STABILITY ASSESSMENT OF
RESERVIOR WALLS
GAUTAM AGARWALLA
17SE06007
CONTENTS
▪ INTRODUCTION
▪ NEED OF STUDY
▪ OBJECTIVES
▪ BACKGROUND OF THE RESERVOIRS
▪ GROUND INVESTIGATION
▪ OVER ALL DESIGN APPROACH
▪ CONCLUSIONS
▪ REFERENCES
INTRODUCTION
A Reservoir is a place where water is retained by man made structures for the
later use in activities such as:
Agriculture
Hydropower
Fishing
Flood retention
▪ A no. of incident occurred ,causing the concern about the robustness of this system .
▪ According to the 1975 Reservoir Act, the significant advance way to regulate reservoir in
terms of protection from the risk of flooding or dam failure along with the mandatory
periodic inspection of all these assets.
Hence, results in the activation of emergency response procedure i.e. stability assessment.
OBJECTIVE
▪ Static and Seismic stability assessment of the masonry walls using the different
methodology and assumptions &
Reservoirs:
1.Burncrooks reservoir
2.Munnoch reservoir
BACKGROUND OF THE RESERVOIRS
1.BURNCOOKS RESERVIOR:
As no built drawing exists it is believed to be earth filled dam embankment
Assumed dimensions:length-350m ,u/s height-22m ,d/s height -6m.
Masonry faced retaining wall at toe.
As per the preliminary survey
• Lower spillway wall require strengthening &
• Stability of toe wall to be investigated.
2. MUNNOCH RESERVOIR
Earth embankment reservoir
Dimensions: height of-13.5m,overall length 515m,d/s slope 1:2.5
The main section of the embankment is masonry head-wall.
As per the preliminary survey it was recommended to be investigated for
seismic event & to determine if any strengthening work required.
GROUND INVESTIGATION
1. BURNCROOK RESERVIOR
Original superficial deposit were entirely removed to rock head and replaced by fill materials
for reservoir embankment
At toe wall , dense silt sandy gravel with medium cobble & boulder.
At spillway wall , sandy gravelly clay up to 1m b.g.l overlying the sandy gravelly silt with
cobble & boulder contain to rock head.
Ground water behind toe wall within made ground & soil behind spillway to be dry.
2. MUNNOCH RESERVIOR
A desk study of ground condition in vicinity of masonry wall as per BGS
It was found a glacial-till over bed rock.
OVERALL DESIGN APPROACH
Hence, the methodology to evaluate the stability were carried out using above codes.
BURNCROOKS RESERVOIR
OVER ALL ASSUMPTION-:
D/s slope 1(v):2.5(H)
Pore water pressure was considered.
Base friction= (2/3)*internal angle of friction of
foundation stratum
Wall friction= (2/3)*internal angle of friction of
Ground model 1
retained materials
1.Lower spillway wall:
Founded on Engineering bed rock
Ground models were developed using 2 possible
retained heights
Ground model 2
2.Toe wall:
Engineering bed rock.
The material in front of it comprise of ground
materials as per G.I
2 ground models were of different depth were
analyzed.
(for seismic analysis , Type 1 & over estimated GWL Ground model 1
was considered)
Ground model 2
STATIC ANALYSIS
SEISMIC ANALYSIS
1.TOE WALL
• The vertical component of inclined active
pressure is considered for toe wall (hence
MoS just above unity).
2. SPILLWAY WALL
• MoS << 1
needed to be added.
Hence partial replacement of backfill material
▪ Arched headwall,
▪ Base sliding
▪ Passive form soil in front of embedded
depth of wall
▪ Passive from wing wall counterforts
▪ Side friction of wing wall.
▪ Munnoch headwall and wing wall were in compliant with the current standards for both
seismic and static loadings.( How ever slight deviation from EC8 for seismic)
▪ Burncrook’s lower spillway wall required strengthening measure to increase the MoS to
comply with current standards. (Over all wall thickening)
▪ And form structural perspectives ,risk management approach was recommended for the
Munnoch reservoir along with inspection at appropriate intervals.
REFERENCES
Manuel Neves ,MSc ,PhD ,Geotechnical Engineering ,Department of Earth Engineering &
sciences, Fraser Linday ,MEng ,CEng ,MICE ,Senior Geotechnical Engineer, Department of
Rail & Ground Engineering & Chris Holt BSc (Hons) ,CEng ,MICE ,Senior Consultant
,Department of Rail & Ground Engineering (ice Vol 27 issue 3).
THANK YOU
Questions ???
(if any)
GROUND INVESTIGATION
▪ 4 percussion boreholes with in situ SPT behind lower spillway and toe walls
▪ 2 rotary boreholes in rock in front of toe wall
▪ 2 hand dug trail pits behind the top of toe wall
▪ 5 hand dug pits to investigate the rock fill wedge at the rear of the toe wall
▪ Ground water monitoring
▪ Geotechnical and geochemical laboratory testing
▪ 6 horizontally 50 mm die masonry cores through toe walls
▪ 4 inclined 50 mm die masonry cores through toe walls
▪ Results, original superficial deposits were entirely removed to rock head and
replaced with fill materials for embankment.