ITEM
1. Description
2. Preparation
3. The main factor contacting with
the displacing ratio
4. Rule and method
5. Procedure
1 Description
Basic rule
Keep the annular pressure balance while
pumping and WOC
Displace all the mud away the cementing
section
The lost circulation or oil/gas/water
channeling into the annular will not
happen
1 Description
Main contents
Well conditions : analyzing the
temperature/ pressure / open hole
condition/mud properties
Selecting the cementing type and method
Slurry design: weight/ volume /properties
Ahead water and behind water design
1 Description
Main contents
Selecting the cementing equipment
and tools/casing accessories
Displacing technology design:
Displacing speed/operation program
Preparation before cementing:
cleaning the open hole/adjusting the
mud properties
Cementing result evaluation
1 Description
Design procedure :
Selecting and analyzing the basic data used
for the design
Deciding the cementing method
Calculating the volume of slurry/ahead
water/behind water/displacing mud
Planning the position of the casing accessories
Making the operation procedures and the plan
1 Description
Design procedure :
Simulating and evaluation the cementing
operation, comparing the design results
Adjusting the design data on the base of the
simulating and evaluation
Carry out the design cementing procedures
Analyzing and evaluating the operation
results
2 Preparation
Return speed
Re
(m/s)
normal
mud + ahead waterpre-flush/spacer/pre-flush
Tow stage
mud + ahead waterpre-flush/spacer+ slurrytail
4 The rule and the method of cementing design
Volume calculation
Volume of slurry
Volume of cement
Volume of mixing water
Volume of additives
Volume of ahead water(pre-flush/spacer)
Volume of displacing fluid
4 The rule and the method of cementing design
q=10Qc60/1000
qvolume of pre-flush m3
Qcdisplacing capacity L/s
4 The rule and the method of cementing design
Following resistance
Static pressure in the annular and casing
Pressure at well head
Pressure at casing shoe
Turbulent follow contacting time
5Cementing design procedure
(1) Selecting and analysis the basic data for the design
(2) Making the first cementing plan
selecting cementing method
design the displacing form
calculating the volume of ahead water
design the slurry column in the annular
design the type of slurry and the properties for
the well condition
5Cementing design procedure