropriate/identifiedlocations
-Organizationandregularizationofon-streetparkingfacilitiesincludingtheir
identificationandregulationCont..
PublicParkingComplexesintegratedwithotherpublicfacilitiesandamenitiescalledPublicfacilities
nodes would besides containing local bus stand, parking for autorickshaws,2-wheelers,etc. would
house amenities like local public offices, post office, police outpost, BSNLOffice, e-seva center,
APCPDCL Fuse call Off Office, Water works branch office, Sewerage works branch office,
Municipal Ward Office, APSRTC Bus Pass and Stand, and private local offices on lease basis
aroundacentralcourtyardopen space.Theseareproposedattheaforementioned 6 junctionsof
Innercircularroadand6 radialroadswhichmay be taken up byWMCalongwithpublicfacilities
center on top priority basis. The site of each is about 4000 sq m or one acre. These are
recommendedtobeundertakenbyWMCwiththelandownersunderBuildOwnOperate(BOO)
mode.

Goods / Truck Terminal


ItisproposedtolimittheentryoflargetruckswithinWarangalcitytotheperipheryalongtheInner
ringRoad;allowingonlysmallandmediumgoodsvansuptotheWarangalInnerCircularRoadand
totally banning plying of small and medium goods vans during the shopping and trading hours
between 10 AM to 8 PM inside the area of the Warangal Inner Circular Road. It is proposed to
develop a Truck terminal at Thimmapur (V) by KUDAin available public lands which is in close
proximitytoboththeKhammamHighwayandOuterRingRoadlinkingtheNationalHighway-202
and other parts of KUDA area. The truck terminal would have necessary facilities like offices of
transport agencies, petrol pumps, service centres, shops, godowns, weigh bridges, spare part
shops,vehiclebodybuildingandrepairshops,restaurantsetc.
BUS SERVICES IN THE ZONE
ThemainbusroutesfromKazipettoWarangaloriginateand
terminateattheexistingWarangalCityBusStandlocated
oppositeWarangalrailwayStation.

ZDPproposesexpansionoftheWarangalCityBusstationby
takingapartofthesiteoftheoldgrainMarket.Moreroutes
couldbeoperatedfromheretoEnumamulaGrainmarket,
KakatiyaUniversity,MuluguRoad,FortWarangal,Khammam
Highway,etc.apartfromoperatingdistrictbusesfromhere.

IntheInnercity,theAPSRTCmayuseminibusesof25
capacitytonegotiatetheexistingroadsandstreetswithpointto
pointfacilityofthebusstandsproposedinthe6multi-nodal
facilitiescentersandWarangalCityBusstation.
Mass Transit System proposals
MasterplanhasadvocatedamasstransitsystemeitherbywayofBusrapid
TransitSystem(BRTS)orLightRailTransitSystem(LRTS)whichtheAndhra
PradeshStateRoadTransportCorporation(APSRTC)andWarangalmunicipal
Corporation(WMC)shouldjointlyundertakeandoperateunderaSpecial
Purposevehicle(SPV).Themasstransitroutessuggestedintherevised
masterplanareallthe30m(110ft.)andaboveroadswhichhaveprovisions
fordedicatedlanesforsuchasystem.Thisfacilitywouldimproveandhavea
positiveimpactonthiscentralzoneofWarangal.

Development of public open spaces,parks


and public amenities complexes in the zone
Sincetheinnercityiscongested,exceptingfortheoldgrainmarketsiteno
specificsitesorplotsareavailable.TheGrainmarketsitehasbeenproposed
foronesuchmulti-facilitynodetocatertotheneedsoftheinnercity.Forthe
otherpartsandcatchmentareaofthezone,6suitablelocationsneedtobe
identifiedofupto2acreseach(1acreforlocality-levelparkandbalance1acre
formulti-facilitiescomplexandtakenupfordevelopmentofmulti-facilities
nodesbytheWarangalmunicipalcorporationinpublicormunicipallands.
DEVELOPMENT PROMOTION STIPULATIONS FOR
WARANGAL ZONAL DEVELOPMENT PLAN
ThesameuseclassificationandusesstipulationsofMasterPlanshallapplyfortheland
useclassificationinthisZDP.Whatisdetailedoutistheenablingstipulationsthatwould
helpinredevelopmentandrejuvenationoftheInnercityandstimulatinggrowthinthis
oldandcentralpartofthecitybydirectlyandrejuvenatingeconomicdevelopmentthat
wouldmakethissoulofWarangalthrivingandvibrantasfollows:

-Building development would be allowed on both existing and proposed


roads.
-Modifying the criteria for allowing buildings upto certain height:
withmaximumheightinsidetheInnerCircularRoadshallbe24mor8floors;and
12floorsor36mforsitesabuttingtheInnerCircularRoadandoutsideand
withintheWarangalPlanningzone.

-Allowing cluster type buildings (for all type of occupancies) with


modified requirements:
-Allowing automatic amalgamation of plots:
Withaviewtoencouragingbiggerandlargerplotssothatoptimum
builtformisensured,automaticamalgamationofplots(meansthecombiningoftwoor
moreplotsintoasingleplotandbuildingdevelopmentpermissionistakenasasingleplot)
shallbeallowed.
Permissible Heights in
Warangal ZDP
Permissible building height
Existing or proposed road * (excluding Parking floor
Remarks
width whether on stilt or
basement or cellar)

OthercriteriaofTableIIIof
Lessthan9mor30ft. 10mor3floors BuildingRules,viz.plotsize,
etc.shallapply
9mor30ft. 4floorsor12m -Do-
12mor40ft. 6floorsor18m -do-
ShallComplywithTableIV
andotherrequirementof
18mor60ft. 8floorsor24m
HighRisebuildingsof
Buildingrules

AspertableIVandrequirementofHighRisebuildingsof
30mor100ftandabove
Buildingrules
Mixeduseswouldbeallowedinentirezoneforamalgamatedplots/siteswithminimum
4000sqmandabutting12mroads,subjecttopaymentoflanduseconversion
charges.
Foramalgamatedplotsofsize4000sqmandabove,therewouldbea25%
concessioninthebuildingfeesleviedbyWMC.
Foranysuchplotsamalgamation,noseparateapprovalisrequiredandbuilding
plans/drawingsinsuchamalgamatedplots/sitescanbesubmitteddirectlytothe
sanctioningauthorityforapproval.

Parking requirements:

I. Consideringthecharacterofthiszone,theparkingrequirementisrationalizedto20%
ofthetotalbuiltuparea.
II.Commonandcontinuouscellars/basementparkingfloorsbetweenadjoiningbuildings
attheselevelswouldbeencouraged
III.surroundingroads,etcsoastoimprovetheaccessibility,etc.
IV.irrespectiveofplotsizeorsite,Basementorsub-cellarof1.5mundergroundandupto
1.5maboveground(dependingonsiteconditionsandgradient)wouldbeallowedas
parkingfloorwithdrivewaywithinthesetbacksdesignedinsuchawaysoasto
achievethedesiredslopeorgradient.Suchparkingfloorisexcludedfromheightofthe
building.
Modification in the Transferable development right
provisions:
Forthelandsurrendered for road widening free of cost to WMC,theTDRapplicable
willbe200%oftheareasurrenderedandsuchareasurrenderedisacceptedbyWMC.
TheTDRshallbeutilizedonlywithintheWarangalzone,orthesamecanbeadjusted
or offsetted against the total fees and charges levied by WMC for issuance of building
permission.Incaseofhigh-risebuildings,theTDRamountcanbeadjustedagainstthe
Citylevelimpactfeesinadditiontooffsettingagainstthetotalfeesandcharges.
Modification in Group Development Scheme
provision:
GroupDevelopmentSchemeshallessentiallyapplytoanynon-residentialormixed
developmentinbuildingdevelopmentsintwoormoreblocks.Theminimumplotsizefor
GroupDevelopmentSchemeshallbe2000sqmwithanabuttingroadof9m.
Other Physical Infrastructure Facilites In The Zone:
Thedetailsandrequirementsofotherphysicalinfrastructurefacilitiesinthiszonehave
notbeendetailedoutsinceitislinkedtotheoverallimprovementandaugmentationof
facilitiesintheentireWarangalmunicipalCorporationarea,forwhichtheWarangal
MunicipalCorporationhaspreparedaCityDevelopmentPlanandaComprehensive
SanitationPlanthroughASCI,Hyderabad.ThisZDPendorsesthetwodetailedutilities
developmentplansandstressesfortakingupthecomponentsrelatingtothisZoneona
THE ISSUE OF EXISTING LEATHER UNITS IN THIS
ZONE:
MostleatherunitsexistinginWarangalarelocatedinthiszoneespeciallyinthe
areanearDesaipetcolonyandEnumamulaColony.Theseunitscurrently
supplyrawmaterialtotheprocessingunitsinChennaiandKolkata.Thisisa
policyinwhichtheAPIIC,LIDCAPinconsultationwiththeAPPCBneedtotake
upsuitablemeasuresfortheexistingLeatherandtanneryunits.

IMPLEMENTATION STRATEGY OF WARANGAL ZDP:


AnImplementationStrategywithresponsibilityonaSteeringCommitteehas
beenadvocatedintheRevisedMasterPlan.InrespectofZDPs,itisthe
Commissioner,WMCwhoisin-chargeofitssuccessfulimplementationand
evolvingasuitablestrategyforthis.InthisroleofKUDAisconfinedtothe
developmentoftheInnerringroadandOuterRingRoads,anditsinputsinthe
overallTrafficManagementPlan.
InsofarimplementationofthisZDPisconcerned,WMCwouldberequiredto
createaseparateDivisionforimplementation.Unlessthisisdonealongwitha
soundfinancialanalysisanddedicatedfunding,theproposalsoftheZDPand
thevariousprojectsandthrustareasadvocatedintheZDPwouldnotfructify.
Further course of
action
This draft MP and Warangal ZDP have been
finalisedbasedonGovernmentinstructionsandthe
inputs/ feedback received from experts, and other
stakeholders.
This Draft Mpand ZDP are to be notified for
Objections&Suggestionsfrompublic&localbodies
givingatimeofonemonth.
ThereaftertheDraftMPwillbefinalized&putupto
the Authority for approval.After approval of the
finalised Draft Master Plan & Warangal ZDP, both
willbeforwardedtoGovernmentforsanction.
THANKYOU