U.E.A.

Chungar

Revisión y Control de los Resultados Operativos

Septiembre 2017
Seguridad
Acum
Accidentes Chungar 2013 2014 2015 2016 Jul Ago Sep
2017
Fatales 1 0 1 0 0 0 0 1
Incapacitantes 16 17 19 3 1 0 0 3
Leves 20 27 23 34 2 1 1 19
A la Propiedad 15 21 30 25 1 1 0 8

Índice de Frecuencia Acumulado Índice de Severidad Acumulado


2013: 2.6
2014: 2.6 2013: 1,082
2015: 3.5 2014: 138
2016: 0.5 2015: 1,289
5,081
2016: 79
0.8 1.0 0.9 3,314
0.8 0.8 0.8 0.7 2,489 1,985
0.6 0.5 0.5 0.6 1,651 1,423 1,272 1,152
0.0 86 82 79 28

o-16 n-16 d-16 e-17 f-17 m-17 a-17 m-17 j-17 j-17 a-17 s-17 o-16 n-16 d-16 e-17 f-17 m-17 a-17 m-17 j-17 j-17 a-17 s-17

Índice de Accidentabilidad Acumulado


2013: 2.8
2014: 0.4
2015: 4.5
2016: 0.0
4.3
1.8 2.1 1.9 1.3 1.3 1.0 0.8
0.0 0.0 0.0 0.0

o-16 n-16 d-16 e-17 f-17 m-17 a-17 m-17 j-17 j-17 a-17 s-17
2 Nota:
 Un índice de Frecuencia de X significa que se. registra X accidentes por cada 1`000,000 de horas hombre trabajadas
 Un Índice de Severidad de Y significa que se pierde Y días de trabajo por cada 1`000,000 de horas hombre trabajadas
 El Índice de Accidentabilidad es igual a: Índice de Frecuencia* Índice de Severidad / 1000
Número de Personal
UNIDAD CHUNGAR Planilla Contratistas
Real Ppto Var Real Ppto Var
Número de Personas
Dic 16 Ago 17 Sep 17 Sep 17 Dic 15 Ago 17 Sep 17 Sep 17
Mina 398 377 374 401 -27 1,277 1,552 1,564 1,380 184
Planta 64 66 65 64 1 23 22 23 23 0
Energía 9 8 8 7 1 72 81 78 85 -7
Taller 107 111 115 111 4 147 166 159 180 -21
Administración 135 146 146 145 1 373 345 342 389 -47
Total 713 708 708 728 -20 1,892 2,166 2,166 2,057 109
0
Geología Regional 2 3 4 2 2 0 1 1 0 1
Proyectos 3 3 1 6 -5 400 521 496 300 196
Total General 718 714 713 736 -23 2,292 2,688 2,663 2,357 306
Personal de Otras Planillas 1 1 1 1 0 0
-25

Total -0.8% +9.1%

0 3,402 3,376 3,093


N°Personas: Contratistas
2,688 2,663 Area Ago 17 Sep 17
2,292 2,357 Total MINA 1,552 1,564
MINA Animón 1,158 1,180
MINA ISLAY 116 111
718 714 713 736 GEOLOGIA 278 273
Dic 16 Ago 17 Sep 17 Ppto Sep 17

3 * 1T-11: Considera el retiro no deseado de los 3 meses y el headcount promedio del trimestre
En retiro no deseado incluye al personal que tuvieron oferta de trabajo de otra empresa.
Formula: IR = Ret. No Deseado / HC * 100
Planilla USD
Costo de Personal Ppto
Dic 16 Ago 17 Sep 17 Var
Miles USD Sep 17
Mina 622 485 454 630 -176
Planta 109 116 116 111 5
Energía 29 31 30 24 6
Taller 197 203 210 205 5
Administración 341 378 383 365 18
Costo de Planilla 1,269 1,214 1,194 1,336 -142
Indemnizaciones - 1 4 4
Capacitación 74 25 7 6 0
Costo Mano de Obra 1,344 1,240 1,205 1,343 -137
Geología Regional 3 3 4
Proyectos 67 - -
Total General 1,413 1,243 1,209

Costo de Planilla
Miles USD -1.7% -10.6%

1,269 1,336
1,214 1,194

Dic 16 Ago 17 Sep 17 Ppto Sep 17

4
Variación de contratistas vs. mes anterior
VARIACIÓN
SITUACIÓN RAZÓN SOCIAL OBSERVACIONES
EN EL MES
PIC DEL PERU S.A.C, RUWANA CENTRO SOCIEDAD ANONIMA CERRADA -
BAJAS Otras Salidas -29
RUWANA CENTRO S.A.C., CONSEGESA S.A.
TECNOMIN DATA SOCIEDAD COMERCIAL DE
BAJAS -24 Reducción de frentes
RESPONSABILIDAD LIMITADA
BAJAS SERVICIOS MINEROS GLORIA S.A.C. -20 Término de contrato con la ECM
MIRO VIDAL Y COMPAñIA SOCIEDAD ANONIMA
BAJAS -9 Cese del personal por renuncia voluntaria
CERRADA MVC S.A.C.
SUPERMAQ SOCIEDAD ANONIMA CERRADA -
BAJAS -8 Término de contrato con la ECM
SUPERMAQ S.A.C.
EMPRESA MINERA CONSTRUCTORA ASUNTOS
BAJAS -6 Cese del personal por término de contrato
AMBIENTALES Y TRANSPORTE HUAYLLAY S.A.
ROCK DRILL CONTRATISTAS CIVILES Y MINEROS
BAJAS -5 Cese del personal por renuncia voluntaria
S.A.C.
BAJAS SECOMINC S.R.L. -5 Término parcial de contrato
BAJAS ATLAS COPCO PERUANA S A -4 Reducción de máquinas. Por paralización de Islay.
BAJAS GRUPO RIMASA SOCIEDAD ANONIMA CERRADA -4 Reducción de máquinas. Por paralización de Islay.
ALTAS CORPORACION PANASERVICE S.A.C. 4 Completa personal presupuestado
EMPRESA COMUNAL MULTISERVICIOS SAN JUAN
ALTAS 5 Completa personal presupuestado
DE HUAYLLAY
ALTAS ADM. DE PROY. MINEROS Y CIV. S.R.LTDA. 7 Incremento de frentes
TECNICOS MECANICOS CRISTOBAL EN
ALTAS 10 Incremento de frentes
CONSTRUCCION & MINERIA SOCIEDAD ANÓNIMA
ALTAS CONSORCIO GEOHIDRAULICA SAC 12 Incremento de frentes
TRANSPORTES ANGEL IBARCENA S.A.C., COMMUNICATIONS AND
ALTAS Otros Ingresos 15
SYSTEMS DEVELOPMENT S.A.C., PARAMOUNT SERVICES GROUP S.A.C.
ALTAS IESA SA 36 Nuevo proyecto. Tunel de Integración Animon - Islay y Zona Satelite.
Total -25

5
Avances y Producción
Avances y DDH - Total Chungar
Total Chungar Animón Islay Sep Plan
Avances (mts) Real Ppto Cump Real Ppto Cump Real Ppto Cump Sep
Desarrollos (laboreo) 967 712 136% - 531 0% 967 1,242 78% 1,129
Verticales - 189 0% - 125 0% - 314 0% 63
Horizontales 588 237 248% - 322 0% 588 560 105% 512
Rampas 379 286 133% - 83 0% 379 369 103% 555
Preparaciones 891 1,402 64% - 463 0% 891 1,865 48% 1,389
Exploración Local > Geología y Brownfield 6,064 1,400 433% - 4,264 0% 6,064 5,664 107% 10,850
Perforación Diamantina 6,013 1,400 430% - 4,264 0% 6,013 5,664 106% 10,850
Brownfield - - - 600 0% - 600 0% -
Potencial - - - - - - 750
Recursos 1,902 - - 203 0% 1,902 203 939% 1,910
Infill Drilling 2,434 - - 361 0% 2,434 361 674% 2,850
Infill Drilling Operativo - - - - - - -
Crecimiento 1,677 1,400 120% - 3,100 0% 1,677 4,500 37% 5,340
Labores mineras 51 - - - 51 - -
Explotación - - - - - - -

Total Chungar Animón Islay Acum a Sep Plan


Avances (mts) Real Ppto Cump Real Ppto Cump Real Ppto Cump Sep
Desarrollos (laboreo) 7,297 8,402 87% 1,916 3,857 50% 9,178 12,259 75% 9,340
Verticales 457 1,728 26% 95 1,100 9% 552 2,828 20% 615
Horizontales 4,960 1,721 288% 1,434 2,041 70% 6,359 3,763 169% 6,282
Rampas 1,880 4,953 38% 387 716 54% 2,267 5,668 40% 2,443
Preparaciones 9,430 11,030 85% 2,569 4,814 53% 11,999 15,844 76% 12,496
Exploración Local > Geología y Brownfield 39,384 54,050 73% 15,127 26,531 57% 54,511 80,581 68% 59,297
Perforación Diamantina 39,253 54,050 73% 15,067 26,531 57% 54,320 80,581 67% 59,157
Brownfield - - - 1,200 0% - 1,200 0% -
Potencial 2,217 2,400 92% - 2,400 0% 2,217 4,800 46% 2,967
Recursos 15,852 15,900 100% 6,351 6,000 106% 22,203 21,900 101% 22,211
Infill Drilling 18,364 22,050 83% 8,716 7,631 114% 27,081 29,681 91% 27,497
Infill Drilling Operativo - - - - 1,142 - -
Crecimiento 2,819 13,700 21% - 9,300 0% 2,819 23,000 12% 6,482
Labores mineras 131 - 60 - 191 - 140
Explotación - - - - - - -
7
Producción – Extracción

EXTRACCIÓN Sep 17 Acum a Sep


Jun 17 Jul 17 Ago 17 Plan Sep
Chungar Real Ppto Var Real Ppto Var
TPD 5,454 5,509 4,381 4,198 5,601 -25% 5,159 5,605 -8% 4,540
Mineral Extraído

Extrac (000 TM) 164 171 136 126 168 -25% 1,408 1,530 -8% 136
Zn (%) 4.7 5.2 6.3 5.7 4.6 23% 5.2 4.8 9% 5.8
Pb (%) 1.2 1.4 1.6 1.7 1.0 59% 1.3 1.1 18% 1.2
Cu (%) 0.1 0.2 0.2 0.2 0.1 123% 0.2 0.1 35% 0.1
Ag (Oz/T) 2.8 2.6 2.2 2.0 2.7 -25% 2.4 2.6 -11% 1.7
Por Mina (000 TM) 164 171 136 126 168 -25% 1,408 1,530 -8% 136
Mineral

Mina
por

Mina Animón 122 132 136 126 123 2% 1,147 1,119 2% 129
Mina Islay 41 39 - - 45 -100% 261 411 -36% 7
Breasting 77 84 90 82 70 18% 723 692 4% 87
Taladros Largos 19 20 7 13 38 -65% 168 327 -49% 19
Métodos

OCF - - - - 3 -100% - 10 -100% -


Subniveles 59 61 39 30 58 -48% 489 481 2% 29
Cámaras y Pilares 9 6 - - - 28 19 45% 1
Otros - - - - - - - -
Propio 118 118 92 85 115 -26% 977 1,080 -10% 93
Tipo

Contratistas 46 53 44 41 53 -24% 432 450 -4% 43

8
Producción – Extracción – Mina Animón
EXTRACCIÓN Sep 17 Acum a Sep
Jun 17 Jul 17 Ago 17 Plan Sep
Mina Animón Real Ppto Var Real Ppto Var
TPD 4,074 4,267 4,381 4,198 4,100 2% 4,201 4,100 2% 4,300
Mineral Extraído

Extrac (000 TM) 122 132 136 126 123 2% 1,147 1,119 2% 129
Zn (%) 5.9 6.4 6.3 5.7 5.9 -4% 6.08 6.08 0% 6.1
Pb (%) 1.3 1.6 1.6 1.7 1.2 34% 1.41 1.26 12% 1.3
Cu (%) 0.2 0.2 0.2 0.2 0.1 77% 0.17 0.14 20% 0.2
Ag (Oz/T) 1.5 1.7 2.2 2.0 1.5 40% 1.64 1.54 6% 1.5
Por Veta (000 TM) 122 132 136 126 123 2% 1,147 1,119 2% 129
V. Andalucia 120 22 33 16 29 7 351% 196 137 44% 31
V. Ram. Piso Lorena 5 8 12 4 6 -22% 42 38 11% -
V. Lourdes 13 13 11 9 1 736% 102 32 218% 3
V. Ram.Piso 3 Principal 10 5 11 15 9 63% 79 146 -46% 14
V. Principal 8 7 19 9 9 4% 89 113 -21% 12
V. Carmen 3 5 - 5 14 -63% 53 168 -68% 4
V. Ofelia 9 6 11 13 - 73 - 13
V. Split Veta Princ. 225 4 3 7 7 - 45 - 5
V. Gisela 7 12 8 3 19 -82% 90 83 9% 15
V. Andalucia 120 Techo 4 6 4 3 0 2006% 37 24 52% 5
Mineral por

V. Split Nw 01 Carmen 11 12 5 6 - 56 32 79% 1


Vetas

V. Karina I 7 5 3 3 18 -83% 22 74 9
V. Janeth Piso - - - - - 21 - -
V. Lorena - - - - 1 -100% - 3 -100% -
V. Janeth 6 3 3 5 16 -71% 51 65 -22% 5
V. Ramal Ofelia Piso 1 - - - 4 -100% 9 37 -76% -
V. Split Janeth 0 4 3 1 - 17 - 4
V. Ram.Piso Carmen - - - - - 6 - -
V. Split Ofelia Piso - - - - - 20 - -
V. Split Maria Rosa 5 2 4 - 4 -100% 12 45 -72% -
V. Elva Piso - - - - 2 -100% 11 50 -77% -
V. Gaby 5 9 - - 35 -
V. Anabel - - - 1 15 -
Otros 1 0 17 12 13 -6% 65 73 -11% 10
Breasting 71 82 90 82 70 18% 679 692 -2% 87
Métodos

Taladros Largos 7 12 7 13 14 -8% 98 124 -21% 17


9 Subniveles 44 39 39 30 39 -22% 371 304 22% 25
Propio 76 79 92 85 70 23% 715 669 7% 86
Tipo

Contratistas 46 53 44 41 53 -24% 432 450 -4% 43


Producción – Extracción – Mina Islay
EXTRACCIÓN Sep 17 Acum a Sep
Jun 17 Jul 17 Ago 17 Plan Sep
Mina Islay Real Ppto Var Real Ppto Var
TPD 1,380 1,242 - - 1,501 -100% 958 1,505 -36% 240
Mineral Extraído

Extrac (000 TM) 41 39 - - 45 -100% 261 411 -36% 7


Zn (%) 1.2 1.1 - - 1.0 -100% 1.3 1.2 4% 0.7
Pb (%) 1.0 0.7 - - 0.5 -100% 0.7 0.6 12% 0.4
Cu (%) 0.1 0.0 - - 0.0 -100% 0.1 0.0 122% 0.0
Ag (Oz/T) 6.7 5.6 - - 6.2 -100% 5.5 5.6 -2% 6.2
Por Veta (000 TM) 41 39 - - 45 -100% 261 411 -36% 7
V. Islay Piso 3 1 - - - 35 35 -1% -
V. Lizeth 2 3 - - - 8 - 1
V. Sur 8 11 - - 33 -100% 64 221 -71% 2
Mineral por

V. Manto Anita 9 6 - - 3 -100% 43 35 24% 1


Vetas

V.Fluorita 9 2 - - - 30 29 4% 1
V.Islay 5 1 - - 9 -100% 39 90 -57% -
M. Escondida - - - - - 16 - -
M. Anita II 1 - - - - 7 - -
V. Victoria 4 6 - - - 10 - -
Otros - - - - - 8 - 1
Otros

Dilución
Sobredilución
Breasting 6 3 - - - 44 - -
Taladros Largos 12 8 - - 23 -100% 71 204 -65% 2
Métodos

OCF - - - - 3 -100% - 10 -100% -


Subniveles 14 23 - - 19 -100% 119 178 -33% 4
Otros 9 6 - - - 28 19 45% 1
Propio 41 39 - - 45 -100% 261 411 -36% 7
Tipo

Contratistas - - - - - - - -

10
Producción – Tratamiento

Sep 17 Acum a Sep 17


Producción Planta Jun 17 Jul 17 Ago 17 Plan Sep
Real Ppto Var Real Ppto Var
Chungar 165,440 165,683 144,327 125,770 168,000 -25% 1,394,341 1,498,160 -7% 136,188
Animón 122,975 126,947 140,402 125,770 123,000 2% 1,134,821 1,095,817 4% 129,000
Tratamiento
Islay en Animón 42,465 38,736 3,925 - 45,000 -100% 258,404 402,343 -36% 7,188
Islay en San Expedito - - - - - 1,116 - -
Zn (%) 4.68 5.09 6.30 5.68 4.62 23% 5.18 4.77 9% 5.81
Pb (%) 1.20 1.42 1.58 1.66 1.05 59% 1.28 1.09 18% 1.21
Leyes
Cu (%) 0.15 0.17 0.20 0.19 0.09 123% 0.15 0.11 37% 0.14
Ag (Oz) 2.86 2.61 2.18 2.05 2.74 -25% 2.35 2.64 -11% 1.71
Zinc (%) 91.3% 92.9% 94.6% 93.9% 90.6% 4% 92.6% 91.4% 1% 92.4%
Plomo (%) 89.5% 90.6% 95.7% 93.6% 86.3% 9% 90.8% 87.2% 4% 89.0%
Recuperaciones
Cobre (%) 64.4% 59.9% 67.1% 72.2% 54.1% 34% 64.7% 57.0% 14% 57.6%
Ag (%) 81.7% 81.5% 82.8% 84.0% 81.8% 3% 81.0% 81.0% 0% 79.2%
Zinc (TMS) 12,870 14,580 15,495 12,144 12,817 -5% 122,897 119,174 3% 13,283
Concentrados
Bulk (TMS) 3,989 4,507 4,241 3,781 3,095 22% 34,740 28,691 21% 2,981
Zinc (TMS) 7,072 7,839 8,603 6,702 7,026 -5% 66,921 65,318 2% 7,309
Plomo (TMS) 1,772 2,130 2,188 1,961 1,520 29% 16,236 14,231 14% 1,468
Finos
Cobre (TMS) 156 172 195 175 78 123% 1,380 956 44% 113
Plata (Oz) 386,698 352,191 260,634 216,309 376,056 -42% 2,649,981 3,203,927 -17% 184,256

11
Producción – Tratamiento – Planta Animón

Sep 17 Acum a Sep 17


Producción Planta Jun 17 Jul 17 Ago 17 Plan Sep
Real Ppto Var Real Ppto Var
Chungar 165,440 165,683 144,327 125,770 168,000 -25% 1,393,224 1,498,160 -7% 136,188
Tratamiento Animón 122,975 126,947 140,402 125,770 123,000 2% 1,134,821 1,095,817 4% 129,000
Islay en Animón 42,465 38,736 3,925 - 45,000 -100% 258,404 402,343 -36% 7,188
Zn (%) 4.68 5.09 6.30 5.68 4.62 23% 5.19 4.77 9% 5.81
Pb (%) 1.20 1.42 1.58 1.66 1.05 59% 1.28 1.09 18% 1.21
Leyes
Cu (%) 0.15 0.17 0.20 0.19 0.09 123% 0.15 0.11 37% 0.14
Ag (Oz) 2.86 2.61 2.18 2.05 2.74 -25% 2.35 2.64 -11% 1.71
Zinc (%) 91.3% 92.9% 94.6% 93.9% 90.6% 4% 92.6% 91.4% 1% 92.4%
Plomo (%) 89.5% 90.6% 95.7% 93.6% 86.3% 9% 90.8% 87.2% 4% 89.0%
Recuperaciones
Cobre (%) 64.4% 59.9% 67.1% 72.2% 54.1% 34% 64.6% 57.0% 14% 57.6%
Ag (%) 81.7% 81.5% 82.8% 84.0% 81.8% 3% 81.0% 81.0% 0% 79.2%
Zinc (TMS) 12,870 14,580 15,495 12,144 12,817 -5% 122,893 119,174 3% 13,283
Concentrados
Bulk (TMS) 3,989 4,507 4,241 3,781 3,095 22% 34,734 28,691 21% 2,981
Zinc (TMS) 7,072 7,839 8,603 6,702 7,026 -5% 66,919 65,318 2% 7,309
Plomo (TMS) 1,772 2,130 2,188 1,961 1,520 29% 16,233 14,231 14% 1,468
Finos
Cobre (TMS) 156 172 195 175 78 123% 1,380 956 44% 113
Plata (Oz)
Sb (TMS) 386,698
- 352,191
- 260,634
- 216,309
- 376,056
- -42% 2,647,004 3,203,927 -17% 184,256

12
Producción – Tratamiento – Planta San
Expedito

Sep 17 Acum a Sep 17


Producción Planta Jun 17 Jul 17 Ago 17 Plan Sep
Real Ppto Var Real Ppto Var

Chungar - - - - - 1,116 - -
Tratamiento
Islay en San Expedito - - - - - 1,116 - -
Zn (%) - - - - - 0.88 - -
Pb (%) - - - - - 0.47 - -
Leyes
Cu (%) - - - - - 0.03 - -
Ag (Oz) - - - - - 3.27 - -
Zinc (%) 0.0% 0.0% 0.0% 0.0% 0.0% 25.7% 0.0% 0.0%
Recuperaciones Plomo (%) 0.0% 0.0% 0.0% 0.0% 0.0% 52.2% 0.0% 0.0%
Ag (%) 0.0% 0.0% 0.0% 0.0% 0.0% 81.6% 0.0% 0.0%

Zinc (TMS) - - - - - 5 - -
Concentrados
Bulk (TMS) - - - - - 6 - -
Zinc (TMS) - - - - - 3 - -
Plomo (TMS) - - - - - 3 - -
Finos
Cobre (TMS) - - - - - 0 - -
Plata (Oz) - - - - - 2,977 - -

13
Costo de Producción e
Inversiones Operativas
Costo total Chungar por naturaleza

CU Chungar Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(USD/TM) Real Ppto Var Real Ppto Var Sep
Mano de Obra 8.5 8.6 8.8 9.6 8.0 1.6 8.6 8.0 0.6 8.3
Suministros 12.7 13.5 13.3 13.9 13.3 0.6 13.5 13.5 0.0 12.9
Energía 1.9 3.2 3.0 2.7 3.0 -0.3 1.9 2.2 -0.3 3.5
Servicios y Otros 31.3 29.9 33.3 35.0 30.4 4.6 31.3 29.9 1.4 31.2
Sub-Total Animón 54.4 55.1 58.3 61.2 54.7 6.5 55.2 53.5 1.7 55.8
Costo de Maquila 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Sub-Total San Expedito 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Costo Total 54.4 55.1 58.3 61.2 54.7 6.5 55.2 53.5 1.7 55.8

Costos Chungar Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(Miles USD) Real Ppto Var Real Ppto Var Sep
Mano de Obra 1,405 1,438 1,240 1,205 1,343 -137 12,032 12,068 -36 1,367
Suministros 2,083 2,281 1,831 1,752 2,238 -487 18,923 20,502 -1,579 2,131
Energía 314 534 429 339 499 -160 2,604 3,271 -667 573
Servicios y Otros 5,134 5,047 4,626 4,402 5,110 -708 43,849 45,388 -1,539 5,140
Sub-Total Animón 8,936 9,301 8,126 7,698 9,190 -1,493 77,409 81,229 -3,820 9,212
Costo de Maquila 0 0 0 0 0 0 20 0 20 0
Sub-Total San Expedito 0 0 0 0 0 0 20 0 20 0
Costo Total 8,936 9,301 8,126 7,698 9,190 -1,493 77,429 81,229 -3,800 9,212

15
Costo total Chungar por área
CU Chungar Sep 17 Acum a Sep Plan
Jun 17 Jul 17 Ago 17
(USD/TM) Real Ppto Var Real Ppto Var Sep
Mina 33.7 32.6 34.1 34.5 33.0 1.6 33.0 32.2 0.8 32.3
Animón 35.4 33.3 33.5 34.5 35.8 -1.3 33.5 34.6 -1.1 34.4
Islay 28.6 30.0 0.0 - 25.2 - 30.8 25.8 5.0 25.8
Planta 3.7 4.4 5.1 4.9 4.4 0.5 4.5 4.6 0.0 4.6
Taller 3.3 3.3 3.5 3.9 3.1 0.9 3.5 3.2 0.3 3.9
Energía 3.3 4.8 4.2 5.2 4.4 0.7 3.5 3.6 -0.2 4.9
Administración y Otros 10.4 10.0 11.5 12.6 9.8 2.8 10.7 9.9 0.8 10.1
Sub-Total Animón 54.4 55.1 58.3 61.2 54.7 6.5 55.2 53.5 1.7 55.8
Costo de Maquila 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Sub-Total San Expedito 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Costo Total 54.4 55.1 58.3 61.2 54.7 6.5 55.2 53.5 1.7 55.8

Costos Chungar Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(Miles USD) Real Ppto Var Real Ppto Var Sep
Mina 5,511 5,565 4,633 4,347 5,538 -1,191 46,457 49,304 -2,847 5,336
Animón 4,325 4,408 4,554 4,350 4,404 -54 38,402 38,700 -298 4,328
Islay 1,186 1,157 79 -3 1,134 -1,136 8,055 10,604 -2,549 1,008
Planta 606 732 730 614 741 -127 6,339 6,838 -499 750.9
Taller 549 549 500 494 513 -19 4,811 4,759 52 646.0
Energía 553 797 611 653 748 -95 4,831 5,448 -617 805.6
Administración y Otros 1,718 1,659 1,653 1,590 1,651 -61 14,970 14,879 91 1,672.8
Sub-Total Animón 8,936 9,301 8,126 7,698 9,190 -1,493 77,409 81,229 -3,820 9,212
Costo de Maquila 0 0 0 0 0 0 20 0 20 0.0
Sub-Total San Expedito 0 0 0 0 0 0 20 0 20 0
Costo Total 8,936 9,301 8,126 7,698 9,190 -1,493 77,429 81,229 -3,800 9,212

16
Costo MinaAnimón por naturaleza

Mina Animón Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(USD/TM) Real Ppto Var Real Ppto Var Sep
Mano de Obra 4.0 3.7 3.6 3.7 3.9 -0.2 3.8 3.8 -0.1 3.7
Suministros 10.4 9.9 9.4 10.1 10.4 -0.3 10.0 10.4 -0.3 9.3
Servicios 20.5 19.3 20.3 20.6 21.2 -0.7 19.4 20.0 -0.6 19.7
Otros 0.5 0.4 0.2 0.2 0.3 -0.1 0.3 0.4 -0.1 0.8
Costo Propio 35.4 33.3 33.5 34.5 35.8 -1.3 33.5 34.6 -1.1 33.6

TME 122,219 132,264 135,797 125,943 123,000 2,943 1,146,930 1,119,300 27,630 129,000

Mina Animón Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(Miles USD) Real Ppto Var Real Ppto Var Sep
Mano de Obra 490 491 483 461 477 -17 4,320 4,291 30 477
Suministros 1,271 1,308 1,281 1,270 1,276 -5 11,513 11,625 -112 1,203
Servicios 2,500 2,557 2,761 2,590 2,611 -21 22,250 22,379 -129 2,544
Otros 64 52 29 29 41 -12 318 405 -87 104
Costo Propio 4,325 4,408 4,554 4,350 4,404 -54 38,402 38,700 -298 4,328

17
Costo MinaAnimón por etapa

Chungar Var Sep - Ago 17 Sep 17


Jun 17 Jul 17 Ago 17
Animón Mano Obra Suministros Servicios Misceláneos Real Mano Obra Suministros Servicios Misceláneos Ppto Var
3.6 9.4 20.3 0.2 Real Sep 17 3.7 10.1 20.6 0.2

Perforación 2.6 2.9 2.5 0.0 0.1 0.1 0.0 2.6 -0.1 -0.1 -1.0 0.0 3.9 -1.2
Voladura 3.2 3.1 3.3 0.0 0.1 -0.5 0.0 2.9 -0.1 0.2 -0.4 0.0 3.2 -0.3
Sostenimiento 10.4 9.8 9.0 0.0 0.4 0.8 0.0 10.2 -0.0 0.6 0.4 0.0 9.3 1.0
Limpieza 3.3 3.1 3.0 0.0 -0.1 -1.0 0.0 2.0 -0.1 0.1 -2.3 0.0 4.2 -2.2
Transporte 2.3 2.1 2.6 0.0 -0.0 -0.1 0.0 2.5 0.0 0.1 -0.2 0.0 2.7 -0.2
Relleno 1.1 0.8 0.9 0.0 -0.1 -0.1 0.0 0.6 0.0 -0.1 -0.3 0.0 1.1 -0.4
Servicios 2.1 2.1 1.5 0.0 0.1 0.9 0.0 2.6 -0.0 -0.3 1.6 0.0 1.3 1.3
Bombeo 1.6 1.9 2.8 0.0 0.0 -0.1 0.0 2.7 -0.0 -0.0 2.5 0.0 0.2 2.5
Supervisión 1.7 1.4 1.3 0.0 0.0 0.1 0.0 1.4 0.1 0.0 0.2 0.2 0.9 0.5
Otros 3.5 3.2 3.7 -0.1 -0.0 -0.1 0.0 3.5 -0.0 -0.4 0.5 0.0 3.5 -0.0
Mantenimiento 3.5 3.0 3.0 0.0 0.3 0.2 0.0 3.5 0.0 -0.3 -1.5 -0.3 5.7 -2.1
Total 35.4 33.3 33.5 0.1 0.7 0.2 0.0 34.5 -0.3 -0.3 -0.7 -0.1 35.8 -1.3
3.7 10.1 20.6 0.2 Ppto Sep 17 3.9 10.4 21.2 0.3

TME 122,219 132,264 135,797 125,943 123,000 2,943

18
Costo Mina Islay por naturaleza

Mina Islay Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(USD/TM) Real Ppto Var Real Ppto Var Sep
Mano de Obra 3.6 4.0 - - 3.4 -3.4 3.8 3.3 0.5 21.3
Suministros 6.0 8.6 - - 7.3 -7.3 8.4 7.4 0.9 39.8
Servicios 18.3 15.7 - - 11.8 -11.8 17.3 12.3 4.9 66.4
Otros 0.7 1.7 - - 2.7 -2.7 1.4 2.7 -1.3 12.8
Costo Propio 28.6 30.0 - - 25.2 -25.2 30.8 25.8 5.0 140.2

TME 41,408 38,510 - - 45,033 -45,033 261,429 410,915 -149,485 7,188

Mina Islay Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(Miles USD) Real Ppto Var Real Ppto Var Sep
Mano de Obra 149 152 3 -2 153 -155 1,000 1,373 -372 153
Suministros 247 333 18 -1 330 -330 2,186 3,058 -872 286
Servicios 759 606 58 0 530 -530 4,513 5,072 -559 477
Otros 30 66 1 0 122 -122 356 1,101 -746 92
Costo Propio 1,186 1,157 79 -3 1,134 -1,136 8,055 10,604 -2,549 1,008

19
Costo Planta Animón

P. Animón Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(USD/TM) Real Ppto Var Real Ppto Var Sep
Mano de Obra 0.7 0.7 0.8 0.9 0.7 0.3 0.7 0.7 0.0 0.9
Suministros 2.6 3.0 3.1 2.9 3.1 -0.2 2.9 3.1 -0.1 2.9
Servicios 0.4 0.7 1.2 1.1 0.7 0.4 0.9 0.8 0.1 1.1
Otros 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Costo Propio 3.7 4.4 5.1 4.9 4.4 0.5 4.6 4.6 0.0 4.9

TMT 165 166 144 126 168 -42 1,393 1,498 -105 166

P. Animón Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(Miles USD) Real Ppto Var Real Ppto Var Sep
Mano de Obra 112 108 116 116 111 5 996 1,006 -9 108
Suministros 424 501 446 364 516 -152 4,078 4,588 -510 501
Servicios 68 122 167 134 114 20 1,262 1,237 26 122
Otros 1 0 0 0 0 0 3 9 -5 0
Costo Propio 606 732 730 614 741 -127 6,339 6,838 -499 732

20 Nota: No incluye costo de la planta San Expedito


Costo Planta San Expedito

P. San Expedito Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(USD/TM) Real Ppto Var Real Ppto Var Sep
Mano de Obra 0.0 0.0 0.0 0.0 0.0 0.0 19.2 0.0 19.2 0.0
Suministros 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Servicios 0.0 0.0 0.0 0.0 0.0 0.0 -1.0 0.0 -1.0 0.0
Otros 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Costo Propio 0.0 0.0 0.0 0.0 0.0 0.0 18.2 0.0 18.2 0.0

TMT 0 0 0 0 0 0 1 0 1 0

P. San Expedito Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(Miles USD) Real Ppto Var Real Ppto Var Sep
Mano de Obra 0 0 0 0 0 0 21 0 21 0
Suministros 0 0 0 0 0 0 0 0 0 0
Servicios 0 0 0 0 0 0 -1 0 -1 0
Otros 0 0 0 0 0 0 0 0 0 0
Costo Propio 0 0 0 0 0 0 20 0 20 0

21
Costo T
alleres Chungar

CU Taller Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(USD/TM) Real Ppto Var Real Ppto Var Sep
Mano de Obra 1.3 1.4 1.4 1.7 1.2 0.5 1.4 1.2 0.1 1.3
Suministros 0.2 0.3 0.3 0.4 0.1 0.3 0.3 0.1 0.1 0.3
Servicios 1.8 1.6 1.8 1.8 1.7 0.1 1.8 1.8 0.0 1.6
Otros 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Costo Propio 3.3 3.3 3.5 3.9 3.1 0.9 3.5 3.2 0.3 3.3

TMT 165 166 144 126 168 -42 1,393 1,498 -105 166

Costos Taller Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(Miles USD) Real Ppto Var Real Ppto Var Sep
Mano de Obra 221 225 203 210 205 5 1,891 1,849 -105 220
Suministros 34 47 38 55 16 38 363 194 0 47
Servicios 292 272 256 228 291 -63 2,543 2,681 0 272
Otros 2 5 2 1 0 1 14 36 0 5
Costo Propio 549 549 500 494 513 -19 4,811 4,759 52 543

22
Costo RRSS Chungar

CU RRSS Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(USD/TM) Real Ppto Var Real Ppto Var Sep
Mano de Obra 0.1 0.2 0.2 0.2 0.1 0.0 0.1 0.1 0.0 0.2
Suministros 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Servicios y Otros 2.1 2.1 2.5 2.8 2.0 0.7 2.2 2.1 0.2 2.1
Costo Propio 2.2 2.3 2.6 2.9 2.2 0.7 2.4 2.2 0.1 2.3

TMT 165 166 144 126 168 -42 1,393 1,498 -105 166

Costos RRSS Sep 17 Acum a Sep Plan


Jun 17 Jul 17 Ago 17
(Miles USD) Real Ppto Var Real Ppto Var Sep
Mano de Obra 23 25 22 23 25 -2 191 220 -29 25
Suministros 1 0 0 1 7 -6 10 60 -50 0
Servicios y Otros 347 348 358 346 341 5 3,075 3,072 3 348
Costo Propio 371 374 380 370 373 -3 3,276 3,352 -76 374

23
Inversiones Operativas
Negocio Minería Septiembre Acumulado 2017
Real / Ppto
Inversiones Operativas Compr
Real Ppto Ejec Var Real Ppto Ejec Var Ppto Ejec Ejec
(Miles USD)
Mina Animón 2,663 1,850 44% 20,272 26,328 -23% 3,180 30,663 66%
Expl. Local 443 159 178% 2,763 3,300 -16% 22.28371 3,511 79%
Desarrollo 1,460 1,196 22% 11,092 14,508 -24% 128 17,973 62%
Mina 617 394 56% 5,735 7,280 -21% 2,258 7,939 72%
Taller 39 - 169 42 301% 144 42 401%
Energía 36 100 -64% 274 1,029 -73% 413 1,029 27%
Areas de Soporte 69 - 135 140 -4% 213 140 96%
Cumplimiento Legal - - 104 29 263% 2 29 363%
Mina Islay 79 1,062 -93% 3,964 10,156 -61% 660 12,010 33%
Expl. Local 5 326 -98% 1,034 3,731 -72% 12 4,273 24%
Desarrollo 3 654 -100% 1,796 4,715 -62% - 5,897 30%
Mina 66 82 -19% 985 1,554 -37% 644 1,684 58%
Energía -0 - 145 151 -4% 4 151 96%
Areas de Soporte 5 - 5 5 -13% - 5 87%
Planta Animón 1,098 337 226% 10,698 6,304 70% 1,820 6,444 166%
Planta 0 337 -100% 356 2,316 -85% 1,085 2,456 14%
Relavera 1,098 - 10,334 3,987 159% 736 3,987 259%
Energía - - 9 - - -
Otros 57 13 314 979 -68% 566 1,012 31%
Energía 0 - 89 416 -79% 304 416 21%
Areas de Soporte 56 13 350% 225 478 -53% 262 510 44%
Total General 3,897 3,261 20% 35,249 43,768 -19% 6,226 50,129 70%

24