2
IMPORTANCE
3
IMPORTANCE
A comprehensive plan will not guarantee success, but
lack of a sound plan will, almost certainly ensures failure
4
OBSTACLES TO EFFECTIVE
PLANNING
Time span covered
As time span of work concerned increase, accuracy
of planning decreases
Present conditions weight heavily in planning &
overshadow future needs may result in errors of
judgment.
5
OBSTACLES TO EFFECTIVE
PLANNING
Mental ability
Planning requires a difficult kind of thought process
Lack of information
Planning may be affected by lack of sufficient
information or deficiencies in its accuracy & quality
Cost of planning
Planning cost include those who plan, control, maintain
the plans & the costs of reworks or delays when
planning is incomplete 6or incorrectly done
WHAT IS GOOD PLAN?
Designed/developed together with project team
members
Must be flexible
Precipitate action
7
WHAT IS GOOD PLAN?
Depending upon the type of project, a plan can
comprise of long range, intermediate range and short
range
8
WHAT TO PLAN?
Construction Planning
9
SIGNIFICANCE OF PLANNING
The Client:
Know how long the project will take to enable the
determination the project capital outlay needed
10
SIGNIFICANCE OF PLANNING
The Consultants:
Identification of key milestones in the design and
construction stage of the project
Anticipating and undertaking tasks at various deadlines at
the various stages of the work
Identifying who does what and when
Identify the critical activities which influence the project
outcomes
Identifying when the contractors will be engaged in the
project
Monitoring the design and construction processes
11
SIGNIFICANCE OF PLANNING
The Contractors
During the tender stage
Determine a realistic contract duration
Decide the construction method
Identify what resources will be required for the project
During construction stage
Provides the basis for the project implementation strategy
and WBS
Planning & scheduling of resources
Engagement of sub contractors
Approvals, claims & payments
Weekly operations
Monitoring work progress
Re planning construction activities
Resource allocation
12
IMPORTANCE OF
CONSTRUCTION PROGRAMME
IN CONSTRUCTION CONTRACT
A key term of reference of the contract
Provides a basis to monitor progress
The contractors considered scheme of work
Commitment to follow the method and sequence of the
construction outlined
Revisions and alterations from clients/consultants may result
in extra payment
Should the contraction/sub contractors fail to meet their
programmes - penalty
13
FACTORS INFLUENCE THE
PROJECT PLANNING
The definition of work tasks
The choice of technology
Methodology of carrying out the works
Estimation of the required resources
Duration of the individual tasks
Interactions among the different work tasks
Site location
14
COMPILING A PROGRAMME
Resources
Organisation and utilization of labour, plant and materials
Activities
Packages of work which consumes resources
Logic
The relationship and interdependence between activities
15
COMPILING A PROGRAMME
Duration
The level of resources allocated / activity
The output of these resources
The quantity of work
External restraints
Partial completion or sectional handover
Constraints on material and plant delivery
Labour constraints
16
COMPILING A PROGRAMME
Method Statement
Can be in formed of schedule, listing only briefly on the
main points of the construction method, plant and labour
involved.
Is the first attempt used to show the inter-relationship
between the various activities that will be undertaken to
complete the activities
It highlights the critical aspects of the project and
concentrating planning on the restraints imposed by those
activities
17
COMPILING A PROGRAMME
18
TAJUK PROJEK : MEMBINA MAKMAL KOMPUTER SEKOLAH
NO AKTIVITI TRED KUANTITI JENTERA BURUH ANGKATAP PENGIRAAN TEMPOH (HARI) KOS (RM)
2 Pengorekan Syarikat 45.9M3 Backhoe(1 Unit) 1 4M3/jam 45.9 =12jam 1 1/2 545. 00
4
4 Lapisan tegar Tukang 39.3M3 Jentera Pemadat ( 1 Unit) 2 1.5M3/jam 39.3 = 13jam 1 1/2 1, 422. 25
Konkrit Backhoe(1 Unit) 1.5 x 2
6 Konkrit Alas Tukang 13.1M3 Mesin Pembancuh 2 1.6M3/jam 13.1 = 4jam 1/2 1, 465. 95
Gred 15 Konkrit Konkrit (1Unit) 1.6 x 2
9 Konkrit lantai Tukang 50.7M3 Mesin Pembancuh 4 1.6M3/jam 50.7 = 8jam 1 6, 768. 34
bawah Konkrit Konkrit (1 Unit) 1.6 x 4
Gred 30
10 Menanggalkan Tukang 33M2 - 2 6M2/jam 33 = 3jam 1/2 30. 00
Acuan Kayu 6x2 19
CONSTRUCTION PROGRAMMES MUST:
Realistic
Achievable
Unambiguous
Based on available information
Co coordinated with any other programs for the work
e.g. that of plant and material purchasing managers
IT MUST SHOW:
All significant activities which should be clearly defined
The work of specialists
Consistent forms of visual expression for clarity & ease
identification
Ease monitoring performances
20
IT MUST REFLECT
Sound construction methods
Availability & economical use of resources
Constraints of all kinds including environmental influences
Holiday & other calendar irregularities
Seasonal influences
21
TYPES OF PLANNING TECHNIQUES
1. Bar Chart
2. Line of Balance
3. Network Analysis
a. Precedence Diagram (AON)
b. Activity on Arrow (AOA)
22
BAR CHART / GANTT CHART
Definition: is a traditional management device for planning &
scheduling construction projects
Earliest planning method introduced by Henry Gantt (19th
century)
Features:
Easiest to understand
Most widely form of planning tool
A series of bars plotted against a horizontal time scale
Left hand side listing the operations / activities to be
carried out
23
BAR CHART / GANTT CHART
Features (contd):
Right hand side bars plotted to a time scale
Shows the start and finish time and also the duration of
each activity
Bar charts also used to monitor progress of work
Double horizontal bars i.e. programmed & progress, or
Single bar indicate / colour actual progress on that
original bar
ACTIVITIES TIMESCALE
24
BAR CHART / GANTT CHART
Levels of details of activities
Level of details of activities depends on the intended use
of the plan. Examples:
Tender stage:
- only shows key items of works
- to prepare tender
For co.s chairman:
- in very broad term
- to see progress
For site manager:
- more detail
- to control the progress
For site engineer:
- very detail
- to execute the work
25
BAR CHART / GANTT CHART
Time scale
Time scale is also prepared to suit the users propose.
Examples: chairman use months, site managers
weeks, engineers days
Advantages
Easy to understand
Most readily recognised format
Quick & ready to prepare
The start & finish dates & duration of each activity is
clearly shown
26
BAR CHART / GANTT CHART
Disadvantages
Unable to depict in detail the multitude of inter
related shown dependencies
Unable to ascertain critical activities
WORKDAYS
ACTIVITY
1 2 3 4 5 6 7 8 9
Site clearing
Dig Trench #1
Dig Trench #2
Assemble pipe #1
Install pipe #1
Install pipe #2
Backfill #1
Backfill #2
27
LINKED BAR CHART
Advantages
The merits of bar charts are retained
Provides a more realistic presentation of the coordination
needs of the projects
Indicates the interdependencies of activities and
consequently the effects of localised delay
Disadvantages
The concept of float is missing
Shows clear linkage of activities
The linking of activities may be limited
28
LINE OF
BALANCE
Is suitable for repetitive works
such as high-rise construction,
tunnels, roadway pavement
construction, pipelines and
housing projects.
The work of each gang
appears as an inclined line that
is being also related to the
output of the gang.
Line of diagrams connect
like activities and express
them as a rate of delivery.
29
PROJECT NETWORK
Activity-on-node (AON)
nodes represent activities,
and arrows show
precedence relationships Node
Activity-on-arrow (AOA)
arrows represent activities 1 2 3
and nodes are events for
points in time
Event Branch
completion or beginning of
an activity in a project
30
ADVANTAGES
31
DISADVANTAGES
32
NETWORK ANALYSIS
Network Analysis
Activity on the Arrow
Activity on the Node (Precedence)
NETWORK ANALYSIS
Critical Path
Float Diagram
Early Start - the earliest date a task could start without conflicting
with dependency relationships
Early Finish the earliest date a task could finish without affecting the
Project end date
Late Start the latest date a task could start without affecting the
project end date
Float - the difference between the time available to complete a
task and the estimated task duration
CPM NETWORK
Now
Before Next
Same
time
Activity on Arrow (A.O.A)
Steps;
- listing of the activities
- Producing a logical network of activities
Activity 1 Activity 2
event event event
Dummy activities
Dummy Activities
A B
Dummy
C D
No Looping :
No Hanging :
Activity on Arrow (A.O.A)
Joiners
first fixing
4
Activity on Arrow (A.O.A)
Terms to remember:
- Earliest Start Time (E.S) = the earliest date a task could start
without conflicting with dependency relationships
- Latest Start Time (L.S) = the latest date a task could start
without affecting the project end date
- Earliest Finish Time (E.F) = the earliest date a task could finish
without affecting the Project end date
- Latest Finish Time (L.F) = the latest date a task could finish
A C C
A
D
B B D
Mode Configuration (A.O.N)
ES EF Earliest finish
ACTIVITY
LS LF
Latest finish
FS
Finish-to-Start (FS) :
Start-to-Start (SS) : SS
Finish-to-Finish (FF) : FF
Start-to-Finish (SF) : SF
Exercise (A.O.N)
64
12
3
8
12 12 4
1 2
4 6 7
4
4 4
65
The objective of project crashing is to
reduce the project duration while
minimizing the cost of crashing
Project completion time can be
shortened only by crashing on the critical
path
Not all activities have to be crashed
Looking at the critical path and seeing
which activity has the minimum crash
cost per week
66