Presentation to Chief Minister Khyber Pakhtunkhwa


Tehsil Level Playgrounds in
Khyber Pakhtunkhwa
Abstract

Number of Play Grounds completed 50
Number of Play Grounds in progress 19
Number of Play Grounds with issues 4
Total No. of Units 76
District Wise Status of Tehsil Playgrounds
D I KHAN DIVISION 
D I Khan Kulachi Completed

Paharpur In progress (Mar 18)

Prova Completed

Daraban Completed

D I Khan Completed

Tank Tank Completed


District Wise Status of Tehsil Playgrounds

BANNU DIVISION

Bannu Domel Completed
Bannu Completed
Laki Marwat Laki Marawat Completed
Serai Norang Completed
District Wise Status of Tehsil Playgrounds

KOHAT DIVISION

Kohat Kohat, Babri Banda Completed
Lachi Completed
Karak Banda Daud Shah Completed
TakhatNasrati Completed
Karak Completed
Hangu Thall In progress (Feb 18)
Hangu Completed
District Wise Status of Tehsil Playgrounds
PESHAWAR DIVISION
Nowshera Nowshera
Jehangira
 Completed
Completed
Pabbi Completed
Charsadda Tangi Completed
Shabqadar Completed
Charsada (TurangZai) Completed
Peshawar Town I Wazir Bagh Court Case
Town II Garhi Baloch Land issue with PHE/WSSP
Town III Wali Abad. Completed
Town IV Mera Kachuri In progress (April 18)
District Wise Status of Tehsil Playgrounds

MARDAN DIVISION

Swabi Topi Completed
ChotaLahor Completed
Rajjar In progress (March 18)
Swabi Approved
Mardan Katlang Completed
TakhtBahi Completed
Mardan at Turu Completed
District Wise Status of Tehsil Playgrounds
MALAKAND DIVISION
Swat Babuzai  Completed
Barikot Completed
Khwazakhela Completed
Matta Sect 4 issued
Kabal Completed
Bahrain Completed
Charbagh Completed
Buner Mandanr Completed
Khadukhel Site changed / Section 4
issued on new site
Daggar College site issue
Gagra School Site issue
Malakand Batekhaila Completed
Dargai In progress (Mar 18)
District Wise Status of Tehsil Playgrounds

MALAKAND DIVISION
Dir Lower Samar bagh Completed
LalQila Completed
Timergarra Completed
Adenzai Completed
Khall New site identified
Munda Completed
Balambat Completed
Dir Upper Warri Site changed CMD
Kalkot Section 4 issued
Dir Upper Approved
Barawal Approved
Chitral Booni/ Mastuj Completed
Chitral Completed
Shangla Alpuri Approved
Puran Approved
Besham Section 4 issued
District Wise Status of Tehsil Playgrounds
HAZARA DIVISION
Abbottabad Havellian 
Abbottabad (Damtour GHS)
Completed
In progress (March 18)
Mansehra Oghi Completed
Balakot (GDC) In process with HED
Mansehra Approved-Court Case
Kohistan Pattan Completed
Palas Land issue (site)
Dassu Land identified
Kandia Land issue (site)
Haripur Ghazi Completed
Haripur Completed
Tor ghar Hssanzai Completed
Judba Award awaited
Battagram Allai Completed
Battagram Approved-Court Case
School Level Playgrounds

Total No of school Playgrounds identified/ 30
found feasible for development on the
criteria of above 10 kanal land
No of school Playgrounds Completed 20

Under process / ongoing 10


SCHOOLS LEVEL PLAYGROUNDS
S.NO DISTRICT NAME OF SCHOOL Physical Progress

1
2
Charsadda
Hangu

Muslim Abad Shakoor
Toghsrai
Completed
Completed
3 Anar China Completed
4 GHS Nandraka Completed
5 Kohat GHS Khadizai Completed
6 GHS Gumbat Completed
7 GHS ToghBala Completed
8 GHS Shahbaz Khel Completed
9 GHS Ghazni Khel Completed
10 LakkiMarwat GHS TajaZai Completed
11 GHS Kot Kashmir Completed
12 GHS Pezu Completed
13 GHS Kherukhel Completed
14 GHS Dallo Khel Completed
15 D I Khan GHSS Kacha Mali Khel Completed
S.NO DISTRICT NAME OF SCHOOL Physical Progress

.
Land Issue Alternate site
16 Karak GHSS Jehangiri
identified
Land Issue Alternate site
17 D.I.Khan GMS Daraban Kalan

18
19 Nowshera

GHSS Pir Pia
GHS Spin Khak
identified
Completed
Completed
20 Nizampur Completed
21 GHSS Balogram Completed
Swat
22 GHS Matta Approved/ Tendered
23 Nowshera Tarujabba Under process
24 GHSS Kabal Under process
25 GMS Malooch Under process
26 Swat GHSS Mingora Under process
27 GHSS Shamozai Under process
28 GHS Nawakalay(B) Under process
29 GHSS baghmaidan Under process
30 Dir Lower GHSS lalqila Under process
31 GHSS rehanpur Under process
OTHER PROJECTS

S# District Facility
1 Peshawar Hayat Abad Sports Complex
2 Abdal Hockey Ground Civil Quarters
3 Reconstruction of Pavillion at Qayyum Stadium
4 Nine Numbers Synthetic Tennis Courts
5 Female indoor Sports Facility at University Town
6 Squash Complex At Peshawar
7 Indoor Sports Facility at NAB Headquartes Peshawar
8 Charsadda Abdul Wali Khan Sports Complex
9 Mardan Badminton Hall at Pirano Park
Other Projects
District 
Facility
10 Swabi Sports Complex at Swabi
11 Playground at Zaida
12 Playground at Kalabat
13 Playground at Pabania
14 Kohat Playground at Siab
15 Playground at Bilitang
16 Playground at Kharmato
17 Hangu Playground at Toghsrai
18 Karak Badminton Hall at Karak
19 Bannu Replacement of Hockey Turf
20 Playground at Mira Khel
Other Projects
District 
Facility
21 Mardan Hockey Turf at Mardan
22 Tank Town Stadium Tank
23 Abbottabad Playground at Khanuspur Ayubia
24 Haripur Indoor Games Hall at Haripur
25 Swat Indoor Games Hall at Makan Bagh Swat
26 Dir Upper Badminton Hall
27 Dir Lower Badminton Hall at Khungi Bala
28 Malakand Playground at Haryan Kot
29 Chitral Polo Ground at Kosht
30 D I Khan Players Hostel at DI Khan