Anda di halaman 1dari 72

PMP Examination Preparation Course

Topic: Project Time Management


Version 4.0
Project Time Management

Hot Topics

Float/Slack/Lag/Lead
Dependencies

Monte Carlo Simulation Precedence diagramming method/AON


Analogous estimating
Duration compression
Resource Leveling
Critical Path
Variance Analysis
Fast Track / Crash

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 1
Project Time Management (Contd.)

Processes required to deliver project on schedule


Define Activities Identifying specific actions to be performed to produce
project deliverables
Sequence Activities Identifying and documenting relationship among
project activities.
Estimate Activity Resource Estimating type and quantities of material,
people, equipment or supplies required.
Estimate Activity Duration Number of work periods required to complete
individual activities with estimated resources.
Develop Schedule Analyzing activity sequences, durations, resource
requirements and schedule constraints to create project schedule.
Control Schedule Monitoring the status of project to update project
progress and managing changes to schedule baseline.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 2
Project Time Management (Contd.)

Initiating Executing Monitoring & Closing


Planning Process
Process Process Controlling Process
Group
Group Group Process Group Group
Define Activities Control Schedule
Sequence
Activities
Estimate Activity
Resources
Estimate Activity
Durations
Develop
Schedule

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 3
Define Activities

Identify the specific schedule activities that need be performed to


produce various project deliverables
Involves:
Documenting the specific action or work to be performed
Identify deliverables at the lowest level i.e. Work Packages
Work packages are further decomposed into schedule activities

Defining and planning the schedule activities such that the project
objectives are met

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 4
Define Activities

Inputs Tools and Techniques Outputs


Scope Baseline Decomposition Activity Lists
Enterprise Rolling wave planning Activity attributes
environmental factors Templates Milestone list
Organizational Expert judgment
process assets

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 5
Inputs Define Activities

1.Scope Baseline
Project deliverables, constraints and assumptions documented in project scope
baseline are considered explicitly while defining activities
2. Enterprise environmental factors
Availability of project management information systems and scheduling
software tools
3. Organizational process assets
Formal / informal policies, procedures and guidelines for activity definitions
Lessons learned / Historical information on activity lists from previous similar
projects

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 6
Tools & Techniques Define Activities (Contd.)

1. Decomposition
Subdividing project work packages into smaller, manageable components
called activities
Define Activities process defines final outputs as activities rather than
deliverable
WBS and WBS dictionary are basis of development of activity list (they can be
developed in parallel as well)
Involving team members in decomposition can lead to more accurate results.

Each work package in the WBS is decomposed into the schedule


activities required to produce the work package deliverables

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 7
Tools & Techniques Define Activities (Contd.)

2. Rolling wave planning


Form of progressive elaboration planning . As scope is evolved, WBS and WBS
dictionary items are more detailed
Work to be accomplished in near term is detailed at low level of WBS while
work to be accomplished in future is at a higher level of WBS
During early strategic planning, activities can be defined at milestone level,
when less information is less defined, later it can be decomposed into activities
3.Templates
Standard activity list or portion of activity list from a previous project
Can contain resource skills, required hours of effort, identification of risks,
expected deliverables, can be used to identify typical milestones
4. Expert judgment
Consulting experts

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 8
Outputs Define Activities

1.Activity lists
Its a comprehensive list including all schedule activities required on the
project
Activities are discrete components of project schedule, but NOT a part of
WBS
Verified against WBS for completeness
Only contains the activities required as a part of project scope
Includes descriptions (activity identifier, scope of work) of activities for the
team to understand
Are used in the schedule model and is part of the project management plan

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 9
Outputs Define Activities (Contd.)
2. Activity Attributes
Extend the description of activity by identifying attributes associated with each
activity.
Attributes Activity identifier, Activity codes, Activity description, Predecessor
activities, Successor activities, Logical relationships, Leads and Lags, resource
requirements, imposed dates, constraints and assumptions, person responsible
for executing the work, geographic area where the work will be performed,
Schedule activity type level of effort, discrete effort and apportioned effort
Used for schedule development, for selecting, ordering & sorting planned
activities within report.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 10
Outputs Define Activities (Contd.)
3. Milestone lists
Milestone is a significant point or event in project
It identifies all the milestones
Indicates whether the milestone is mandatory (required by contract) or optional
(based on project requirements or historical information)

Milestones Have no duration, indicate start or completion


of an activity

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 11
Question?

Which of the following is an activity attribute:


Activity code
Lead and lag
Constraints and assumptions
Person responsible

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 12
Sequence Activities

Identifying and documenting the logical relationships among the


schedule activities

Sequencing can be performed by using project management software


or by using manual or automatic technique.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 13
Sequence Activities (Contd.)

Inputs Tools and Techniques Outputs


Activity list Precedence Project schedule
Activity attributes diagramming method network diagrams
(PDM) Project document
Milestones List
Dependency updates
Project scope determination
statement
Applying leads and
Organizational lags
Process Asset
Schedule Network
templates

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 14
Inputs Sequence Activities

1. Activity lists (described earlier)


2. Activity attributes (described earlier)
3. Milestone lists (described earlier)
4. Project Scope statement
Product characteristics described in scope description may impact activity
sequencing. These are often apparent in activity lists
This is reviewed to ensure accuracy
5.Organizational Process Assets
Organizational Process Asset can influence the sequence activities process.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 15
Tools & Techniques Sequence Activities (Contd.)

1.Precedence diagramming method (PDM)


A method of critical path methodology for constructing a project schedule
network diagram
This technique is also called Activity-On-Node (AON).

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 16
Tools & Techniques PDM

Precedence Diagramming method (PDM)


FS/SS/FF/SF
Commonly used
A B Relationship C

No Dummies

START
Activity FINISH

D E F

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 17
Tools & Techniques Dependency /logical Relationship

PDM includes four types of logical relationships

A B FINISH TO START

A B START TO START

A B
FINISH TO FINISH

A B START TO FINISH

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 18
Tools & Techniques Sequence Activities (Contd.)

2. Dependency determination
Three types of dependencies are used to define the sequence among the
activities.
Mandatory
Discretionary
External

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 19
Tools & Techniques Dependency determination

Task Dependencies

TYPE DESCRIPTION EXAMPLE(S) !REMEMBER!


Mandatory Logical dependencies due to The code must be completed Also called as HARDLOGIC
nature of work before it can be reviewed
Often involve physical Foundation must be complete
limitations before building floor

Discretionary Dependencies defined by the An additional level of review Also called as SOFT
project management team before delivery to the client LOGIC, PREFERRED
LOGIC
Should be used with care
Should be fully documented

External Dependencies on events Software licenses must A dependency can be both


outside the project be supplied by Client external and mandatory
before development

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 20
Tools & Techniques Sequence Activities

3. Applying Leads and Lags


Lag is the amount of wait time before the successor activity can be started
Lead allows the acceleration of the successor activity
4. Schedule Network templates
Portions of project schedule network diagram are referred as sub-network or
fragment network
Useful as templates when project includes several identical deliverables e.g.,
floors on high rise buildings

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 21
Outputs Sequence Activities

1. Project schedule network diagram


Schematic display of projects schedule
Includes either full project details or one or more summary activities
2. Project document updates
Project documents that may be updated include, but not limited to:
Activity list
Activity attributes
Risk Register

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 22
Question?

Identify the type of dependency:


Building plan to be cleared by the local municipal department before
construction can start
Testing to be done before product can be put into the market
Marketing and legal department to clear RFP prior to submission

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 23
Estimate Activity Resources

Estimating the type and quantities of resources required to perform


each schedule activity
Estimate Activity Resource process is closely coordinated with Estimate
Cost process.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 24
Estimate Activity Resources (Contd.)

Inputs Tools and Techniques Outputs


Expert judgment Activity resource
Activity lists Alternative analyses requirements

Activity attributes Published estimating Resource


data breakdown structure
Resource Calendars
Bottom-up estimating Project Document
Enterprise updates
environmental Project management
factors software
Organizational
process assets

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 25
Inputs Estimate Activity Resources

1.Activity list
Activity List identifies the activities which will need resources.
2. Activity attributes
Developed during the define activities and sequence activities processes
3. Resource Calendar
Provides information on which resources are potentially available during
planned activity period and is used for estimating resource utilization
Specify when and how long identified project resource will be available
during project.
Includes availability, capabilities, and skills of human resources.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 26
Inputs Estimate Activity Resources

4.Enterprise environmental factors


Can influence the Estimate Activity Resources process
5. Organizational process assets
Policies regarding staffing, purchase and rental of supplies and equipments
Available historical information regarding what type of resources were required
for similar projects in past

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 27
Tools & Techniques Estimate Activity Resources

1.Expert judgment
People or group with specialized knowledge in resource planning and
estimating
2. Alternatives analysis
Alternative methods for accomplishing schedule activities
Various levels of resource capabilities or skills
Different size or type of machines
Hand operated tools versus automated tools
Make or buy decisions regarding resource (equipment, supplies)
3. Published Estimating data
Published updated production rate and unit costs of resources for an extensive
array of labor trades, material, and equipment for different countries and
geographical locations within a country

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 28
Tools & Techniques Estimate Activity Resources (Contd.)

4. Bottom-up Estimating
If project team does not have adequate confidence in the estimates at the
schedule activity level, it needs to be further decomposed
Resource needs at these decomposed levels are estimated and quantities are
rolled up to the scheduled activities resources
Dependencies between these activities may impact application and use of
resources and such pattern of resource usage is documented
5. Project Management Software
Helps planning, organizing, managing resource pools and develop resource
estimates
Sophisticated tools have capabilities to define resource breakdown structures,
resource availabilities, resource rates and resource calendars

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 29
Outputs Estimate Activity Resources

1. Activity resource requirements


Description of type and quantities of resources required for each schedule
activity in work package
Aggregated to determine resource estimates for each work package
Supporting documentation basis of estimate for each resource, assumptions
made while determining type, availability and quantity of resources
2. Resource breakdown structure
Hierarchical structure of identified resources by resource category and type
3. Project Documents updates
Project documents that may be updated include, Activity list, Activity attributes
and Resource calendars.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 30
Question?

Which of the following is not a tool and technique for


activity resource estimating?
Published estimating data
Bottom-up estimating
Alternative analysis
Parametric estimating

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 31
Estimate Activity Durations

Estimate activity durations is the process of approximating the number of work


periods needed to complete individual activities with estimated resources.
Uses information on activity scope of work, required resource types, estimated
resource quantities and resource calendars.

Estimating the number of work periods required to complete each


schedule activity

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 32
Estimate Activity Durations (Contd.)

Inputs Tools and Techniques Outputs


Activity list Expert Judgment Activity duration
Activity attributes Analogous estimating estimates

Activity Resource Parametric estimating Project Document


Requirements updates
Three-point estimate
Resource calendars Reserve analysis
Project scope statement
Enterprise environmental
factors
Organizational process
assets

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 33
Inputs Estimate Activity Durations
1. Activity list (described earlier)
2. Activity attributes (described earlier)
3. Activity Resource requirements
Duration of activities will depend on the resources available to work on
activities
Availability of skilled resources will significantly influence the duration of most
activities.
Project experience communication overload as more resources are added
thus reducing productivity
Output improves proportionally less than the increase in resources

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 34
Inputs Estimate Activity Durations (Contd.)

4. Resource calendars
Developed as part of Estimate activity resource process.
Type of resource assigned, quantity, availability, capability of both equipment &
material resources could significantly influence the activity duration
For example senior staff members are expected to complete the activity in
lesser time as compared to junior staff members
5. Project scope statement
Constraints and assumptions are considered when estimating activity
durations.
Example of constraints are available skilled resources, contract terms and
requirements.
Example of assumptions are existing conditions, availability of information and
length of reporting periods.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 35
Inputs Estimate Activity Durations (Contd.)

6. Enterprise environmental factors


Duration estimating databases and other reference data.
Published commercial information
Productivity metrics
7. Organizational process assets
Historical duration information
Project calendars
Scheduling methodology
Lessons learned.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 36
Tools & Techniques Estimate Activity Durations

1. Expert judgment
Should be used along with historical information
Can also be used to determine whether to combine methods of estimating and how to
reconcile differences between them
2. Analogous estimate
Also called as Top-Down estimates
Form of expert judgment
Uses performance results of similar past activities
Used when there is only limited amount of detailed information about project.
3. Parametric estimating
Uses a statistical relationship between historical data and other variable to calculate an
estimate for activity parameter such as cost, budget & duration.
Can produce higher levels of accuracy depending upon sophistication and underlying
data built into the model.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 37
Tools & Techniques Estimate Activity Durations (Contd.)

4. Three point estimate


Most likely Duration of the schedule activity, given the resources likely to be assigned,
their productivity, realistic expectations of availability for the schedule activity,
dependencies on other participants, and interruptions
Optimistic Duration is based on a best-case scenario of what is described in the most
likely estimate
Pessimistic Duration is based on a worst-case scenario of what is described in the most
likely estimate
Activity duration estimates can be constructed by taking an average of 3 estimated
durations which will often provide more accurate estimates than a single point estimate
5. Reserve Analysis
Incorporating additional time referred to as contingency, time reserves, buffers
Can be percentage of estimated activity duration, fixed number of work periods, or
developed by quantitative risk analysis
Can be used completely or partially, can be reduced or totally eliminated later on

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 38
Outputs Estimate Activity Durations

1. Activity duration estimates


Quantitative assessments of likely number of work periods that will be required
to complete a schedule activity
Generally expressed as a range 2 months +/- 5 days or 90% probability of
finishing in 2 weeks
2. Project Document updates
Project Document updated may include
Activity attributes, and assumption made in developing the activity duration
estimate such as skill levels and availability.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 39
Question?

Identify the kind of estimation technique used in each of the


following:
(27000 use case points) / (27 use case points/ hr) = 1000 hrs
Aggressive = 10 days; Pessimistic = 20 days; Most likely = 16 days
Similar functionality in an earlier project took 15 person days to
complete

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 40
Develop Schedule

Develop schedule is the process of analyzing activity sequences,


duration, resource requirements and schedule constraints to create the
project schedule.
Developing an acceptable project schedule is often an iterative
process.

Serves as a baseline against which project progress can be


tracked

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 41
Develop Schedule(Contd.)
Inputs Tools and Techniques Outputs
Activity lists Schedule network analysis Project schedule
Activity attributes Critical path method Schedule baseline
Project schedule Network Critical chain method Schedule Data
diagrams Resource leveling Project Document
Activity Resource What-if scenario analysis Updates
requirements
Adjusting leads and lags
Resource Calendars
Schedule compression
Activity duration estimates
Scheduling tool
Project scope statement
Enterprise environmental
factors
Organizational process
assets

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 42
Inputs Develop Schedule (Contd.)

1. Activity list (described earlier)


2. Activity attributes (described earlier)
3. Project schedule network diagrams (described earlier)
4. Activity Resource requirements (described earlier)
5. Resource calendars (described earlier)
6. Activity duration estimates (described earlier)

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 43
Inputs Develop Schedule (Contd.)

7. Project scope statement


Assumptions and constraints Imposed dates, market window on
technology project
Commonly used constraints in PM software Start No Earlier Than and
Finish NO Later Than
Major milestones dictated by Project sponsor, customer
8. Organizational process assets
Scheduling methodology
Project calendars
9. Enterprise environmental factors
Can influence the develop schedule process include a scheduling tool that can be
used in developing the schedule

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 44
Tools & Techniques Develop Schedule

1. Schedule network analysis


Used to calculate early and late start and finish dates
Network loops and open ends are adjusted before applying any techniques
Analytical techniques critical path method, critical chain method, what-if analysis, and
resource leveling
Points of path convergence and path divergence can be identified and used in schedule
compression analysis
2. Critical path method
Calculates theoretical early start and finish dates and late start and finish dates by
performing forward pass and backward pass analysis
It is called as theoretical as resource limitations are not considered
Measure of flexibility in a schedule is FLOAT If difference between early and late dates
is positive, schedule is flexible. Critical path has ZERO or NEGATIVE float and activities
on critical path are termed as critical activities
(More details are provided later on)

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 45
Tools & Techniques Develop Schedule (Contd.)

3. CRITICAL CHAIN Method (scheduling & managing uncertainty by):


Schedule network analysis technique that modifies project schedule to account for limited
resources.
Resource-constrained critical path is known as critical chain.
Adds duration buffers that are non-work schedule activities to manage uncertainty.
One buffer is known as project buffer. Additional buffers are known as feeding buffers.
Size of buffer should account for uncertainty in the duration of chain of dependant tasks.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 46
Tools & Techniques Develop Schedule (Contd.)
4. Resource leveling
Often cause original critical path to change and is necessary when resources are over
allocated.
Allocate scarce resources to the critical activities first It lets the cost and schedule slip in
favor of having stable number of resources per month
Sacrificing schedule for having resource stability is called as resource-based scheduling
Scheduling of finite or critical resource from project ending date is known as reverse
allocation scheduling

Levelled Resources
Uneven Resource loading
250 225 200
200 157 157 157 157 157 157
200 180 150
160
150
100 100
100 80
50
50
0 0
Jan Feb Mar April May June Jan Feb Mar Apr May June
Hours Hours

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 47
Tools & Techniques Develop Schedule(Contd.)

5. What-if Scenario analysis


Consideration of different scenarios of event occurrence and their impact on the project
schedule. These events could be external to the project or integral part of project
Examples What will happen if there is a change in process? What will happen if a
specific component gets delayed
Out come of scenario analyses helps to assess the feasibility of schedule under adverse
conditions and in preparing contingency/response plan to mitigate the impact of
unexpected situations
Most common technique is Monte Carlo analysis used to calculate a distribution of
possible outcome for the total project.
6. Leads and lags
Adjustments to leads and lags to come up with a viable project schedule.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 48
Tools & Techniques Develop Schedule (Contd.)

7.Schedule compression
Shortening of schedule without changing the project scope, to meet the schedule
constraints, imposed dates, or other schedule objectives
Crashing
Maintain scope and add more resources to the critical path activities
Almost always associated with increase in cost
Not all activities can be executed faster by adding resources
Fast tracking
Performing critical path activities in parallel
Increases the probability of rework
Increases risks
8. Scheduling tool
Can be used in conjunction with other project management Software application as well
as manual methods.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 49
Outputs Develop Schedule

Project schedule
Contains milestone schedule, summary schedule and detailed schedule with
logical relationships.
Remains preliminary until resource assignments are confirmed
This process is completed on or before the completion of project management
plan
Can be at summary level master schedule or at a detailed level
Can be presented in tabular or graphical format
Project schedule network diagram
Bar charts or
Milestone charts

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 50
Develop Schedule(Contd.)

Definitions of key terms


Free Slack/Free float/Slack/Float : The amount of time the activity can be
delayed without affecting the start of successor activity
Total Slack/Total Float : The amount of time the activity can be delayed
without affecting the project completion date
Project Slack/Project Float : The amount of time the project can be delayed
without delaying the externally imposed completion date imposed by the
customer or Sr. Management
Critical path is the longest sequence of activities on the network diagram and is
characterized by zero float or slack for activities. There is no slack along the
critical path
Any delay in critical path delays the project
Sometime multiple critical paths can exist
In practice, apart from the critical activities, activities that have small amount of
float are also closely monitored
PMP Workshop | Financial Services
All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 51
Develop Schedule(Contd.)

Scheduling Techniques / Mathematical Analysis


Calculate Theoretical early/late start and finish dates
These dates are subject to change after resource leveling and duration
compression

Critical Path Method (CPM)


Deterministic method
Single estimate (most likely)
Focus on float to identify the least flexible activities
Does not allow for looping in network and shows only one path

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 52
Develop Schedule

Building Network Diagrams STEP1: Create Activity List

Activity Description Duration Predecessor ES EF LS LF Float

1 A 15 -

2 B 5 1

3 C 4 2

4 D 4 2

5 E 3 4 STEP3: Determine predecessor

6 F 15 2

7 G 30 6

8 H 4 7

9 I 10 5
STEP2: Assign duration
10 J 20 9,8

11 K 5 3,10

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 53
Develop Schedule(Contd.)

STEP4: Forward Pass Calculate Early


schedule activities
Scheduling Conventions
1st Activity is always scheduled to Early Start Duration Early Finish

start on project start date Task Name

Each activity starts at the beginning of


Late Start Slack/Float Late Finish
the start period and finishes at the
end of the finish period
A one day activity starting on Jan
1st has end date of Jan 1st
Early Finish date (EF) = Early start
date (ES) + duration - 1
The successor activity starts in the
next available time period. If an
activity finishes on Day 3, successor
activity will start on Day 4

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 54
Develop Schedule(Contd.)

Mon 6/12 15 Fri 6/30

Mon 6/12 0 Fri 6/30

Mon 7/10 4 Thu 7/13 Fri 10/13 5 Thu 10/19

C J

Mon 10/9 65 Thu 10/12 Fri 10/13 0 Thu 10/19

Fri 7/14 3 Tue 7/18


Mon 7/3 5 Fri 7/7 Mon 7/10 4 Thu 7/13 Wed 7/19 10 Tue 8/1 Fri 9/15 20 Thu 10/12

B D E I J

Mon 7/3 0 Fri 7/7 Mon 8/23 32 Mon 8/28 Mon 8/29 32 Mon 8/31 Fri 9/1 32 Thu 9/14 Fri 9/15 0 Thu 10/12

Mon 7/10 15 Fri 7/28 Mon 7/31 30 Fri 9/8 Mon 9/11 4 Thu 9/14

F G H

Mon 7/10 0 Fri 7/28 Mon 7/31 0 Fri 9/8 Mon 9/11 0 Thu 9/14

STEP7: Determine Critical Path

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 55
Outputs Develop Schedule (Contd.)
Methods of presenting Project Schedule
Milestone Chart Gantt (Bar) Chart Schedule Network Diagram
Shows start/finish dates of Bar chart that shows activity Shows interdependencies
major deliverables and key start and finish dates with of all tasks and activity
external dependencies expected duration dates information
Similar to bar chart but can Generally do not depict Shows workflows and can
also be represented in a interdependencies identify the critical path
tabular form Weak planning tool Can aid in effective
Good for management and Effective for progress planning, organizing and
customer reporting reporting and control control of project

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 56
Outputs Develop Schedule(Contd.)

2. Schedule baseline
Specific version of the project version developed from the schedule network
analysis of the schedule model
Approved and accepted by project management team as schedule baseline
Contains baseline start and finish dates
3. Schedule data
Supporting data schedule milestones, schedule activities, activity attributes,
assumptions and constraints
Resource requirements by time periods resource histograms
Alternative schedules best case, worst case schedules etc
Scheduling of contingency reserves

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 57
Outputs Develop Schedule (Contd.)

4. Project Documents updates


Include but not limited to
Activity Resource Requirements
Activity Attributes
Calendar
Risk Register

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 58
Question?

A critical project is running behind schedule and the resources are


being overworked everyday. What option should the project manager
choose:
Fast tracking
Crashing
None of these

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 59
Control Schedule

Control Schedule is concerned with


Determining current project status
Influencing factors that cause schedule changes
Determining that project schedule has changed
Managing the actual changes as they occur

This is the process necessary for controlling changes to the


project schedule

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 60
Control Schedule(Contd.)
Inputs Tools and Techniques Outputs
Project Management Plan Performance Reviews Work Performance
Variance analysis measurements
Project Schedule
Project Management Organizational process
Work Performance assets (updates)
Information software
Change Request
Organizational process Resource leveling
assets Project management plan
What-if scenario analysis
(updates)
Adjusting leads and lags Project Document
Schedule compression (updates)
Scheduling tool

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 61
Inputs Control Schedule

1. Project Management Plan


Contains schedule management plan and schedule baseline, which is used to
compare with actual results to determine if change, corrective action or preventive
action is necessary.

2. Project Schedule
Most recent version of the project schedule with notations to indicate updates,
completed activities and started activities as of the indicated data date.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 62
Inputs Control Schedule (Contd.)

3. Work Performance Information


Information about the project progress such as which activities have started their
progress and which activities have finished

4 Organizational process assets


Existing formal informal schedule control related policies, procedures and guidelines;
Schedule control tools; and
Monitoring and reporting method to be used

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 63
Tools & Techniques Control Schedule

1. Performance Reviews
Measure, compare and analyze schedule performances such as actual start
and finish date, percent complete and remaining duration of work in progress
An important part of Schedule Control is to decide if the schedule variation
requires corrective action.
2. Variance analysis
Schedule performance measurements (SV,SPI) are used to asses magnitude
of variation to the original schedule baseline.
Identifying which variance would call for corrective actions
Mainly focused on critical activities / sub-critical activities (less float)
3. Project Management Software
Ability to track planned versus actual, ability to forecast effects of schedule
changes
4. Resource leveling
PMP Workshop | Financial Services
All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 64
Tools & Techniques Control Schedule(Contd.)

5. What-if scenario analysis


6. Project Management Software
Ability to track planned versus actual, ability to forecast effects of schedule
changes
7. Adjusting leads and lags
8. Schedule compression
9. Scheduling tool
Scheduling tool and supporting data are used in conjunction with manual
methods or other PM SW to perform schedule network analyses to generate an
updated project schedule.

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 65
Outputs Control Schedule (Contd.)

1. Work Performance measurements


Schedule variance (SV) and Schedule performance index (SPI) at work
package and control account level are communicated to stakeholders
2. Organizational Process assets (updates)
Feeding the organizational database with lessons learned causes of schedule
variance and reasoning behind corrective actions taken. Any other lessons
learned during schedule control
3. Change Requests
Requested changes to the schedule baselines
May require adjustments to other components of the project management plan
Processed for review and disposition through Perform Integrated change
control process

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 66
Outputs Control Schedule(Contd.)

4. Project Management Plan Updates


Elements of project management plan that may be updated but are not limited
to: Schedule baseline, Schedule management plan, Cost baseline.

5. Project Document Updates


Schedule Data
Project Schedule

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 67
Question?

Which of the following are tools and techniques of


schedule control?
Variance analysis
Schedule comparison bar charts
Progress reporting
Performance measurement

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 68
Recap

Float/Slack/Lag/Lead
Dependencies
Arrow diagramming method

Monte Carlo Simulation Precedence diagramming method

Analogous estimating
Duration compression
Resource Leveling
Critical Path
Variance Analysis
Fast Track / Crash
AON/ADM/GERT

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 69
Review Questions Time

Review Questions

PMP Workshop | Financial Services


All work described was performed by Capgemini or a Capgemini affiliate
2009 Capgemini - All rights reserved 70
Thank You

www.capgemini.com/financialservices

Anda mungkin juga menyukai