RANG DONG FIELD - MARCH 2007

GAS TURBINE 2610 REPLACEMENT


SECLECT AREA FOR MOVING GTC OUT OF SKID

(IN GAS METERING SIDE?)

Advantage:
-No need shutdown GTC2 when carry
out heavy lift
Disadvantage:
-Cut structure beam
-Shutdown fuel gas line (10 days)
-Need disassemble 01 valve (actuator)
-Modify removal trolley beams
AREA BETWEEN GAS TURBINES?

Advantage:
-Confidence for lifting as it is meet
design drawing
-No need shutdown fuel gas line
-No need to cut structure beam
Disadvantage:
-Need to shutdown GTC2 when carry
out heavy lift (30)
-Modify removal trolley beams
WORK STEPS FOR REMOVAL OF
OLD ENGINE OUT OF ITS SKID
1. REMOVE PANEL DOORS TO OUTSIDE

1. Install two eyebolts in lift receptacles in upper panel frame


2. Remove panel clips at bottom of panel frame inside enclosure
3. Use overhead crane (or chain block) above enclosure and attach lift
equipment hooks to eyebolts
4. Unseat bottom of panel by raising panel up to top of the retaining
angle, then pull bottom of panel outward to clear turbine skid
5. While guiding bottom of panel away from enclosure, low panel to
clear the top retaining channel
Use crane to lift panel up (PK2610) and remove to outside area
All panels of PK2610 have been removed
DISASSEMBLE STARTER MOTOR

1. Make sure the motor has been isolated (ICC)

2. Use chain block to secure the starter motor


with the existing monorail

3. Unscrew bolts (6)


4. Control chain bock and move the motor to
temp. platform
DISASSEMBLE HYDRAULIC DRIVEN PUMP

1. Install chain blocks to the existing monorail and


hydraulic driven pump (see the picture)
2. Disassemble all bolts on flanges, connected to
engine & suction pipe
3. Control chain blocks and move it on temp platform
DISASSEMBLE/REMOVE AN ELECTRICAL & INST. EQUIPMENT

Remove or disassemble all instrument /


electrical cables which are concerned
(obstructed) to the engine
- REMOVE INSULATION SHEET FROM ENGINE & EXHAUST
- REMOVE BOLTS/NUTS FROM INLET & EXHAUST DUCT FLANGES
Install 4 hoists to existing beams before installation of removal trolley beams
(outside)
1. Install a reinforcement beam to the top of
GTC enclosure, using platform crane &
chain blocks
2. Install beams & fittings as indicated in the
drawing below, using platform crane
The trolley beams have been installed

The trolley beams are being installed


REMOVE ENGINE MOUNT ASSEMBLY (forward)

Disassemble bolts/nuts (6 &7)


REMOVE ENGINE MOUNT ASSEMBLY (aft)

Disassemble items: 19, 20


and 17 (one side only)

Disassemble items: 8 to 12
MOVE OLD ENGINE TO OUTSIDE THE SKID

Move the old engine out by using


hoists (02) on trolley beams
SOME MORE PICTURES
INSTALL A SINGLE POINT LIFTING BEAM TO THE ENGINE FOR
ADJUSTING IT TO THE MIDDLE
ENGINE REST ON WOODEN BLOCKS
REMOVE EXHAUST DUCT FROM ENGINE

1. Use platform crane or chain blocks


to hanging exhaust before step 2, 3

2. Remove bolts/nuts (14, 15, 16)

3. Move exhaust out of engine


SOME MORE PICTURES
REMOVE GEAR BOX FROM OLD ENGINE

Temp. tool
Due to removal of starter motor & hydraulic pump
completed before engine is out of skid, so
temporary tool for disassemble of gear box needs
to be fabricated to make it balance with gear box
(C.G) during removal
REMOVE GEAR BOX FROM OLD ENGINE

1. Install temporary tool & chain blocks 3. Remove the remaining bolts (11, 12, 13)
to gear box (see the pictures)
2. Replace some bolts (06) by guide rods 4. Pull out gearbox, using chain blocks &
temporary tool
PICTURES OF GEAR BOX

ON GEAR BOX

ON ENGINE
REMOVE AIR INLET COLLECTOR FROM ENGINE

1. Install chain blocks to gear box &


existing structure (see the pictures)
2. Remove bolts (2, 3 & 4; 5, 6, 7 &8)

3. Pull the air collector out


PREPARE FOR REMOVAL OF OLD ENGINE TO OPEN AREA

1. Use platform crane to remove old 2. Engine is being lifted up


engine to outside
SOME MORE PICTURES
REMOVE A COUPLING FROM
NEW ENGINE
REMOVE A COUPLING FROM
NEW ENGINE
CLUTCH PARTS
CLUTCH PARTS
LIFTING NEW ENGINE AND MOVE IT TO THE SPACE
BETWEEN TWO TURBINES
NEW ENGINE AT THE SPACE BETWEEN TWO TURBINES
INSTALLING AIR INLET COLLECTOR AND ACCESSORIES
TO NEW ENGINE
HEATING A COUPLING TO 120-135oC IN OVEN

INSTALLING
THE HEATED COUPLING TO ENGINE
INSTALLING GEARBOX TO NEW
ENGINE

INSTALLING THE DRIVEN ADAPTER


TO GEAR BOX
PREPARING FOR REMOVING THE
ENGINE TO THE POSITION ON THE SKID
REMOVING THE ENGINE
TO THE POSITION ON THE SKID
INSTALLING ENGINE MOUNT ASSEMBLY
INSTALLING HYDRAULIC PUMP

INSTALLING THE STARTER MOTOR


EQUIPMENT ALIGNMENT
(REFER TO SOLAR DWG No: 71681-149894)
EQUIPMENT ALIGNMENT
REFER TO SOLAR DWG No: 71681-149894
CHECKING ALIGNMENT

(INSTALLING THE ALIGNMENT TOOLS)


CHECKING ALIGNMENT

(ALIGNMENT TOOLS)
INSTALLING IGV ACTUATOR AND
ACCESSORIES TO THE ENGINE
LESSON LEARN
LESSON LEARN
A. PREPARATION
1. Not familiar with lifting beam arrangement at
first time

2. Confusing for selection of loadout area


LESSON LEARN
3. Not utilize the available lifting tools for disassembling starter
motor and gearbox
LESSON LEARN
4. No single point lifting tool is available (not purchased)

5. Four hoists are available, but not good in condition (New hoists
need to be purchased for future use)

6. Not enough special tools for the job such as oven, temporary
stand
LESSON LEARN
B. DURING CARRYING OUT THE WORK

1. Too many persons were involved with lifting operation. It must be


controlled by deck foreman
2. Service Engineer: not familiar with some tasks during disassembling
of engine

3. Due to building the temporary platform (by scaffolds), so access


to/from engine was limited. This platform is not necessary for removing
the engine
LESSON LEARN
C. AFTER COMPLETION OF THE WORK

1. Not good pack of old engine before sending to onshore for overhaul,
caused the engine got corroded badly

2. List of the hired tools have not been checked before turning back to
VSP, causing some items missing (need to be ordered)