Quality Planning
(Aerospace APQP)
Introduction
October 2013
1
Purpose
www.iaqg.org/scmh
APQP Introduction
Page 3
Document structure
Page 4
What is APQP?
Page 7
Aerospace APQP Model
Customer Satisfaction
On-Time, On-Quality, Shorter lead times
Cross Functional
Effective Project
Commitment &
Organizational
Management
Planning
Support
Team
APQP PRINCIPLES
Page 8
Aerospace APQP main pillars
Page 9
Aerospace APQP main pillars
Page 10
Aerospace APQP main pillars
Page 11
Aerospace APQP main pillars
Deliverables
Deliverable Deliverable Deliverable Deliverable
Owner Owner Owner Owner
1 - Planning 5 - Production
Customer 4 - Product Process
2 - Product Design & Development
APQP Validation
1 - Planning 5 - Production
timeline
xx Q
Representative
Deliverables
Deliverable Deliverable Deliverable Deliverable
Owner Owner Owner Owner
Page 12
Aerospace APQP model
5 PHASES
Aerospace APQP
Program Phases
Needs
Phases ELEMENTS
DEFINING
Elements Elements ACTIVITIES
Deliverables
Page 13
Aerospace APQP model
Page 14
Aerospace APQP model aligns
with PDP
Alignment with Product Development Process (PDP)
Product Development
Process
APQP phases
1 - Planning D 5 - Production
A
E
4 - Product Process
2 - Product Design & Development B
Validation
APQP milestones
Page 15
Aerospace APQP model
Product Development
Process
4 - Product Process
2 - Product Design & Development
Validation
4 - Product Process
2 - Product Design & Development
Validation
4 - Product Process
Validation
Page 17
Aerospace APQP principles
Page 18
Aerospace APQP principles
Phase 1 Planning
Identifies and gathers all the inputs applicable to the product
Collects the technical and non-technical requirements applicable to the
project/product
Defines the product and project goals
Ensures that the organization has decided what will be made in house
and what will be purchased/sub-contract
Provides an agreed timing for deliverables attached to each Aerospace
APQP elements
Output
The product concept is frozen (milestone A) and a pre-design is
available
Concurrent product design and process design can start
Page 19
Aerospace APQP principles
Output
Specified prototype testing (e.g. simulation & functional testing) have
been completed
The product design is verified and validated (milestone B) by the design
organization
Page 20
Aerospace APQP principles
Output
The process is defined, established, verified (production readiness
review - milestone C) and ready for validation.
Page 21
Aerospace APQP principles
Page 22
Aerospace APQP principles
Page 23
Aerospace APQP principles
Phase 5 - Production
Records Lessons Learned for continuous improvement
Ensures robust product realization processes are in place
Implements actions to reduce product and process variation in order
to achieve quality goals
Supports on-going Maintenance Repair and Overhaul (MRO)
operations
Performs capacity monitoring
Outputs
Project goals are achieved, including reliability, quality, and customer
satisfaction
On-time, on-quality, on-cost production and service
Page 24
Aerospace APQP principles
Elements
Describes key activities accomplished during each
Aerospace APQP phase
Assure the health of the project through monitoring on-
time,on-quality key deliverables
Encourages a standardized approach
Applicability evaluated for each project
Phases
Elements
Deliverables
Page 25
Aerospace APQP principles
Deliverables
Specific outputs defined for each element
Tangible outcomes of the cross functional team activities
Provides the base for assessing the on-quality of the
Aerospace APQP elements
Provides standardized content wherever possible (e.g.
FMEA, Control plan etc.)
Page 26
Aerospace APQP principles
Checklist
Standardized tool to evaluate on-quality of deliverables and
elements
Short set of simple, clear questions which will deliver closed
answers (Y/N)
Provides document references as evidence and records
deviations
Collects corrective actions to recover deviations
Establishes the first level of Red/Yellow/Green rating
The floor plan layout should be developed to clearly show the position and layout for all processes to be covered by the control plan.
The plan should identify each process which affects the quality characteristics of the part.
Synchronous material flow and floor usage optimisation should be taken into account when performing the lay out in an effort to
Description: economise space usage increasing the value added of floor space and minimising the travel and handling of materials, parts and
assemblies following lean principles. Value Stream Mapping (VSM) and Spaghetti diagram techniques can be used in support of this.
Deliverable is a plant layout plan approved by the Production manager and the Quality Manager.
Deliverables:
* In the Y column use IP (In progress) when the CTQ is progressing as planned Note: If planned review is delaid by more than two weeks item to be highlighted
but still has not reached completion as RED and escalated.
Open Due Status Actual End
#
1
Question
Was the Floor plan layout created by a cross
functional team including Process Engineering,
Production Manager, Quality, Facilities Management,
Maintenace and Health, Safety & Environment
Representatives?
Y* N N/A RAG Evidences Actions Required Responsible Date Date % Date
Phases
Have all the necessary inputs, in the development of
the plant lay out, been taken into account and they
are frozen at the right stage (e.g., Build Process
2 Definition , Value Stream Mapping Analysis, Inbound /
Outbound Logistics Flow, H&S and environmental
rules, Plant Lay Out Blue Print and plan, existing
Elements
facility utilities )?
Deliverables
Is the floor plan layout up-to-date and managed in
9 configuration? Is it consistent with the latest process
flow chart?
Have all potential risks affecting the CTQ been
10 identified?
11
12
13
14
15
Page 27 X
25%
N/A CTQ RAG Rating
Red: Some questions have a negative answer and no recovery plan is in place or the plans
Location: / Site:
R identified will have an impact in program timing. Support is required. When an item is
highlighted Red an assessment on the impact to the WP timing needs to be provided. Rewiewed by:
Status (%): 25% - Action Identified 50% - Owner Identified A Amber: Some questions have a negative answer but a recovery plan is in place which will Reviewed with:
75% - Action in Progress 100% - Action Closed G prevent impact
Green: All on timing
questions have a positive answer (Y) and are ongoing normal program Date :
development
Aerospace APQP key milestones
Elements
Process Validation
PPAP
Page 28
Summary
Advance Product Quality Planning (APQP) is taking
hold in the Aerospace Industry
APQP ensures the delivery of product on-time, on-
quality, on cost
PPAP validates the production process Aerospace APQP
PPAP
Page 29