Good preparation will improve SSV efficiency extremely, which are included in following
slides:
System
Parameters Audit
Verification Test
SSV Control
Table
Y Problem
Troubleshooting
Found?
N
SSV Report
Generation SSV
Report
Radio Network
Tuning
Before starting the drive test, we need to define the test methodology with customer,
including:
Test Method: long call, short call, Video call, throughput test method, etc.
Test Period for each type of test.
Categories for test UE.
File Size for Download and Upload (throughput) and ftp window size configuration.
DT Check Items as per SSV report format.
The principles for SSV DT route planning must be defined together with customer.
Check
Comm
Category Checks
(OK/ ent
NOK/NA)
Frequency and Scrambling Code correctly defined
PS PS detach is checked
Soft handover for voice service to and from the 3G cells checked OK
Handover Soft handover for VP service to and from the 3G cells checked OK
Check
Comm
Category Checks (OK/
ent
NOK/NA)
Dynamic Test/Moving Test: In the dynamic drive test we have to move the each sector
with Genex Probe connect and record its values of RSCP & Ec/No. The Value of RSCP
& Ec/No should be good. In dynamic Drive test we have to test Coverage, quality and
Handovers of all the sectors in Long call. Long Call:- Long call means continuous call
on testing number.
PS DL throughput
(Measured on Application Level)
in R99 for FTP R99 Data Services
Average throughput = 80% of the RAB capacity for all RABs
Transfers
Data
Performance
PS UL throughput
(Measured on Application Level)
in R99 for FTP R99 Data Services
Average throughput = 80% of the RAB capacity for all RABs
Transfers
Now you
are ready
for DT.
11. For checking Irat handover of CS and cell reselection from 2G cell to 3G cell in packet
mode of PS are performed by MS3, MS1. In this test we set the mobile network in Auto
MODE to check the 3G to 2G Handover in MS3(check from bellow left side snapshot).
12. For cell reselection in CS mode and 3G to 2G and 2G to 3G we perform it Automatically
by MS2 (check it from right side snapshot).
13. In Cell reselection test in PS mode, first we have to connect internet by the dialup then
we can check this test by browsing.
14. After completing those tests we perform the mobility test. In mobility test MS2 is in idle
mode MS3 in dedicated mode, MS1 is in PS mode. In MS1 we download a file from the
given server. In this test we try to cover the entire possible road in that particular site
15. In mobility test, we check also the soft and softer handover for the particular site for both
CS and PS mode.
16. After completing all the functionality test, we have to perform coverage test by locking
PSC and 1st carrier frequency of particular sector and drive until sector RSCP <=-
105dBm.
Most of the problems in SSV phase are related to installation and parameter problems,
so RF Engineer has to distinguish the problems and send the solution to different
teams, apart from monitoring the troubleshooting progress. It is recommended to
propose that installation team prepares one team to be dedicated to troubleshoot SSV.
A SSV Record Table is required to record all the SSV actions, including problems, test
times, test date and by the SSV control table it is easy to get progress statistics.
Once the test result is acceptable and problems are solved, generate the SSV Report.
Report format will be as per operator demand.
An An An An
te te te
te
nn nn nn
nn a-
a- a-
a- B B
A A
Tx/Rx
Tx/Rx
Rx
Tx/Rx
Rx
Tx/Rx
Rx
Rx
Sector_A Sector_B Sector_A Sector_B
Right Wrong