OF
TESTING:
WHAT ARE THE DIFFERENT FORMS
OF TESTING??
Testing of structural
components are classified into two
(2) namely, DESTRUCTIVE TESTING
(DT) & NON DESTRUCTIVE TESTING
Destructive testing, as the
(NDT).
name implies destroys a certain
weak portion/ whole portion of the
structural
Though component.
it may sound like
expensive as the whole component
could be destroyed, it actually is
Testing involving the
destructive method are much
easier to be carried-out by using a
much cheaper and less
complicated device/ equipment.
As well as its results are much
easier to interpret as compared to
NDT.
That it is desirable for test
specimens that are mass produced
(like pipes) and undesirable to
those that are not mass produced
(like ships, planes, etc.)
NDT which stands for NON-
DESTRUCTIVE TESTING gives
analysis to evaluate the properties
of a material, component, or
system, WITHOUT CAUSING
DAMAGE onto the specimen.
It uses a wide range of
analysis techniques and at the
same time certain equipments/
instrumentations to give
diagnostics.
TYPICAL METHODS
OF
TESTING:
The field of industry employs a
wide array of testing procedures
and these include the following:
1. Hydrostatic Pressure Testing
2. Pneumatic Testing
3. Flow/ Service Testing
4. Head Pressure Testing
5. Visual Inspection
6. Holiday Testing
7. Equipment Testing
1. Hydrostatic Pressure Testing
THE PIPING
SYSTEM
2. Pneumatic Testing
INSTRUMENTAT
ION LINES
LIQUIGAZ PLANT PREMISES
PBR PLANT PREMISES
PTT DEPOT PREMISES
A PIPING SYSTEM is an
indispensable mechanical part of
any type of industry that makes
use of fluids as part of their
A piping system allows the
processes.
convenient handling of fluids from
one location to another or from
one process into another at
precise amounts or volumes made
1. Pipes/
possible by thepipelines
use of:
2. Various fittings
3.
Instrumentations
WHY IS IT
NECESSARY
TO TEST THE
PIPING SYSTEM??
CHINESE INDUSTRIAL
PLANT
BRAZILIAN INDUSTRIAL
PLANT
Testing the PIPING SYSTEM is
necessary so that the ERECTED
PIPELINE will:
1. Have uninterrupted fluid flow/
operation.
2. Save on costs, re: maintenance
& leaked fluid.
3. Ensure the safetiness of working
personnels/ operators of such
system from any catastrophic
breakdown/ leakage of hazardous
substances..
Testing actually starts from its
individuals components/ materials,
namely the pipe itself & piping
components such as valves and
fittings Such testing
is more on the
flaw* on how
such components
were made.
PRESSURE
GAUGE JOINT
ZERO READING
PRESSURE
GAUGE
REGISTER PRESSURE
JOINT
BLOW UP OF JOINT
Showing JOINT DEFECT
3. LEAKING TRANSPIRES DUE TO PRESSURE.
PRESSURE
GAUGE
PRESSURE DROPS,
DUE TO LEAK LEAK
FLUID PRESSURE
Blow-up Section
Showing leak due to weld joint failure
NO LEAK PIPING SYSTEM/ VESSEL..
PRESSURE GAUGE
NEEDLE IS STEADY OR
STATIC
TEST
PRESSURE WATER PRESSURE.
SET-UP FOR HYDROSTATIC PRESSURE TEST
A:Test Equipment
1. Water Supply
2. Test Pump
3. Manifold
Gate Valve
Check Valve
Relief Valve (see note)
Connector for inlet/outlet
Pressure Gauge (calibrated)
Wye Strainer/ Drain
RELIEF/ VENT VALVES
WYE STRAINER/ DRAIN
SET-UP FOR HYDROSTATIC PRESSURE TEST
B. Piping System to be tested
7. Pressure Gauge
(calibrated)
Hydrostatic testing at high pressures is very
dangerous. If a portion of the system fails during
hydrostatic testing, serious injury and even
death can result; therefore, the test must be
performed only under close supervision by
qualified personnel.
A. mechanical test
plugs B. welded
caps
C. blind flanges
-- bolt
connected -- slip
Mechanical test plugs:
used when test
pressure to be used in the
piping system to be tested is not
extremely high.
Rubber which as a
SEALANT that
expands/ contracts
depending upon
the bolt/ nut
movement
Welded Caps:
Used when test
pressure to be used in the
piping system to be tested is
Emphasis
extremely high. should be given
to the welding procedure
where it is tested (preheated
and thenDisassembling the cap
stress relieved.. )
from the weld is done by torching
or by mechanically cutting
(grinding) through it
Blind Flange:
Normally used as the
sealant and is either slipped
through a pair of open flanges or
is paired with a single open
flange while withstanding
extremely high
Much pressures.
easier to
disassemble unlike
the other
sealants though
the disassembly of
its connecting
bolts.
Emphasis is given to the
proper tightening of bolts to
ensure that no leakage would
occur as well avoiding the
warping of the flange face..
Use of
torque
wrench
along with
an open-end
socket
wrench
ensures the
proper
OPEN-END SOCKET
WRENCH
TORQUE WRENCH
RATCHET WRENCH
Torque wrench is primarily
for tightening, using an open end
socket wrench/ ratchetwrench will
do for loosening.
Torque
wrench is
applied at
the NUT and
not on the
BOLT.
TYPICAL BOLT BLIND FLANGE
TYPE:
A SLIP TYPE BLIND FLANGE
could be purchased from
retailers/ it could also be
FABRICATED.
Known as PANCAKE
FLANGE, it should be of the
correct thickness and correct
material so that it could offset
the TEST PRESSURE of the
system.This to prevent it from
bending/ buckling so that it
could be removed after testing..
A SLIP TYPE
BLIND FLANGE has a
T-handle that is
usually cut along
with the blind flange
itself. If not, such
handle could be
welded with the blind
flange itself.
WAYS OF
PERFORMING A
HYDROSTATIC
PRESSURE TEST:
PERFORMING HYDROSTATIC
PRESSURE TEST:
1. PREPARATION
2. TESTING:
2A. Water Filling
2B. Pressurizing
2C. Observation
2D. Confirmation/
approval
2E. Draining
2F. System Restoration
PERFORMING HYDROSTATIC
PRESSURE TEST:
1. PREPARATION
-- seeking approval
(permits) from the proper
authorities of such testing.
-- complying with the set
of SAFETY REQUIREMENTS:
Barricading the test area
Putting signages on the
adjacent areas the use of PPEs
Requiring
to test personnel/ even the
non-test personnel
PERFORMING HYDROSTATIC
PRESSURE TEST:
2. TESTING:
2A. Water Filling:
-- Open the HIGH POINT VENT
VALVES/ BLEEDER VALVES
AIR
WATER
PERFORMING HYDROSTATIC
PRESSURE TEST:
2. TESTING:
2A. Pressurizing:
-- Slowly build-up the test
pressure up to 50% of its test
capacity
-- Operator should at least be
wary of the pressure given-off by
the pump
** Rate of pressurization should
not exceed 29 psi/ min (2 bars/
min).
-- Operator should also be aware
of possible leaks even at this
minimal pressure..
PERFORMING HYDROSTATIC
PRESSURE TEST:
2. TESTING:
2A. Pressurizing:
-- Give pressure increments of
10%, 60%, 70%, 80%, 90%, until
100% (final
** At eachtesting pressure)
increment wait for the
system to stabilized before adding
on additional pressure
-- Observe again for any
possibilities of leaks with each
possible increments
-- Upon reaching the desired test
pressure, you may now close the
valve between the test pump and
PERFORMING HYDROSTATIC
PRESSURE TEST:
FURTHER LEAKING
LEAK
50% 60%
70% 80% 90% 100%
15 mins/ more
Report:
with leak
PERFORMING HYDROSTATIC
PRESSURE TEST:
3. OBSERVATION:
-- Following the application of the
FULL HYDROSTATIC TEST
PRESSURE, test pressure is then
reduced at AT A VALUE NOT LESS
THAN THE WORKING PRESSURE OF
THE
-- AsPIPING WSYSTEMcould now
such observation
be made at a much nearer
distance giving emphasis on joint
connections (flanged/ threaded
** In certain instances such JOINTS are
joints)
actually painted to make
observations much easier
PERFORMING HYDROSTATIC
PRESSURE TEST:
MAXIMUM Report:
TEST NO leak
PRESSURE
NOT LESS
THAN
MAXIMUM
WORKING
PRESSURE
OF THE
PIPING FURTHER OBSERVING A
PERFORMING HYDROSTATIC
PRESSUREAPPROVAL:
4. CONFIRMATION/ TEST:
-- If there is a LEAK, a report
would be made indicating WHERE
(specific portion) the leak took
place
** At at the
such test pressure
REPAIRS/ it
ALTERATIONS
happened
would be made before the whole piping
system/ specimen is again retested
-- If there is NO LEAK, a report
would also be made fully
CERTIFIED by the contracted
firms designated
** At such tester.
the whole piping system/
specimen is ready for use
PERFORMING HYDROSTATIC
PRESSURE TEST:
Report:
with leak
(for repairs)
CONFIRMATION/
APPROVAL.
PERFORMING HYDROSTATIC
5. DRAINING:
PRESSURE TEST:
-- SLOWLY open (crack) the drain
valve at the test manifold to relieve
pressure from the tested system..
-- OPEN the high point vent valve
to allow air to seep into the
system.. FAILURE TO OPEN THE HIGH POINT VENT VALVE WHILE DRAINING CAN
WARNING CREATE VACUUM IN THE PIPING SYSTEM WHICH CAN CAUSE
COLLAPSE OF THE PIPING COMPONENTS!!!
AIR-IN
VIBRATION IS
MINIMIZED
PIPING ASSEMBLY IS
PREVENTED FROM
WATER-OUT COLLAPSING
PERFORMING HYDROSTATIC
6. RESTORATION:
PRESSURE TEST:
-- Remove temporary items such as
TEST BLINDS, SPOOLS, ETC..
-- Re-install permanent items such
as LINE CHECK VALVE, RELIEF
VALVES, CONTROL VALVES, GASKETS,
ETC to bring back the original
designed piping system..
-- Seek approval from the
authorized personnel of the
contracting/ testing firm that such
piping assembly is FIT to be used..
PERFORMING HYDROSTATIC
PRESSURE TEST:
RESTORATION OF THE
IMPORTANT
REMINDERS/
NOTES IN
HYDROSTATIC
PRESSURE
IMPORTANT REMINDERS/ NOTES
IN HYDROSTATIC PRESSURE
TESTING:
-- The correct test pressure for a
particular piping system..
-- Scope/ limitation of such testing
on a given assembly to be tested (at
what part/ portion)..
-- Location of instruments & if such
could be included in such testing. If
not a DUMMY should be created
-- Proper usage of piping supports..
LEAK
GAS PRESSURE
Blow-up Section
Showing leak due to weld joint failure
CONDITIONS NECESSITATING
PNEUMATIC TESTING: