Padang Bypass Capacity Expansion

Project
Seminar Hasil Kerja Praktek
Padang bypass capacity expansion
Map project
Harry Malz Harpendi
1310922006
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Data Umum Proyek
• Nama Proyek : Pembangunan Padang Bypass Capacity Expansion Project.

• Lokasi : Kota Padang dan Kabupaten Padang Pariaman, Provinsi Sumatera Barat

• Nilai Kontrak : Rp. 358.291.208.000 (Tiga Ratus Lima Puluh Delapan Milyar Dua Ratus Sembilan
Puluh Satu Juta Dua Ratus Delapan Ribu Rupiah)

• Nilai kontrak konsultan : Rp. 9.560.687.080 (Sembilan Milyar Lima Ratus Enam Puluh Juta Enam
Ratus Delapan Puluh Tujuh Ribu Delapan Puluh Rupiah)

• Kode Proyek : EDCF LOAN No. INA – 17

• Tanggal SPMK : 8 Agustus 2014

• Waktu Pelaksana : 730 Hari Kalender

• Konsultan : Dohwa Engineering co. ltd.; PT. Perentjana Djaja; dan PT. Hasfarm Dian Konsultan

• Kontraktor : Kyeryong Construction Industrial co. ltd.; PT Yala Persada Angkasa. Jo


Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Papan Proyek
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Pemilik Proyek
PPK 12, PELAKSANAAN PRESERVASI DAN
PENINGKATAN KAPASITAS JALAN DAN JEMBATAN
NASIONAL SOLOK DAN SEKITARNYA, DIREKTORAT
JENDRAL BINA MARGA (KEMENTRIAN PEKERJAAN
UMUM DAN PERUMAHAN RAKYAT)
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Organisasi Owner
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Lingkup Pekerjaan
A. Peningkatan Jalan
B. Drainase
C. Jembatan
D. Pelengkap Jalan
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
A. Peningkatan Jalan
Typical Cross Section Sta 00 + 000 – Sta 05 + 000 [Perkerasan Kaku]
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
A. Peningkatan Jalan
Typical Cross Section Sta 05 + 000 – Sta 27 + 000 [Perkerasan Lentur]
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
A. Peningkatan Jalan
Lingkup pekerjaan pada peningkatan jalan:
1. Pekerjaan Galian
2. Pekerjaan Timbunan
3. Pekerjaan Perkerasan Berbutir
4. Pekerjaan Perkerasan
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
1. Pekerjaan Galian
• Pekerjaan Galian adalah pekerjaan yang mencakup penggalian dan pembuangan
tanah. Tanah digali dengan kedalaman tertentu sesuai dengan kondisi tanah
disekitar pembangunan proyek. Penggalian bertujuan untuk membuang lapisan
tanah lunak dan untuk pembuatan drainase.
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
2. Pekerjaan Timbunan
• Pekerjaan Timbunan adalah pekerjaan yang mencakup pengadaan, pengangkutan,
penghamparan, dan pemadatan tanah atau bahan berbutir yang disetujui untuk
pembuatan timbunan. Pekerjaan timbunan bertujuan untuk mencapai elevasi akhir
yang disyaratkan dalam gambar perencanaan.
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
3. Pekerjaan Perkerasan Berbutir
• Perkerasan berbutir meliputi lapisan pondasi bawah (subbase) dan pondasi atas
(base). Untuk pondasi bawah material yang digunakan adalah agregat kelas B dan
pondasi atas agregat kelas A.
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
4. Pekerjaan Perkerasan
• Pada proyek ini, pekerjaan perkerasan ada terbagi 2 jenis, yaitu perkerasan lentur
dan perkerasan kaku. Perkerasan lentur spesifikasi lapis perkerasannya AC (asphalt
concrete) dengan jumlah lapisan terdiri atas 3 lapisan, yaitu AC-WC (4cm), AC-BC
(6cm), dan AC-Base (7,5cm). Perkerasan kaku k-250 dengan tebal lapisan 28 cm.
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Alat yang Digunakan
• Excavator • Vibrator roller
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Alat yang Digunakan
• Motor Grader • Dump Truck
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Alat yang Digunakan
• Concrete Paver • Asphalt Mixing Plant
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Alat yang Digunakan
• Asphalt Finisher • Asphalt Sprayer
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Alat yang Digunakan
• Compressor • Wheel Loader
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Alat yang Digunakan
• Backhoe Loader • Tandem Roller
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Alat yang Digunakan
• Pneumatic Tire Roller • Waterpass
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Alat yang Digunakan
• Water Tank
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Uji Mutu
• DCP (Dynamic Cone Penetrometer) • Sandcone Test
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Uji Mutu
• Uji Sondir • Pemerikasaan suhu campuran aspal
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Uji Mutu
• Core Drill • Ekstraksi
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
Kurva S
• Project : Padang Bypass Capacity Expansion Project • Contract No. : KU.08.08/KTR.06.PPK-12-PJN.II/IV/2014
• Province : West Sumatera • Contract Date : April 29th , 2014
• Owner : Ministry of Public Work and Public Housing(BBPJN II) • Contract Amount : IDR 358.291.208.741,77 (Excl. VAT)
• Contractor : Kyeryong Construction Co.Ltd(JO) - PT.Yala Persada Angkasa • AMENDMENT No.6 : IDR 426.034.029.031,56 (Excl. VAT)
• Consultant : DOHWA Engineering, Co.Ltd in Association With PT. Perentjana Djaya and Dian Konsultan • AMENDMENT No.8 : IDR 436.006.233.313,17 (Excl. VAT)
• AMENDMENT No.9 : IDR 436.006.233.313,17 (Excl. VAT)
• Construction Period : Aug, 08, 2014 ~ Aug. 7, 2016 (730 days)
• Construction Period Amd No.6 : Aug, 08, 2014 ~ Dec. 19, 2016 (864 days)
• Construction Period Amd No.8 : Aug, 08, 2014 ~ Feb. 27, 2017 (934 days)
• Construction Period Amd No.9 : Aug, 08, 2014 ~ May. 29, 2017 (1025 days)
• Fund Sourece : Economic Development Cooperation Fund
CONSTRUCTION SCHEDULE (AMENDMENT NO.9)

2014 2015 2016 2017


Total Price Weight
Pay item Description AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY REMARKS

Rp % 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34

DIVISION 1. GENERAL 4.481.303.500,00 1,03 0,12 0,16 0,22 0,03 0,04 0,04 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 - - - - - - 0,01 0,015 0,01 0,01 0,01 0,01 - - - - 0,02 0,01 0,13

DIVISION 2. DRAINAGE 59.661.148.468,48 13,68 - - - 0,07 0,20 0,39 0,30 0,18 - - - - - 0,07 - - - - - - - 1,83 2,007 1,23 1,80 1,96 1,60 1,09 - - - 0,96 - -

DIVISION 3. EARTHWORKS 73.554.870.780,35 16,87 - 0,09 0,39 0,70 1,07 1,49 1,15 0,96 0,84 1,06 0,84 0,40 - - - ORIGINAL
- - - - - - 1,27 0,970 0,61 1,18 1,52 2,02 0,31 AMENDMENT
- - NO
- 8 - AMENDMENT
- - NO 9

DIVISION 4. PAVEMENT WIDENING AND SHOULDERS 7.192.674.293,10 1,65 - - - - - - - - - - - - - - - - - - - AMENDMENT


- - - NO 6- - - 0,48 0,60 0,55 - - - 0,02 - -

DIVISION 5. GRANULAR PAVEMENT 73.230.167.684,21 16,80 - - - 0,28 0,78 2,55 2,29 2,39 2,44 2,87 0,35 - - - - - - - - - - 1,41 0,576 0,35 0,35 - - - - - - 0,16 - -

DIVISION 6. ASPHALT PAVEMENT 134.292.970.191,93 30,80 - - - - - - 0,40 0,95 1,43 2,25 2,52 2,05 2,26 1,98 0,87 - - - - - - 3,42 2,69 1,33 1,85 1,59 1,85 1,18 - - - 1,08 1,00 0,09

DIVISION 7. STRUCTURES 62.875.973.666,60 14,42 - - - - 0,10 0,30 0,17 0,12 0,02 0,01 0,02 0,33 0,38 0,91 0,92 - - - - - - 3,22 1,532 0,23 0,67 1,27 1,29 0,93 - - - 1,32 0,67 -

DIVISION 8. REINSTATEMENT AND MINOR WORKS 20.119.769.739,87 4,61 - 0,01 0,01 0,00 0,00 0,00 - - - - - - - - - - - - - - - 0,02 0,021 0,01 0,04 0,09 0,02 0,02 - - - 1,72 2,30 0,35

DIVISION 9. DAYWORK 597.354.988,64 0,14 - 0,00 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,01 0,00 - - - - - - 0,01 0,008 0,00 0,01 0,01 0,01 0,01 - - - - - -

TOTAL 436.006.233.313,17 100,00

ORIGINAL PLAN 0,15 0,21 0,44 1,36 2,77 6,11 5,49 5,92 6,02 6,56 4,56 3,98 4,14 4,34 4,50 4,41 4,05 5,03 6,31 5,50 6,29 7,11 4,59 0,12 0,04 - - - - - -

ACCUMULATIVE ORIGINAL PLAN 0 0,15 0,36 0,80 2,16 4,93 11,04 16,54 22,46 28,48 35,04 39,60 43,58 47,72 52,07 56,56 60,98 65,02 70,05 76,36 81,86 88,15 95,25 99,84 99,96 100,00 - - - -

AMENDMENT NO 6 PLAN 0,12 0,27 0,64 1,10 2,21 4,78 4,33 4,62 4,75 6,25 3,88 2,80 2,66 3,01 1,81 - - - - - - 12,71 8,01 4,15 7,86 8,89 9,92 4,62 0,61

ACCUMULATIVE AMENDMENT NO 6 0 0,12 0,39 1,03 2,13 4,34 9,12 13,45 18,07 22,82 29,06 32,94 35,74 38,40 41,41 43,22 43,22 43,22 43,22 43,22 43,22 43,22 55,93 63,94 68,09 75,95 84,85 94,76 99,39 100,00

AMENDMENT NO 8 PLAN 0,12 0,27 0,63 1,10 2,20 4,78 4,32 4,62 4,75 6,21 3,75 2,80 2,66 2,98 1,81 - - - - - - 11,19 7,82 3,69 5,90 6,78 - - 12,41 7,59 1,63

ACCUMULATIVE AMENDMENT NO 8 0 0,12 0,39 1,02 2,11 4,32 9,10 13,42 18,04 22,78 28,99 32,74 35,54 38,20 41,18 42,99 42,99 42,99 42,99 42,99 42,99 42,99 54,18 61,99 65,69 71,59 78,37 78,37 78,37 90,78 98,37 100,00

TECHNICAL JUSTIFICATION PLAN 0,12 0,27 0,63 1,10 2,20 4,78 4,32 4,62 4,75 6,21 3,75 2,80 2,66 2,98 1,81 - - - - - - 11,19 7,82 3,76 5,90 6,93 7,40 4,08 - - - 5,29 3,98 0,56

ACCUMULATIVE TECHNICAL JUSTIFICATION PLAN 0 0,12 0,39 1,02 2,11 4,32 9,10 13,42 18,04 22,78 28,99 32,74 35,54 38,20 41,18 42,99 42,99 42,99 42,99 42,99 42,99 42,99 54,18 61,99 65,76 71,66 78,59 86,00 90,08 90,08 90,08 90,08 95,36 99,34 100,00

#REF! - - -

APPROVED BY, SUBMITTED BY,


PPK - 2.1 CONTRACTOR
PELAKSANAAN PRESERVASI DAN PENINGKATAN KUALITAS KAPASITAS JALAN KYERYONG Construction Industrial Co.,Ltd. (JO) - PT. YALA PERSADA ANGKASA
DAN JEMBATAN NASIONAL SOLOK DAN SEKITARNYA
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
K3
• Watering • Pemasangan Rambu
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
K3
• Memasang Tolo-tolo • Memasang Safety Line
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006
K3
• Peringatan Rambu K3 untuk Pekerja
Terima
Padang bypass capacity expansion
project
Harry Malz Harpendi
1310922006

Kasih