Terminology
Agreement : Consent of various parties to join hands to
do something for the benefit of one or more parties.
Contract : A legally enforceable agreement.
Client : The beneficiary (Individual or party (ies)) who
may be investor for self or others.
Contractor : The party to execute the requisite work(s).
Consultants: A third party, not a legal partner but
authorized to check the works on behalf of the client.
3
PC I
Project Documentation
PC II
Feasibility Study
PC III
Quarterly Progress Report
PC IV
Project Completion Report
PC V
Evaluation Report after Completion
4
INTRODUCTION
CONTRACT.
A contract is a formalized means of communication
between parties.
5
INTRODUCTION
CONTRACT
In law a contract can be defined:
A valid contract is an agreement made between two
or more parties whereby legal rights and obligations
are created which the law will enforce.
6
INTRODUCTION
CONTRACT
A simple contract consists of an agreement
between two or more parties under certain
terms and conditions whereby one party
undertakes to execute works or to supply
materials at specified rates and the other
party undertakes to make necessary payments
for the work completed by the first party.
7
Types of Contracts
9
Contracts. (cntd)
2-Scheduled Contract
In this type of contract the client may refer to a
schedule of unit rates covering each item of work
and ask the contractors, when tendering, to quote a
percentage above or below the given scheduled rates
for which the contractor would be willing to execute
the work.
10
Contracts. (cntd)
11
Contracts. (cntd)
4-Labour Contract
This is a contract where labour and
workmanship is provided by the contractor but all
the materials are supplied by the client.
12
Contracts. (cntd)
13
Contracts. (cntd)
14
Contracts. (cntd)
15
Contracts. (cntd)
8-Serial Contract
16
Procurement & Tendering
Project Procurement includes the processes to purchase or
acquire the products, services, or results needed from outside
the project team to perform the work.
17
Procurement & Tendering
Good procurement practices can increase corporate
profitability, minimizing cash flow problems, and seeking out
quality suppliers.
18
General Types of Procurement &
Tendering
Civil Works for example, bridges and buildings,
harbors and highways;
Goods typically equipment, material and supplies,
commodities, textbooks, medical supplies; and
Services Consultancy Services, Expert advice and
training conventionally labeled as Technical
Assistance as well as such things as building
maintenance, computer programming, etc.
19
Procurement & Tendering
Procurement can be done through:
20
Normal set of tender documents
1. Instructions to tenders
2. Information to tenders
3. Conditions of contract (general part-i & particular part-
ii)
4. Forms of tender & appendices
5. Specifications ( special & technical provisions
6. Bill of quantities or schedules of prices
7. Form of bid security, contract agreement, performance
Security
8. Drawings
21
Tendering Process
22
A - Pre-requisition for Invitation to
Tender
23
Benefit Cost Raito (B/C Ratio)
The ratio between the present value of
benefits and the present value of costs of a
project during its entire design life.
24
Cost
Cost is define measure of expenditure incurred
for hiring/use of resources to implement the
project.
25
Tangible Cost
The costs which can be quantified and to which a monetary
value can be assigned
e.g.
Capital cost.
Annual recurring cost .
26
Intangible Cost
27
Benefits
29
B/C RATIO
Three situations may be visualized in case of B.C Ratio.
It is a viable project.
31
A - Pre-requisition for Invitation to
Tender. ..(contd.)
A-3. ADMINISTRATIVE APPROVAL
PREPARATION OF PC-1 PROFORMA
APPROVAL BY THE GOVERNMENT
32
B. Formulation of Tender Documents
a. Specifications
b. Design Calculation and Analysis (Design)
c. Tender Drawings
d. Estimation of Quantities
e. Decision about Specific Provisions
f. Decision About funding-e.g. ADB/IDA
(International Donor Agency)
g. Conditions of Contract - Part 1 & II.
33
Tender Documents
General Conditions of Contract
These define the legal rights and obligations of the parties
and may be described as the regulations under which the
contract will be performed.
Nominates an independent third person called the
Engineer who is responsible for administering the
contract
General conditions vary from country to country and
organization to organization
Conditions of Contract internationally
Federation Internationale des Ingenieurs Counseils
(FIDIC), Switzerland, 1992.
Pakistan Engineering Council
34
Tender Documents (Contd.)
Special Conditions of Contract
These are additions to, deletions from or amendments to
the General Conditions to make them project or party
specific.
Specifications
Give full description of work to be carried out
Detail the materials and workmanship that the Contractor
is to utilize in the project
Define the quality and standards of workmanship required
Act as a legal evidence in the event of litigation
35
Tender Documents (Contd.)
Drawings
Bill of Quantities
Quantities are estimates only and should have limits of
accuracy
Tender/Bid
Formal offer to undertake the project. Price, conditions and
method statements are detailed. It should be noted that all
documents submitted with a tender form part of the tender
Letter of Acceptance
Relevant Correspondence
This often include points of clarification of either the
Tender Documents or about the project.
36
Instructions to Tenderers
C-1. Tendering
Tendering Process
LCB (Local Competitive Bidding)/ICB
Tendering
Procedure for Tendering
38
C-2. Evaluation
Tender Opening
Preliminary Evaluation
Detailed Evaluation
Procedure for Preference
39
Tendering gives
Straight forward purchasing or hiring procedure
Objectives of works clear at the time of beginning
Needs are established and clear
Time and cost saving may be taken
Every one offering his optimum price
Healthy competition
Quality assurance
40
Tendering Process
Type of tender (Public Tender/Public Tender
with Pre-qualification/Tender by Invitation)
Advertisement
Pre-qualification documents
Invitation to tender
Purchase of Tender Documents
Pre-tender meetings and joint site visits
Amendments to Tender Documents through
Tender questions.
41
Tendering Process (Contd.)
42
Tender Security
43
C-2 Tender Evaluation
44
Tender Evaluation (contd.)
45
Tender Evaluation (contd.)
46
Tender Evaluation (contd.)
47
Legal & Contractual Evaluation
48
Cost & Financial Evaluation
Correction of Errors
Adjustment of Foreign Currency Components
Interest Rate for Delayed Payments
Price Adjustments
Evaluated Tender Price
Balanced Tender
49
Technical Evaluation
Program of Work
Key Personnel
Mobilization
Method of Construction
Equipment
Dewatering
Sub-Contractors
Materials
50
Tender Evaluation (contd.)
51
D. Contract Administration
Award of Contract
Signing of Contract
Mobilization
Contractual Provisions Enforcement
Important Contract Clauses
52
Notification of Award and Signing of
Agreement
53
Notification of Award and Signing of
Agreement (contd.)
54
Contractual Provisions Enforcement
55
Contractual Provisions Enforcement (contd.)
Priority of Contract Documents
1. The Contract Agreement
2. The Letter of Acceptance
3. The completed Form of Bid
4. Special Stipulations (Appendix A to Bid)
5. The Conditions of Contract Part II
6. The Conditions of Contract Part I
7. The Bill of Quantities (Appendix D to Bid)
8. The Appendices to Bid (B-Foreign Currency, C-Price
Adjustment, E-Schedule, F, G, H, I, J, K, L)
9. The Drawings
10. The Specifications
56
Important Contract Clauses
1. Extensions in time
2. Variation Order
3. Escalation
4. Force Majeure.
5. Remedies & Powers.
6. Dispute Resolution
7. Arbitration
8. Termination of Contract
57
58
59
60
TYPES OF PROCUREMENT
61
TYPES OF PROCUREMENT(Contd.)
62
TYPES OF PROCUREMENT(Contd.)
2 FOR ELECTRICAL & MECHANICAL WORKS
A GOODS/EQUIPMENT SUPPLY CONTRACTS
OPEN TO REGISTERED, ENLISTED &
PRE-QUALFIED MANUFACTURES/
SUPPLIERS(LCB/ICB)
B EQUIPMENT ERECTION CONTRACTS
ON PRE-QUALIFICATION BASIS
(LCB/ICB)
63
TYPES OF PROCUREMENT(Contd.)
4. CONSULTANCY SERVICES
64
Use of PECs Bidding Documents
Standard Form of Bidding Documents has been
approved by ECNEC in its meeting on 12
November 2007. The document has been notified
by Planning Commission, Government of Pakistan
vide Notification No. 8(60)WR/PC/2008 dated 12th
February 2008.
It is mandatory for all engineering organizations
and departments at Federal and Provincial level
and district government to use the document for
procurement of civil works funded locally and/or
through donor agencies.
65