0 - PP Module
SAP ECC 6.0
SAP the company was founded in Germany in 1972 by five ex- IBM Engineers.
SAP R/3
S - System
A Applications
P Products
But now the SAP R/3 product name has been changed into SAP ECC (ERP Central
Component), the latest version - SAP ECC 6.0
A real time platform that provides accurate and easy to use Management Information
System
Provides information transparency and increase decision making capability
Enables global management and information sharing among companies, divisions and
business units.
Reduced or eliminating non-value-adding work
SAP ECC 6.0 Application Modules
Project SHAKTI is a project undertaken to implement SAP at all the units of L&T Power
through L&T Infotech.
The following process of SAP are taken into consideration for Project SHAKTI at L&T MHI
Boilers Pvt. Ltd.
MTD processes which are being addressed in Project SHAKTI are as follows:
Process Description
Number
MTD010_B Production Planning, Scheduling and Control
MTD020_B Material Requirement Planning Project based
MTD040_B Material withdrawal process from Stores
MTD060_B Incorporation of Master data changes into Production order
MTD080_B Shop floor execution, activity confirmation and data capturing
MTD110_B Rework and Rejection processing
Company Code
Definition
Company Codes are not optional within SAP and are required to be defined.
Characteristics
Structure
Code Name
1000 EPC-Power
1200 L&T Power Limited
1600 L&T MHI Turbine Generator Private Limited
1800 L&T MHI Boiler Private Limited
Plant
Definition
It is a place where either materials are produced or goods and services provided.
Use
The company code plant assignment will be done as per the table below:
Definition
Storage Location is the place where stock is physically kept within a plant.
Use
Stocks are managed only on a quantity basis and not on a value basis at storage
location level
LMB Plant - Hazira LMB Office - Faridabad LMB office - Vadodara LMB project - Site1
1800 1810 1820 1830
BMS1 BRM1
LMB Main Store LMB RM Store
BMN1 BQA1
LMB Maint. Store LMB Quality Store
BFG1 BSA1
LMB FG Store LMB Shop Store A
BSB1 BSC1
LMB Shop Store B LMB Shop Store C
BSD1 BSE1
LMB Shop Store D LMB Shop Store E
BSF1 BSCR
LMB Shop Store F LMB Scrap Yard
SAP ECC 6.0 PP Module
The Production Planning & Control (PP) module of SAP takes care of Master data
needed like
Work Center
Routing
Definition
The material master (item Master) contains information on all the materials that a
company procures, produces, stores and sells.
It is the companys central source for retrieving material-specific data. This information
is stored in individual material master records.
Materials with the same basic attributes are grouped together and assigned to a
material type like
Raw material
Semi-finished material
Finish material
Consumables
Tools
Components
Packaging material
Spare parts
Assets
Attributes of a material are stored in various views of Material Master.
Person responsible for defining the planning and production related attributes of
material master will extend the MRP1, MRP2, MRP3, MRP4, and Work Scheduling views
of material master.
Work scheduling view is created only for in-house manufactured items. (& not for
purchased items).
Data contained in Material Master with respect to PP Module (Production Planning and
Control) is used for material requirements planning, scheduling, and work scheduling.
Major planning and production specific data that we maintain in the material master
specifies the following:
Material Requirement Planning procedure, where we specify relevance of MRP and MRP
Controller for the material
E In-house production
F External procurement
X Both procurement types
Lead times, where we specify the In-house production time, planned delivery time etc
to calculate scheduled dates
The planning strategy to be used for planning the material i.e. Make to Stock or Make
to Order.
Definition
The bill of material is a complete, formally structured list of the components that make
up a product or an assembly.
The list contains the item number of each component, together with the quantity and
unit of measure.
A group of parts that is assembled, and that forms either a finished product or a
component of a finished product, is an assembly.
Material Provisions for production: The production storage location can be specified in
the bill of material for each component
The production planner uses bills of material as a basis for operation planning and
production control (Work Scheduling)
Product Costing: To calculate the cost of the materials required for a specific finished
product.
Work Center
Definition
Scheduling
Operating times and formulas are entered in the work center, so that the duration of
an operation can be calculated.
Costing
Formulas are entered in the work center, so that the costs of an operation can be
calculated. A work center is also assigned to a cost center.
Capacity planning
The available capacity and formulas for calculating capacity requirements are entered
in the work center.
Routing
Definition
It also contains the information about the operations and the order in which they are
carried out.
A routing also contains details about the work centers at which they are carried out as
well as about the required production resources and tools (includes jigs and fixtures).
Definition
Production resources/tools (PRTs) are the capacities you require to perform an operation
at a certain work center
Production resources and tools are assigned to production orders for which they are
required
The system provides a function, with which you can check whether the production
resources/tools that you require for the order are available.
A set of techniques that uses bill of material data, inventory data, and the master
production schedule to calculate requirements for materials. It makes recommendations
to release replenishment orders for material.
This process involves the monitoring of stocks and, in particular, the automatic creation
of procurement proposals for purchasing and production.
Terminology Used
Planned Order
It is an output of the MRP process which triggers the initiation of in-house production.
It is a proposal generated by the system. It specifies when material required for the
production should be made available and in what quantity.
It is not binding and does not therefore trigger procurement directly, but it serves
for planning purposes.
It can be changed or deleted at any time (exceptions: planned orders for direct
production and for direct procurement).
Whether a material will later be produced in-house or procured externally is left
open.
For materials produced in-house, it specifies the basic dates for production.
Terminology Used
Purchase requisitions
These are the internal documents used to request purchasing department to procure a
particular quantity of a material or a service for a particular date.
Production Order
It also defines which resources are to be used and how the order costs are to be
settled.
Production orders are used to control production within a company and also to control
cost accounting.
Terminology Used
An order type contains control information that is needed for managing the order.
Every order is to be assigned to an order type. Each order type can have a separate
number range.
The various order types and their number range lengths are identified by business as
below;
Reservation
It is a request to the warehouse to keep materials ready for withdrawal at a later date
and for a certain purpose. This simplifies and accelerates the goods receipt process.
A reservation for goods issue can be requested by various departments for various
account assignment objects (such as cost center, order, asset, etc.)
Pick Slip
It is the list of material with qty. to pick with respect to reservation.
Cost Center
General or operating accounts are known in SAP as Cost Centers. Cost Centers are
budgeted on the fiscal year.
Transaction Code
Transaction let users to create, change or display data or run a report in SAP. For each
process there is a code.
Process Steps - Production Planning & Scheduling
Process Steps - Material Requirement Planning
Click on the
Log On
User
LMBTEST06
Password - lntmhi
Create Material
Access Transaction by
Via Menu : Logistics > Production > Master Data > Material Master > Material >
Create General
Via Code : MM01
Field Name R/O/C User Action & Value
Press Enter
Transaction Code List
Business
Business Process Step T Code Activity
Process
CS01 Create BOM
BOM Create Change
CS02 Change BOM
CS03 Display BOM
BOM _Display CS11 Display BOM Level by level
CS12 Multilevel BOM
Business
Business Process Step T Code Activity
Process
Running Material Requirement Planning for
MD51 Project
Execute MRP
MD02 MRP - Single-item, Multi-level -
MD03 MRP-Individual Planning-Single Level
MTD020_B
Material MD05 Individual Display Of MRP List
Requirement
MD06 Collective Display Of MRP List
Planning Project
Based MD04 Display Stock/Requirements Situation
Evaluate MRP Results
MD07 Current Material Overview
MD09 Pegged requirement List for an MRP List
MD4C Multilevel Order progress Report
Transaction Code List
Example: Project Def. 1st Level 2nd Level WBS 3rd Level WBS
11001A - 12 - 100 - 0001