Weld Map for A Standard Tank

2
General Arrangement view of LSW Work Station

3
Sequence of Welding & Inspection Plan (SWIP)

STAGE-1
1. Set Up the Rolled Plate on the Fixture
2. Clamp the Copper Clamps on the Joint
3. Check the Alignment
4. Verify CTWD, Feed parameters to Welding
machine
5. Start the Welding, the MIG Gun Carriage
Moves on the joint, welding of J1 Takes place
in 1G position
4
Set Up Condition [SUC] for Joint-1 [J1]-Long Seam Welding [LSW]

Steel
fingers

Copper
fingers

Copper Job
Backing

I Beam

5
SUC for J1-LSW – Alt-1

Air Hose

Steel
Fingers

Copper
Fingers

Copper Job
Backing

I Beam

6
SUC for J1-LSW – Alt-1

Air Hose
Steel
Fingers

Copper
Fingers
Copper Job
Backing

I Beam

7
One clamp actuated

8
Both clamps actuated

9
Gun positioned @ start

10
Operator pushes weld start

11
12
13
Welding J1 – Stage-1 Complete

14
Fixture for J2 & J3 - CSW

15
Control Unit Box [CUB] & Remote Operator Pendant

16
Existing Set Up condition for
CSW with CTQLs

17
Proposed Set Up condition for CSW with CTQLs

=15 to 20 mm
Flat Face

Zero Gap

18
Sequence of Welding & Inspection Plan (SWIP)

STAGE-2
1. Assemble the Welded Shell & Both the Caps
2. Set Up & Manually Tack the Joint in the
Sequence the tacks are diagonally each other
3. Mount the Set up on the Fixture
4. Check Run out and Face Out
5. Set CTWD, Welding Parameters
6. Start the Motor, Job Starts rotating on rollers,
welding of J2 takes place in 3F downhill position
7. Follow same sequence for Welding of J3
19
Manual Tacking of J2 & J3

20
Auto Welding of J2

21
Auto Welding of J3

22
Welding of Tank completed