Anda di halaman 1dari 18

1stQuarter

Solid Waste Management


Focal Persons’ Meeting
February 28, 2018
Provincial Government of Pampanga
Environment and Natural Resources Office
Agenda

1. 10-Year SWM Plans


2. MOA and DOD of Garbage Dump Trucks
3. Drafting of the Provincial SWM Plan
4. Other Matters
10-Year SWM Plans
Approved 10-Year SWM Plans

District LGU NSWMC Resolution No. Date Approved


1st MABALACAT CITY 147 June 30, 2015
2nd GUAGUA 158 August 25, 2015
3rd CITY OF SAN FERNANDO 167 August 25, 2015
2nd SANTA RITA 200 October 27, 2015
4th CANDABA 240 December 11, 2015
4th MINALIN July 26, 2016
For Deliberation at the NSWMC

Approximate No. of
District LGU Date of Submission Submitted to
Working Days
2nd FLORIDABLANCA May 3, 2016 NSWMC 455
2nd LUBAO May 25, 2017 NSWMC 190
Submitted to the NSWMC / EMB R3;
For Review

Approximate No. of
District LGU Date of Submission Submitted to
Working Days
May 2017 NSWMC 206
1st MAGALANG
September 9, 2017 DENR-EMB R3 116
July 20, 2016 NSWMC 400
2nd PORAC May 19, 2017 DENR-EMB R3 194
February 26, 2018 NSWMC 2
2nd SASMUAN June 8, 2017 DENR-EMB R3 180
3rd ARAYAT May 2017 NSWMC 207
3rd BACOLOR May 26, 2017 NSWMC 189
3rd MEXICO March 10, 2017 DENR-EMB R3 241
3rd SANTA ANA May 9, 2017 NSWMC 202
Submitted to the NSWMC / EMB R3;
For Review

Approximate No. of
District LGU Date of Submission Submitted to
Working Days
4th APALIT April 10, 2017 DENR-EMB R3 220
4th MASANTOL March 30, 2017 NSWMC 227
4th SAN LUIS May 8, 2017 NSWMC 203
4th SAN SIMON March 2017 DENR-EMB R3 248
4th SANTO TOMAS August 16, 2017 DENR-EMB R3 132
For Submission

Approximate No. of
District LGU Date of Submission Submitted to
Working Days
4th MACABEBE - - -
Summary

Status No. of LGUs


Approved 6
For Deliberation 2
For Review 12
For Submission 1
TOTAL 21
Status of SWM Plans

1
5%

6
29%

Approved
For Deliberation
For Review
For Submission
12 2
57% 9%
Memorandum of Agreement (MOA) and
Deed of Donation (DOD)
of Garbage Dump Trucks
Completed MOA and DOD

District LGU District LGU


1st MAGALANG CANDABA
FLORIDABLANCA MACABEBE
2nd
PORAC MASANTOL
4th
ARAYAT MINALIN
CITY OF SAN FERNANDO SAN LUIS
3rd
MEXICO SANTO TOMAS
SANTA ANA
For Completion

District LGU Documents for Submission


2nd GUAGUA 4 – MOA, SB Reso MOA, DOD, SB Reso DOD
2nd LUBAO 1 – SB Reso DOD
2nd STA. RITA 1 – SB Reso MOA
2nd SASMUAN 2 – MOA, SB Reso MOA
4th APALIT 2 – MOA, SB Reso MOA
Drafting of the Provincial SWM Plan
Other Matters
Holcim Geocycle Municipal Waste
Acceptance Status

E-mail from Holcim


Geocycle dated
February 27, 2018
Questions?
Dacal pung salamat!