The purpose of a soil investigation program
1. Selection of the type and the depth of foundation suitable
for a given structure.
2. Evaluation of the load-bearing capacity of the foundation.
3. Estimation of the probable settlement of a structure.
4. Determination of potential foundation problems (for
example, expansive soil, collapsible soil, sanitary landfill,
and so on).
5. Establishment of ground water table.
6. Prediction of lateral earth pressure for structures like
retaining walls, sheet pile bulkheads, and braced cuts.
7. Establishment of construction methods for changing subsoil
conditions.
8. To investigate the safety of the existing structures and to
suggest the remedial measure.
Stages of subsurface exploration program
Exploration methods
Borings Sounding or
Test pits, Trial Auger penetration
pits, Trenches Auger and shell Tests and
Wash Boring Geophysical
Percussion drilling methods
Rotary Drilling
Test pits
Depth upto 3m
Uneconomical at greater depths.
Supports are required at greater depths. Especially in
case of weak strata
Problems with GWT and the same should be lowered
Open type Exploration
Soils are investigated in natural condition
Soil samples are collected for determining strength
and Engineering properties
Excavated test pit
Boring
Drilling a hole into the soil strata upto specified
depth is known as boring
1. Auger boring
2. Core boring
3. Wash boring
4. Percussion drilling
5. Rotary drilling
Auger Boring
Drilling is made using a device called Soil Auger
Power driven (upto 3 to 5m) and Hand operated.
Advancement is made by drilling the auger by simultaneous
rotating and pressing it into the soil
Dry and unsupported bore holes
When the auger gets filled with soil same, it is taken out and
the soil sample collected.
It is particularly useful for subsurface investigations of
highway, railway and airfield where the depth of
exploration is small.
Auger boring can not be used when there are large boulder
present in the soil profile.
Soil augers
Core Boring
Core boring is method is used for drilling holes and
obtaining rock cores.
As the drilling is rotated , the bit cut an annular hole around
an intact core.
The core is then removed from its bottom and is retained by
a core lifter and brought to the ground surface.
Water is pumped continuously in to the drilling rod to keep
the drilling bit cool and to carry the disintegrated material to
the ground surface.
The core drilling ma be done using either a diamond
studded bit or a cutting edge. The diamond drilling is
superior to the other type o drilling , but it costlier.
RQD
Wash Boring
Initially, the hole is advanced for a short depth by using an
auger.
Then a casing pipe is pushed in and driven with a drop
weight. The driving may be with the aid of power.
Water jet under pressure is forced through the rod and the bit
into the hole.
This loosens the soil at the lower end and forces the soil-water
suspension upwards along the annular surface between the rod
and the side of the hole.
This suspension is collected in a settling tank.
Soil particles are allowed to settle down and water is allowed
to overflow into a sump which is then recalculated
Very disturbed sample is obtained.
whenever a soil sample is required, the chopping bit is to be
replaced by a sampler.
The change of the rate of progress and change of colour of
wash water indicate changes in soil strata.
Wash boring
Percussion Drilling
This method is used for making holes in rocks, boulders
and other hard strata.
In this method heavy chisel is lifted & dropped.
Sample will be collected with the help of bailer at
regular interval.
This drilling may required casing.
This is particularly used in drilling holes in boulder.
Disadvantages
The formation gets badly disturbed by impact at the
bottom.
i
Rotary Drilling
A drill bit, fixed to the lower end of a drill rod, is rotated by
power while being kept in firm contact with the hole.
Drilling rod is rotated , the cutting bit shears off chips of the
material penetrated.
Drilling fluid or bentonite slurry is used under pressure
which brings up the cuttings to the surface.
Drilling fluid also cool down the drilling bit, in case of an
uncased hole drilling fluid also support the walls of the
hole.
When soil sample is required to be taken the drilling rod is
raised and the drilling bit is replaced by a sampler.
SOIL SAMPLING
Two types of soil samples can be obtained during sampling
disturbed and undisturbed.
The most important engineering properties required for
foundation design are strength, compressibility, and
permeability. Reasonably good estimates of these properties
for cohesive soils can be made by laboratory tests on
undisturbed samples which can be obtained with moderate
difficulty.
It is nearly impossible to obtain a truly undisturbed sample
of soil; so in general usage the term "undisturbed" means a
sample where some precautions have been taken to
minimize disturbance or remolding effects. In this context,
the quality of an "undisturbed" sample varies widely
between soil laboratories.
STANDARD PENETRATION TESTING
OVERBURDEN PRESSURE
CORRECTION
In granular soils, overburden pressure affects the
penetration resistance
If two soils, having same relative density but
different confining pressures are tested, the one
with a higher confining pressure gives a higher
penetration number as the confining pressure in
cohesion less soils increases with the depth, the
penetration number for soils at shallow depths is
underestimated and that at greater depths is
overestimated.