Advantage:
-No need shutdown GTC2 when carry
out heavy lift
Disadvantage:
-Cut structure beam
-Shutdown fuel gas line (10 days)
-Need disassemble 01 valve (actuator)
-Modify removal trolley beams
AREA BETWEEN GAS TURBINES?
Advantage:
-Confidence for lifting as it is meet
design drawing
-No need shutdown fuel gas line
-No need to cut structure beam
Disadvantage:
-Need to shutdown GTC2 when carry
out heavy lift (30)
-Modify removal trolley beams
WORK STEPS FOR REMOVAL OF
OLD ENGINE OUT OF ITS SKID
1. REMOVE PANEL DOORS TO OUTSIDE
Disassemble items: 8 to 12
MOVE OLD ENGINE TO OUTSIDE THE SKID
Temp. tool
Due to removal of starter motor & hydraulic pump
completed before engine is out of skid, so
temporary tool for disassemble of gear box needs
to be fabricated to make it balance with gear box
(C.G) during removal
REMOVE GEAR BOX FROM OLD ENGINE
1. Install temporary tool & chain blocks 3. Remove the remaining bolts (11, 12, 13)
to gear box (see the pictures)
2. Replace some bolts (06) by guide rods 4. Pull out gearbox, using chain blocks &
temporary tool
PICTURES OF GEAR BOX
ON GEAR BOX
ON ENGINE
REMOVE AIR INLET COLLECTOR FROM ENGINE
INSTALLING
THE HEATED COUPLING TO ENGINE
INSTALLING GEARBOX TO NEW
ENGINE
(ALIGNMENT TOOLS)
INSTALLING IGV ACTUATOR AND
ACCESSORIES TO THE ENGINE
LESSON LEARN
LESSON LEARN
A. PREPARATION
1. Not familiar with lifting beam arrangement at
first time
5. Four hoists are available, but not good in condition (New hoists
need to be purchased for future use)
6. Not enough special tools for the job such as oven, temporary
stand
LESSON LEARN
B. DURING CARRYING OUT THE WORK
1. Not good pack of old engine before sending to onshore for overhaul,
caused the engine got corroded badly
2. List of the hired tools have not been checked before turning back to
VSP, causing some items missing (need to be ordered)