Agenda
• 2nd Carrier Configure MoP Introduction
• 3rd Carrier Activation
• Iub BW & CID Experience Sharing
• Q and A
Expanding to 2nd DUW
• The expanding can be done with a 8U subrack or with a DUx adaptor
• import configuration (cabinet, site & mib)
• Insert 2nd DUW into the expansion (still powered down)
• Make sure the ManagedElementData:: autoConfigurationAllowed is true
• Power up 2nd DUW
• Connect your PC with the serial interface to the 2nd DUW and format both harddrives (c2 & d)
• Connect the IDL cable between both DUWs
(ATTENTION: connect the side with “PRIM” to the 1st DUW and the side with “SEC” to the 2nd
DUW)
• Run the modify script to add the 2nd DUW to the RBS (switch on 2nd DUW if you see “waiting for
start up of board” in the Modify-Wizzard)
• Restart NodeB
• Check the status of the 2nd DUW with EMAS (needs to be enabled)
Cabling
Expanding RBS6000 with 2nd DUW
and RUWs