Example 2
A $10 000 PC sum was allowed in the contract. Actual cost was
$11 500. Charge the client the extra $1 500 plus your margin
of say 10-%, a total of $1 650.
Example 3
$35/m2 for a 100 m2 tiled floor was allowed in the contract. If
the tiles the client chose cost $30/m2, the client gets a refund
of $5/m2 x 100 m2 = $500.
More Terminology
Estimate:
Machine hire: 20 hrs @ $60/hr = $1 200
Labour: 1 person 20 hrs @ $25/hr = $500
Truck hire: 15 hrs @ $50/hr = $750
Dumping fees: 85 ton @ $8/ton = $680
Total = $3 130
Terminology
86 100
120
150
500
300 150
TRENCHING incl edge form
Description Unit Qty Rate $
Setting out: 1 person day hr 4 30 120
Backhoe 1 day hr 8 55 440
Clear site to 150 mm m2 25 25 625
Labour: 2 persons 1 day hr 16 30 480
Spoil removal 6.8 m3 ton 11 11 121
Total to summary $1 786
CONCRETE placement and finishing
Description Unit Qty Rate $
Labour 2 persons 1 day hr 16 30 480
Concrete pump* No. 1 350 350
Vibrator (own) No. 1 - -
Miscellaneous 100
Total to summary $930
Due to limited site access
For small areas round off to 50/m2 and add a %-age for waste
Tendering process