CRITICAL PATH

SCHEDULE

4/26/18
EARLY START

LATE START
ORACLE

PLANNING EARLY
START ORACLE

Primavera SLACK
FORWARD PASS EPS
PASS

Activity types & Relationships


Creating logic in your project

By Er.Nikil Raj…

Copyright © all rights reserved to www.tutomaash.com | any queries can be mailed to tutomaash@gmail.com
1
4/26/18
Activity types

START MILESTONE TASK DEPENDENT LEVEL OF EFFORT


FINISH MILESTONE RESOURCE DEPENDENT WBS SUMMARY

2
Start milestone activities

4/26/18
displays start date

START MILESTONE
Finish milestone activities
FINISH MILESTONE displays finish date

0 DURATION
ACTIVITIES

3
4/26/18
RESOURCE PROJECT
TASK DEPENDENT CALENDAR CALENDAR
RESOURCE DEPENDENT

TASK DEPENDENT ACTIVITY

RESOURCE DEPENDENT ACTIVITY

4
4/26/18
FOUNDATION

30d SUPER STRUCTURE

SS 30d
FINISH WORK
LEVEL OF EFFORT
30d FF
PROJECT MANAGEMENT (LOE)

NOTE 90d
Duration is calculated from its relationships
• Level of effort activities cannot have
constraints assigned to them.

• Level of effort activities are not included


when leveling resources.

5
4TH Floor Roof Slab – 10 day

4/26/18
• Marking - 1day
• Wall reinforcement - 3day
• wall shuttering - 2 day
• Roof slab shuttering - 1 day
WBS SUMMARY • Slab reinforcement - 2 day
• Slab concreting - 1 day
• Total slab duration (WBS summary) – 10 day

WBS Summary Activities


will follow its
WBS Summary duration

6
Relationships

4/26/18
LEAD
ACTIVITY A
FS
FINISH TO START
ACTIVITY A
SS
START TO START
ACTIVITY A FS-1D
ACTIVITY B ACTIVITY B ACTIVITY B

1D
LAG
ACTIVITY A SF
START TO FINISH
ACTIVITY A FF
FINISH TO FINISH
ACTIVITY A FS+1D
ACTIVITY B ACTIVITY B
ACTIVITY B
1D

7
4/26/18
Queries Subscribe us for more videos
We would love to hear from you
Feedback
tutomaash@gmail.com
www.facebook.com/Trainernikhil

Training
www.youtube/Tutomaashcom

Anda mungkin juga menyukai